Review the solar power project and transfer it to the investigation agency

PHẠM ĐÔNG |

The Deputy Prime Minister requested to review the solar power projects mentioned in the Government Inspectorate's conclusions and transfer them to the investigation agency.

On August 23, at the Government Headquarters, Deputy Prime Minister Tran Hong Ha chaired the third meeting of the State Steering Committee for important national programs, works and projects, and key energy sectors.

According to a report from the Ministry of Industry and Trade, regarding the two LNG thermal power plant projects Nhon Trach 3 and 4, the handover, land leasing and construction infrastructure items have basically been completed.

However, the work of compensation and site clearance for power grid projects to release capacity for LNG Nhon Trach 3 and 4 thermal power plants has been implemented very slowly. In the coming time, EVN and PVN need to soon agree and sign a power purchase agreement (PPA).

The Deputy Prime Minister proposed that Dong Nai province focus on directing and closely coordinating with the Ministry of Natural Resources and Environment to complete site handover for power grid projects to release capacity for LNG Nhon Trach 3 and LNG thermal power plants. 4 by the end of 2024.

For projects in the Quang Trach Power Center, the Quang Trach 1 Thermal Power Plant project has reached 63% but still faces difficulties in site clearance for some items. The Quang Trach 2 Thermal Power Plant project is adjusting its investment policy to convert to using LNG.

Concluding the meeting, Deputy Prime Minister Tran Hong Ha requested that the Ministry of Industry and Trade and localities coordinate with the Ministry of Public Security and relevant agencies to review the solar power projects mentioned in the Inspector's conclusions. Government and turned to investigation agencies.

Classify projects that have no signs of violations or criminal violations, can be remedied according to inspection and examination conclusions... and meet the criteria for system and technology safety transmission, economic efficiency to put into operation.

The Deputy Prime Minister requested to review the solar power projects mentioned in the inspection conclusions. Photo: Minh Khoi
The Deputy Prime Minister requested to review the solar power projects mentioned in the inspection conclusions. Photo: Minh Khoi

For gas thermal power projects, there are problems with the mechanism to determine contract power output (QC), power purchase price... The Deputy Prime Minister requested corporations and businesses to proactively participate with Ministry of Industry and Trade to complete the amendment and promulgate relevant circulars; Prepare documents to report to the Government to submit to the National Assembly for promulgation of a Resolution on mechanisms and policies for gas power projects.

Regarding the pilot project to develop offshore wind power, the Deputy Prime Minister requested that there must be a specific project and model (full export, green fuel production, generation to the national grid), and method. implementation method, thereby determining the "problem" that needs to be solved in terms of legal corridors, surveys, planning... "so that the Prime Minister can approve it so that it can be deployed synchronously and comprehensively." can".

The Deputy Prime Minister assigned the Ministry of Industry and Trade, the Ministry of Planning and Investment, the Ministry of Justice and localities to review and specifically report the number of power projects behind schedule, clarifying "which projects can be handled, which any project that has not been processed yet", proposes to the competent authority to handle it according to the provisions of law.

The Ministry of Industry and Trade urgently researches and develops a project to ensure proactive capacity compensation for power projects that are behind schedule compared to the implementation plan of Electricity Master Plan VIII with solutions and investment decision mechanisms. invest in new power source projects and mobilize additional power sources.

PHẠM ĐÔNG
TIN LIÊN QUAN

154 dự án điện mặt trời được nêu trong kết luận thanh tra

PHẠM ĐÔNG |

Nhiều dự án điện mặt trời do địa phương đề xuất chưa được cập nhật vào kế hoạch là do thuộc danh sách 154 dự án được nêu trong kết luận của Thanh tra Chính phủ.

Được bán tối đa 20% công suất lắp đặt điện mặt trời mái nhà

PHẠM ĐÔNG |

Phó Thủ tướng Chính phủ đề nghị nghiên cứu, thống nhất tỉ lệ bán điện dư của nguồn điện mặt trời mái nhà tự sản, tự tiêu là 20% công suất.

Rà soát dự án điện mặt trời, điện gió đang khắc phục vi phạm

PHẠM ĐÔNG |

Phó Thủ tướng yêu cầu rà soát, cập nhật vào kế hoạch các dự án điện mặt trời, điện gió đã và đang khắc phục những vi phạm, sai phạm theo kết luận thanh tra.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Quảng Ngãi khuyến cáo không ồ ạt trồng cau

VIÊN NGUYỄN |

Giá cau ở Quảng Ngãi đạt mức kỷ lục 80.000 đồng/kg. Tuy nhiên, ngành chức năng khuyến cáo nên đa dạng hóa cây trồng, trong bối cảnh giá cau rất khó lường.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

154 dự án điện mặt trời được nêu trong kết luận thanh tra

PHẠM ĐÔNG |

Nhiều dự án điện mặt trời do địa phương đề xuất chưa được cập nhật vào kế hoạch là do thuộc danh sách 154 dự án được nêu trong kết luận của Thanh tra Chính phủ.

Được bán tối đa 20% công suất lắp đặt điện mặt trời mái nhà

PHẠM ĐÔNG |

Phó Thủ tướng Chính phủ đề nghị nghiên cứu, thống nhất tỉ lệ bán điện dư của nguồn điện mặt trời mái nhà tự sản, tự tiêu là 20% công suất.

Rà soát dự án điện mặt trời, điện gió đang khắc phục vi phạm

PHẠM ĐÔNG |

Phó Thủ tướng yêu cầu rà soát, cập nhật vào kế hoạch các dự án điện mặt trời, điện gió đã và đang khắc phục những vi phạm, sai phạm theo kết luận thanh tra.