Coal conveyor system project from G9 warehouse to Hoa Chat - Mong Duong port (belonging to Mong Duong - Khe Day port cluster) is invested by Cam Pha Port and Warehouse Company - Vinacomin.
The conveyor route has its starting point at the existing TCT2 transmission tower and its ending point at the TCT1 coal receiving tower (new investment) at the surface coal warehouse of Hoa Hoa Port. The conveyor line has a belt width of 1,200mm and a route length of 1,348.3m..., intended to transport commercial coal from G9 warehouse to Hoa Hoa port and transport mixed coal dust at the port to supply to the Mong Thermal Power Plant. Duong 1.
According to the investor's report, following the Group's direction, the investor and the contractor have closely coordinated and focused on implementing project items, and have completed the foundation. , pillars and Tunnel No. 2, Tunnel No. 1... The steel structure has completely installed 4/4 roof floors of TCT1 tower, the assembly of 2 51m ice bridge trusses. Installation of equipment with complete transmission installed at TCT2 tower and electrical cabinet. Installing rollers along a total of 1,348m. However, due to the influence of rainy weather, the concrete pouring at the Tuynel location and equipment installation were slow compared to the planned schedule.
In August 2024, the investor and the contractor will focus on construction, accelerating progress to complete and put into use. Construction work, steel structure installation, and equipment installation will be 100% completed before August 20, 2024. From August 20 - 30, test run without load and with load. It is expected that the acceptance and handover will be completed before August 30 and will be ready to organize the installation of construction signs to celebrate the 30th anniversary of the establishment of Vietnam Coal Corporation (now Vietnam Coal and Mineral Industry Group).
On-site inspection, Deputy General Director of Vinacomin Group Vu Anh Tuan emphasized that this is an important project to meet the needs of coal production and consumption in the context of increased coal demand, ensuring environmental protection. , protecting coal resources, security and order work...
Deputy General Director of Vinacomin Group directed Cam Pha Port and Logistics Company to coordinate with the contractor to urgently carry out related work to maximize the construction progress to ensure acceptance and handover into use. project before August 30. Urge contractors to closely follow the schedule, strive to complete package No. 16 and complete the 72-hour load test before August 30. Implement and develop a test run plan to ensure safe conditions for people and equipment, fire and explosion prevention, environmental sanitation, security and order within the operating scope of the conveyor line.