Russian nuclear power plant built in Hungary delayed for concrete pouring

Thanh Hà |

The foundation pit for the Paks-2 nuclear power plant in Hungary is ready, but the concrete pouring has been delayed.

The foundation pit of the Paks-2 nuclear power plant has been completed in Hungary. However, the ceremony to deploy the first concrete pouring was postponed for technical reasons, TASS reported.

"The foundation pit for the reactor of Plant Team No. 1 has been completed at the Paks-2 construction site. Currently waiting for permission from the Hungarian Atomic Energy Agency to start pouring concrete" - the Russian Embassy in Hungary informed.

The construction of the nuclear power plant in Hungary is being carried out under the project of Russia's state-owned nuclear corporation Rosatom.

TASS reported that the Hungarian nuclear power agency - the project supervisor and licensor for each construction phase - has not yet turned on the green light for the first concrete pouring at the Pak-2 nuclear power plant.

Previously, Hungarian Foreign Minister Peter Szijjarto and Rosatom Alexey Likhachev have repeatedly identified the first concrete pouring as scheduled for the end of March.

However, this plan had to be adjusted after recording cracks in the pit. According to Rosatom, this incident did not affect the technical specifications of the foundation, but the work at the foundation was suspended according to the decision of the Hungarian supervisory authority.

In other areas in the factory construction site, construction activities still take place without any restrictions.

Paks-2 CEO Gergely Jakli said "this event will not affect the future of the nuclear power plant construction project".

The Hungarian Atomic Energy Agency requested a report on additional handling and inspection measures taken regarding cracked soil and rock that have not yet been granted a first-time concrete pouring permit. It is expected that the implementation license will be achieved soon.

The Paks nuclear power plant, built by Soviet experts in the 1980s and using Russian nuclear fuel, provides half of the electricity produced and a third of the electricity consumed in Hungary. Currently, four VVER-440 pressure water reactors are operating at the Paks nuclear power plant, located on the banks of the Danube River, 100 km south of Budapest.

The construction of the second phase of the plant - the 5th and 6th processing groups - is underway. Moscow has confirmed it is ready to finance the Paks-2 project, estimated at 12.5 billion euros, with an expected 80% of the project budget coming from a Russian loan.

According to preliminary calculations, after the two new VVER-1200 reactors are put into operation, the plant's capacity will increase from the current 2,000 megawatt to 4,400 megawatt, thereby increasing the total share of energy generated from Hungary's nuclear reactor to 70%.

Thanh Hà
RELATED NEWS

The future of Russian oil and gas when sanctions are eased

|

Russia's energy trade could change if Western sanctions are eased.

Former customer suffers serious consequences for Russian gas loss

|

Austria recorded the highest wholesale electricity price in the EU in the winter of 2024-2025 due to the loss of Russian gas.

Strong cold air forecast causing bad weather

|

Strong cold air causes unfavorable weather in many sea areas; The Gulf of Tonkin has northeast winds of level 7, sometimes level 8, gusting to level 9 from noon and afternoon of December 13.

The secret to helping Vietnamese karate fighters overcome Thailand

|

Boxer Khuat Hai Nam defeated host Thailand to win the gold medal for Vietnamese karate at the 33rd SEA Games.

Kim Chung CT3 social housing application is paid in large numbers due to lack of salary table photos for the whole company

|

Hanoi - On December 12, many people who came to submit documents at the CT3 Kim Chung social housing project had their documents returned due to the lack of photocopy of the salary table of the whole company.

Lieutenant General Le Van Huong holds the position of Deputy Chief of the General Staff of the People's Army

|

Lieutenant General Le Van Huong - Director of the Department of Military Affairs, General Staff was appointed to the position of Deputy Chief of the General Staff of the Vietnam People's Army.

Strong cold air is about to arrive, the North will have heavy rain, severe cold, some places below 5 degrees Celsius

|

Due to the impact of strong cold air, the mountainous and midland areas of the North will be very cold, with some mountainous areas experiencing severe cold with temperatures below 5 degrees Celsius.

The future of Russian oil and gas when sanctions are eased

Thanh Hà |

Russia's energy trade could change if Western sanctions are eased.

Former customer suffers serious consequences for Russian gas loss

Thanh Hà |

Austria recorded the highest wholesale electricity price in the EU in the winter of 2024-2025 due to the loss of Russian gas.

Russia speaks out about the transfer of Zaporizhzhia nuclear power plant

Thanh Hà |

Zaporizhzhia nuclear power plant remains under Russian control, Moscow said.