Vinh Long Chairman urges progress on two key traffic projects in the East

HOÀNG LỘC |

Vinh Long - Vinh Long Chairman requests to accelerate site clearance and construction progress of Ba Lai 6 and Ba Lai 8 bridges to connect inter-regional traffic.

Removing site bottlenecks, promoting construction progress

Grasping information from the investor about the construction progress of two key transport projects, in which Ba Lai 6 bridge has only reached about 22% of the volume, while Ba Lai 8 bridge still faces obstacles in site clearance, Chairman of Vinh Long Provincial People's Committee Tran Tri Quang inspected the reality to promptly remove difficulties and promote implementation progress.

At the site, the Provincial Traffic Project Management Board and construction units reported on the implementation progress, capital disbursement situation, site clearance work as well as difficulties arising during the project implementation.

According to reports, Ba Lai 8 bridge has a total investment of 2,255 billion VND, currently implementing 3 construction packages. Of which, package XL02 reached about 62% of the volume, package XL01 reached 34% and package XL03 reached about 30%. Accumulated disbursement reached about 901.2 billion VND, equivalent to 54% of the allocated capital plan.

Nhiều hạng mục của cầu Ba Lai 8 đang được triển khai đồng loạt. Ảnh: Hoàng Lộc
Many items of Ba Lai 8 bridge are being deployed simultaneously. Photo: Hoang Loc

Site clearance work in Bao Thanh commune basically meets construction requirements. In Thanh Phuoc commune alone, site clearance has been handed over to 86/97 households, and 11 households related to forest land are completing compensation procedures to soon hand over to the construction unit.

For Ba Lai 6 bridge, the overall progress is currently about 22%. The contractor is focusing on constructing drilled piles for the main pillars. The project has disbursed more than 58.1 billion VND, reaching about 43% of the allocated capital plan. According to the investor, early removal of site obstacles will create conditions to accelerate construction, ensuring the completion of the set progress milestones.

Decisively handle the site, accelerate construction

After listening to the report and actual inspection, Chairman of the Provincial People's Committee Tran Tri Quang requested localities to focus on accelerating compensation, support and site clearance, urgently handing over clean ground to the construction unit, and not allowing prolonged problems to affect the progress of the two projects.

For cases that are still facing difficulties in compensation work, the Chairman of the Provincial People's Committee assigned the Department of Agriculture and Environment to urgently guide handling in accordance with regulations, ensuring the legitimate rights of the people. In case consensus is not reached, relevant units should proactively develop construction protection plans according to the provisions of law.

The Provincial Traffic Project Management Board is assigned to coordinate with the Department of Finance to review and advise on plans to implement additional items using contingency funds; and at the same time continue to coordinate with localities to strengthen mobilization of households that still have problems, and thoroughly handle cases where land has not been handed over.

Cầu Ba Lai 6 đang thi công cọc khoan nhồi các trụ chính. Ảnh: Hoàng Lộc
Ba Lai 6 bridge is under construction of drilled piles for the main pillars. Photo: Hoang Loc

The Chairman of the Provincial People's Committee also requested the investor and contractors to mobilize maximum manpower and equipment, organize scientific construction, and synchronously deploy solutions to compensate for progress; in which, construction is also carried out at night when conditions are met, striving to soon close Ba Lai 8 bridge and accelerate the progress of Ba Lai 6 bridge.

Provincial leaders emphasized that units must regularly review the progress of each item, proactively handle arising difficulties, strengthen coordination between investors, localities and contractors, and be determined to complete Ba Lai 6 bridge and Ba Lai 8 bridge according to the plan, ensuring project quality and efficiency in using public investment capital.

HOÀNG LỘC
RELATED NEWS

Ba Lai 6 bridge is waiting to untie the site bottleneck to accelerate towards the finish line

|

Vinh Long - Ba Lai 6 Bridge still has two households that have not agreed on crop compensation, creating bottlenecks before the goal of accelerating project completion.

Vinh Long Chairman directs intervention to protect the bird garden of an 80-year-old farmer

|

Vinh Long - Chairman of Vinh Long Provincial People's Committee directs functional sectors to urgently inspect and handle the situation of bird hunting in the bird garden of an 80-year-old farmer.

Vinh Long Chairman directs handling of stagnant waste case reported by Lao Dong Newspaper

|

Vinh Long - After Lao Dong Newspaper's reflection on the situation of garbage accumulation in Tra Vinh, the Chairman of the Provincial People's Committee directed the locality to intervene and thoroughly handle it.

Workers hope for wage increase and price restraint

|

Hanoi - Workers are excited when the regional minimum wage for 2027 is proposed to increase by 7.8%, but also hope to restrain the price increase of essential goods.

Parking lot fire in Nam Nha Trang, many cars burned down in the night

|

Khanh Hoa - A fire occurred at a parking lot in Nam Nha Trang ward at night, causing damage to many cars.

Ba Lai 6 bridge is waiting to untie the site bottleneck to accelerate towards the finish line

HOÀNG LỘC |

Vinh Long - Ba Lai 6 Bridge still has two households that have not agreed on crop compensation, creating bottlenecks before the goal of accelerating project completion.

Vinh Long Chairman directs intervention to protect the bird garden of an 80-year-old farmer

HOÀNG LỘC |

Vinh Long - Chairman of Vinh Long Provincial People's Committee directs functional sectors to urgently inspect and handle the situation of bird hunting in the bird garden of an 80-year-old farmer.

Vinh Long Chairman directs handling of stagnant waste case reported by Lao Dong Newspaper

HOÀNG LỘC |

Vinh Long - After Lao Dong Newspaper's reflection on the situation of garbage accumulation in Tra Vinh, the Chairman of the Provincial People's Committee directed the locality to intervene and thoroughly handle it.