6-lane road to relieve traffic jam in Thu Duc "froze" for 4 years

MINH QUÂN |

HCMC - The 6-lane road of Ring Road 2 through Thu Duc City has been "frozen" for more than 4 years. Although the project was extended to 2026 for completion, it has not yet restarted.

On October 24, the construction site of the road connecting Pham Van Dong Avenue to Go Dua intersection, Thu Duc City, was quiet. This is the third of four sections of the unfinished Ho Chi Minh City Ring Road 2, which has been suspended since 2020.

Unfinished projects are covered with weeds and become abandoned after a long period of stagnation, while many spontaneous shortcuts have appeared around the area, serving the travel needs of local people.

Cong truong Vanh dai 2 hoang phe sau 4 nam dung thi cong.  Anh: Minh Quan
The Ring Road 2 construction site through Thu Duc City is deserted after 4 years of stopping construction. Photo: Minh Quan

The project started in 2017 with a total investment of more than 2,700 billion VND in the form of BT (build - transfer), with Van Phu Bac Ai Joint Stock Company as the investor.

The project is over 2.7km long, with a land clearance scale of 67m wide and construction of two parallel roads with 3 lanes on each side, the land in the middle is reserved for future implementation items.

According to the original plan, this road section was expected to be completed in 2020, helping to connect the two main axes of Pham Van Dong and National Highway 1, significantly reducing the distance having to go around routes such as Linh Dong and National Highway 13.

However, since March 2020, the project has been stalled due to problems in site clearance and land fund payment to investors.

At the end of January 2024, the Ho Chi Minh City People's Committee decided to postpone the project completion deadline until 2026.

Mat bang Vanh dai 2 doan giap duong Pham Van Dong da ban giao.  Anh: Minh Quan
Beltway 2 site plan, section adjacent to Pham Van Dong Street. Photo: Minh Quan

According to a report by Van Phu Bac Ai Company, the prolonged payment procedures have caused the project’s bank loan interest to increase to more than 600 billion VND, putting great pressure on investors. The company is currently paying more than 14 billion VND in interest each month, causing the total cost of the project to increase and causing damage to the budget.

The Ho Chi Minh City People's Committee has directed departments and branches to review procedures for negotiating and signing an appendix to adjust the BT contract, and at the same time develop a payment process for investors to remove difficulties and restart the project.

According to the latest report of the Ho Chi Minh City Department of Transport, the actual value of the project as confirmed by the State Audit as of August 31, 2019 was 1,272.8 billion VND, including 372 billion VND in construction costs and more than 900 billion VND in compensation, support and resettlement costs.

The interdisciplinary working group in charge of the project met and agreed to recommend that in the immediate future, it may consider paying the audited construction value, in order to reduce costs arising from loan interest and support businesses to overcome difficulties.

Cong truong Vanh dai 2 (tu Pham Van Dong den cau vuot Go Dua dinh tre thoi gian dai.  Anh: Minh Quan
The construction site of Ring Road 2 (from Pham Van Dong to Go Dua overpass) has been stalled for a long time. Photo: Minh Quan

Regarding the payment land fund, the Department of Natural Resources and Environment of Ho Chi Minh City is reviewing and proposing payment land areas for investors.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board, the site handover will be completed in December 2024 and the project can restart in early 2025.

If everything goes according to plan, this 6-lane road will be completed in 2026, playing an important role in relieving traffic pressure for Thu Duc City area, contributing to closing Ho Chi Minh City Ring Road 2.

MINH QUÂN
RELATED NEWS

Thu Duc reclaims land from 1,151 households to build Ho Chi Minh City Ring Road 2

|

HCMC - This year, Thu Duc City will spend nearly 7,600 billion VND to compensate and clear land of 1,151 households to serve the Beltway 2 project.

4-level intersection to be built on Pham Van Dong Avenue in Thu Duc

|

HCMC - The Pham Van Dong intersection with Ring Road 2 in Thu Duc City will be designed with 4 floors, including an underpass and three overpasses.

HCMC builds 5 bridges larger than VND175,000 billion, ending ferry problems

|

Ho Chi Minh City is about to build a road and a sea overpass connecting Can Gio - Vung Tau, Can Gio bridge, Cat Lai bridge, Phu My 2 bridge, Dong Nai 2 bridge, with a total investment of about 175,000 billion VND.

Fishing boat sinks, 4 fishermen saved

|

Quang Tri - 4 fishermen in distress when their fishing boat sank at sea near Hon La Island were rescued safely.

After the severe flood, Lam Dong farmers struggle to restore dragon fruit gardens

|

Lam Dong - After the floodwaters receded, many farmers began their journey to restore their dragon fruit gardens.

Tropical depression level 8 is about to enter the East Sea, latest forecast of path

|

According to the meteorological agency, the tropical depression is forecast to maintain the intensity of level 6 gusting to level 8 in the next 24 to 48 hours.

Da Nang bustling Christmas market

|

Da Nang - Entering its third year, Danang Christmas Market 2025 continues to prove its appeal by attracting a large number of people and tourists.

Ecohome Nhon Binh residents are miserable due to prolonged power outages and water shortages after floods

|

Gia Lai - The flood has receded for half a month, more than 1,000 residents of Ecohome Nhon Binh Apartment Building are still struggling with power outages and prolonged water shortages, disrupting their lives.

Thu Duc reclaims land from 1,151 households to build Ho Chi Minh City Ring Road 2

MINH QUÂN |

HCMC - This year, Thu Duc City will spend nearly 7,600 billion VND to compensate and clear land of 1,151 households to serve the Beltway 2 project.

4-level intersection to be built on Pham Van Dong Avenue in Thu Duc

MINH QUÂN |

HCMC - The Pham Van Dong intersection with Ring Road 2 in Thu Duc City will be designed with 4 floors, including an underpass and three overpasses.

Dự án Vành đai 2 TPHCM lận đận 16 năm vẫn chưa khép kín

MINH QUÂN |

TPHCM - Dự án đường Vành đai 2 TPHCM được quy hoạch từ năm 2007 với tổng chiều dài 64km có vai trò quan trọng giúp phân luồng, giảm áp lực giao thông nội đô. Tuy nhiên, cho đến nay, đường Vành đai 2 hiện vẫn còn 14 km (chia làm 4 đoạn) chưa được khép kín.