On July 18, talking to reporters, Mr. Tran Van Hau - Chief Inspector of Thai Nguyen Province said that this unit has issued the Inspection Conclusion of the Da Thien Cultural Ecotourism Area project (Trai Cau town, District 1). Dong Hy) invested by Thien Phuc Fine Arts Construction Company Limited (Thien Phuc Company).
According to Mr. Hau, the inspection conclusions pointed out many violations of construction, land and environment at the Da Thien Cultural Ecotourism Area project. In addition, Thien Phuc Company was also required to refund nearly 3 billion VND in merit money received improperly.
"Concluding the inspection, the branches are currently directing implementation. As for the amount of merit money received that is not in accordance with regulations, we are requesting a report to see how the business is performing," Mr. Hau informed.
Previously, Inspection Conclusion No. 05 dated June 19, 2024, Thai Nguyen Provincial Inspectorate clearly pointed out that Da Thien Temple is a religious facility under common ownership of the community, assigning Thien Phuc Company to implement the tourist area project. Da Thien cultural ecological calendar is not in accordance with the provisions of the Land Law.
During the construction process, some construction items are not in accordance with the construction permit, some even do not have a construction permit, and are not included in the approved basic design. Some construction projects are built on land areas that have not been fully allocated by the People's Committee of Thai Nguyen province.
In particular, Thien Phuc Company constructed a number of projects that directly affected and caused difficulties to production and daily life of some households, affecting roads and agricultural land, causing People were angry and gathered to protest.
As Lao Dong reported, at the end of July 2023, people living around the Da Thien Tourist Area project gathered to protest Thien Phuc Company's arbitrarily setting up barricades and fences on the concrete road for people to live in. connected to the project, making it impossible for people to travel into the production forest land.
Also at this project site, in mid-2023, a 10-year-old boy died due to falling into a large underground area filled with water that was under construction but was not covered or had warning signs or was separated from the outside. .
Dong Hy District People's Committee has decided to fine investors more than 100 million VND for building projects not according to planning, some project items and investors causing flooding, environmental pollution, and unsafety. At the same time, request this business to thoroughly fix it.
On August 22, 2023, the Chief Inspector of Thai Nguyen province issued decision No. 125 on the inspection of the Da Thien cultural eco-tourism area project. This is an unscheduled inspection and not a regularly scheduled inspection. The purpose is to clarify the existing problems of this project.