The unfinished resettlement project caused severe flooding in residential areas in Ha Long

Đoàn Hưng |

For nearly 2 years, some households in group 3, area 5, Gieng Day ward, Ha Long city, Quang Ninh province have been struggling to find ways to cope with floods from the adjacent resettlement area. comes down every time it rains heavily.

Flooding from unfinished resettlement project

Residential and resettlement technical infrastructure project in area 5, Gieng Day ward, approved by Ha Long City People's Committee in Decision No. 15337/QD-UBND dated December 18, 2020; Project adjustment in Decision No. 4874/QD-UBND dated December 29, 2022, project implementation period until the end of 2023. Area scale is 4.78 hectares with the nature of a new residential area with synchronous technical infrastructure. of 216 plots of land for resettlement. Although unfinished, the project has suspended all construction activities for 2 years.

Taking reporters to see the seepage marks on the wall, the remaining consequences of the flood on June 8 - 9, 2024, Mr. Hoang Hong Thiep, group 3, area 5, Gieng Day ward - was bored: "Heavy rain, the road This Can team has water flowing like a river, flooded 50-60cm along with soil and gravel from the project flowing down. During the recent rain, the family damaged a refrigerator worth 7 million VND and a water purifier worth nearly 6 million VND due to water flooding into the house.

Mr. Tran Van Nghien, 90 years old, group 3, area 5 said: "I have been here since 1960 but have never been flooded like the last two years, turning family life upside down. The family's main source of income comes from a boarding house with more than 20 rooms, each room rented for 600,000 - 700,000 VND/month. Yet now there are only a few rooms with guests, every time it rains it floods up to the foot of the bed, no one dares to rent."

Talking to reporters, Mr. Le Van Chuyen - Secretary, Head of Area 5, Gieng Day Ward, Ha Long City - said: "For every heavy rain, about 5 households and nearly 20 rooms are flooded. In 2023 alone, there will be 13 rains, 8 severe floods, and one time a car stalled in the middle of the road; From the beginning of 2024 until now, there have been 3 heavy rains, the heaviest one was on June 8 - 9, causing flooding in some households.

Construction on this resettlement project has stopped since 2023, leaving only a small part to handle flooding. Households have also built ditches in front of their doors and gates, but that's only partially overcome. When it rains heavily, water still enters the house."

The clay yard has not been able to be moved to another place for more than a year to have space for the resettlement project. Photo: Doan Hung
The clay yard has not been able to be moved to another place for more than a year to have space for the resettlement project. Photo: Doan Hung

Temporary solution

According to research, the Residential Area Technical Infrastructure project in Area 5, Gieng Day Ward is invested by the Construction Investment Project Management Board of Ha Long City. The contractor is Lung Lo 2 Construction Joint Stock Company.

During the project implementation process, a large volume of soil suspected to be clay was discovered. The Ward People's Committee and the Project Management Board made a written report to the city asking for opinions on how to handle it, but up to now the large volume of land revealed has not been discovered yet. was transported out of the resettlement area to construct the next items, leading to the project's temporary suspension of construction. Construction items were not synchronized, leading to heavy rains and many households were flooded.

Mr. Luu Van Binh - Vice Chairman of the People's Committee of Gieng Day Ward, Ha Long City - said: "The previous status of the resettlement project was clay mining. When it rains, part of the water is stored in the moong, the rest drains evenly around. When implementing this project, the slope flows to Doi Can street, group 3, area 5, Gieng Day ward.

Every time it rains, we are also very impatient, coordinating with the construction unit, project management board, and being on duty with excavators and cars to dredge sewers, but unexpected heavy rains are often too late to keep up. Doi Can is the main road of area 5, each time it floods, it affects hundreds of households.

The immediate solution that the government and construction units have been implementing is to surround the exposed mountain of soil to prevent it from spilling into residential areas. On the route from the resettlement area to Doi Can street, sandbags have been arranged to prevent mud and mud and water is distributed into the sewer, and the sewer line is regularly dredged."

These are only temporary solutions, what people wonder is when will the flooding situation in the area be completely resolved?

Đoàn Hưng
TIN LIÊN QUAN

Quy định mới nhất về bồi thường, tái định cư khi Nhà nước thu hồi đất

Như Hạ |

Chính phủ ban hành Nghị định số 88/2024/NĐ-CP ngày 13.7.2024 quy định về bồi thường, hỗ trợ, tái định cư khi Nhà nước thu hồi đất.

Nghịch lí nhà tái định cư bỏ hoang trên "đất vàng", người dân khát nhà ở giá rẻ

Tuyết Lan |

Trong bối cảnh người dân thiếu nhà ở giá rẻ, khó tiếp cận nhà ở xã hội, phương án chuyển đổi nhà tái định cư bỏ hoang sang nhà ở xã hội được coi là giải pháp thiết thực giúp tăng nguồn cung nhà ở, tạo cơ hội an cư cho người dân.

Khu tái định cư ở Cần Thơ hơn 10 năm chờ điện, nước sạch

Yến Phương - Tạ Quang |

Người dân sinh sống tại khu tái định cư thuộc quận Cái Răng, TP Cần Thơ tha thiết mong chính quyền các cấp quan tâm đầu tư hoàn thiện cơ sở hạ tầng, điện, nước…

Người dân Hà Nội chen chân trên phố Hàng Mã chơi Trung thu

NHÓM PV |

Tối 16.9 (tức 14.8 Âm lịch), hàng ngàn người dân đổ về khu vực phố Hàng Mã (Hoàn Kiếm, Hà Nội) để vui chơi Trung thu khiến tuyến phố trở nên ùn tắc.

Kịch bản đường đi khi áp thấp nhiệt đới mạnh lên bão số 4

AN AN |

Đại diện cơ quan khí tượng nhận định áp thấp nhiệt đới có thể mạnh thành bão số 4 và khả năng tác động đất liền nước ta.

Tạm giữ lái xe ô tô cán học sinh tử vong trong sân trường

BẢO TRUNG |

Đắk Lắk - Cơ quan chức năng đã tạm giữ hình sự người lái xe ô tô bán tải cán tử vong em học sinh lớp 2 ngay trong sân trường.

Lô đất trúng đấu giá hơn 100 triệu đồng/m2 ở Hà Nội bị bỏ cọc

CAO NGUYÊN |

Dù đã hết thời gian nộp tiền nhưng đến nay lô đất có giá trúng đấu giá hơn 100 triệu đồng/m2 ở huyện Thanh Oai (Hà Nội) vẫn chưa đóng tiền.

Hà Nội tắc đường cả cây số, người dân ì ạch di chuyển

Nhóm PV |

Tối 16.9, nhiều tuyến đường tại Hà Nội tắc cứng do giờ tan tầm và lượng người đổ ra đường đi chơi Trung thu.