Accordingly, the notice of conclusion on March 20, 2025 of the Standing Committee of the Provincial Party Committee on the organization of coercive clearance of the Ring Road Project 4 - Hanoi Capital Region, Chairman of the Provincial People's Committee assigned the People's Committee of towns and cities: Thuan Thanh, Que Vo, Bac Ninh to coordinate with departments, agencies: Provincial Police, Construction, Justice, Provincial Inspectorate and relevant tasks, absolute safety and duties, to be able to implement the functions, to be absolutely implemented by the functions, to ensure the functions of the function, to be able to implement the functions, to the function of the function, to be absolutely implemented by the functions and organizations. on security and order and comply with the current law provisions.
During the implementation process, if there are any difficulties or problems, promptly report to the Chairman of the Provincial People's Committee for consideration and decision.
Previously, on the afternoon of March 11, a conference was held to urge the progress of the Ring Road 4 project - Hanoi Capital Region (section through Bac Ninh province).
According to the report of the Bac Ninh Province Traffic and Agricultural Project Management Board, component project 1.3, compensation, support, and site clearance (GPMB) has handed over 364 hectares (reaching 100%) of agricultural land area...
There are about 8.6 hectares of residential land, land sold without authority, and assets on land of 435 households that have not yet been handed over.
Localities have approved compensation plans, are making payments and organizing the dismantling and relocation of assets.
The relocation of all technical infrastructure items is expected to be completed in September 2025.
Regarding resettlement projects, 2 projects have been completed and 8 projects are under construction.
For component project 2.3, 33 construction teams are currently being arranged. The total construction value reached VND627.83 billion (reaching 27.31%).
The project is still facing difficulties with residential land areas, land allocated without authority, contested farm land that has not been handed over with a length of 4.7km; sand material resources are very scarce; some locations of the site have not been relocated due to infrastructure works... directly affecting the project's construction progress.
The Prime Minister requested the project to be completed in 2025
The construction project of Ring Road 4 - Hanoi Capital Region belongs to the group of important national projects, with a total length of 112.8km (including 58.2km through Hanoi, the remaining 9.7km is the route connecting to Hanoi - Ha Long Expressway and the part passing through Hung Yen and Bac Ninh provinces).
The total preliminary investment of the project is 85,813 billion VND.
The Ring Road 4 project of the Capital Region has 35.3km passing through Bac Ninh, including 4 districts and towns: Bac Ninh City, Thuan Thanh Town and Que Vo, Gia Binh District.
Previously, on September 22, during the working program in Bac Ninh, Prime Minister Pham Minh Chinh inspected the progress of the investment project to build the Ring Road 4 - Hanoi Capital Region through Bac Ninh.
The Prime Minister requested that the Ring Road 4 section through Bac Ninh must be completed by the end of 2025.