On June 28, a representative of the Bao Loc Pass Traffic Police Team, Lam Dong Provincial Police, said that during the two weekends (Saturday and Sunday) during peak times with a lot of traffic on National Highway 20.
Meanwhile, the construction of a level crossing at this time for vehicles traveling only in one direction is unreasonable. This has led to overload, causing traffic congestion on National Highway 20 and Bao Loc Pass.

Therefore, the Traffic Police force worked with the construction unit, analyzed, assessed the situation and agreed to temporarily suspend the construction of the project to prevent congestion and ensure smooth traffic.
From 1:30 p.m. on June 28, the sewer construction unit on National Highway 20, the section through B'Lao cre intersection (Dai Lao commune, Bao Loc city) has leveled the road surface and stopped all construction work.

After about 30 minutes of leveling and returning the road, by 2:00 p.m. the same day, the congested and congested vehicles on National Highway 20 and Bao Loc Pass were traveling in both directions again.
With reasonable regulation and diversion, hundreds of vehicles were congested and jammed on National Highway 20 and Bao Loc Pass and were quickly cleared.

At around 3:00 p.m. the same day, traffic was moving back and forth on Bao Loc Pass and the section passing through the culvert across National Highway 20, although it was still moving slowly, but it was basically guaranteed smoothness. Accordingly, the congestion and congestion in the cross-culverage area is gradually being cleared.
In the immediate future, the construction will be temporarily suspended from now until the end of Sunday, June 29. During this time, the construction unit will specifically assess and report to Road Management Area IV.1 on issues related to the construction of cross-culverts and traffic on National Highway 20.

From there, there will be an optimal plan for time, regulation, and flow to effectively construct, limiting traffic congestion.
Previously, Lao Dong Newspaper reported that from early this morning, traffic on National Highway 20 through Dai Lao and Loc Chau communes (Bao Loc city) has only been traveling in one direction.
Hundreds of vehicles traveling from Da Lat to Ho Chi Minh City lined up, waiting for a long traffic jam of about 4km from B'Lao cre intersection (Dai Lao commune), where the repair of the cross-culverts on National Highway 20 to the center of Loc Chau commune is underway.