Thu Duc reclaims land from 1,151 households to build Ho Chi Minh City Ring Road 2

MINH QUÂN |

HCMC - This year, Thu Duc City will spend nearly 7,600 billion VND to compensate and clear land of 1,151 households to serve the Beltway 2 project.

According to the latest report from the Thu Duc City People's Committee, two sections of the Ring Road 2 project need land acquisition with a total of 1,151 households affected.

Section 1 from Phu Huu Bridge to Vo Nguyen Giap Street, over 3.5km long, has 893 households whose land will be recovered. The public investment capital allocated in 2024 to clear the land for this section is 5,825 billion VND.

Section 2 from Vo Nguyen Giap Street to Pham Van Dong Street, nearly 2.5km long, with 258 households affected. The public investment capital allocated in 2024 for site clearance is 1,742 billion VND.

Thu Duc City People's Committee has directed relevant units to urgently complete compensation procedures and resettlement support for affected households. Up to now, procedures such as mapping the current status, locating and planting landmarks, and handing over land boundaries in the field have been completed.

Currently, Thu Duc City is continuing to confirm the legal status of real estate, conduct inventory and land valuation to speed up disbursement progress.

For resettlement needs, Thu Duc City needs to arrange 555 plots of land and 58 apartments for households in section 1 and 102 plots of land and 10 apartments for section 2.

Huong duong Vanh dai 2 tu duong Vo Nguyen Giap den duong Pham Van Dong.  Anh: Anh Tu
Direction of Ring Road 2 from Vo Nguyen Giap Street to Pham Van Dong Street. Photo: Anh Tu

To ensure the progress of public investment disbursement this year, the People's Committee of Thu Duc City has proposed that the People's Committee of Ho Chi Minh City allow the review of public land funds along Ring Road 2 to adjust the planning and create resettlement land funds for affected households.

The goal is to ensure resettlement as close to the clearance area as possible, helping people quickly stabilize their lives after their land is acquired.

Thu Duc City People's Committee commits to resettle eligible households with land and apartments.

However, to meet the demand for land, Thu Duc City proposed that the Ho Chi Minh City People's Committee promptly hand over two plots of land at 118 Dang Van Bi, Binh Tho Ward and 15/6C Dang Van Bi, Truong Tho Ward.

These are lands that have been recovered from Sanofi-Synthelabo Vietnam Pharmaceutical Joint Stock Company, currently being considered for use in resettlement of the Ring Road 2 project and other key projects in Thu Duc City.

According to the plan, the land at 118 Dang Van Bi, Binh Tho ward, can provide from 32 to 47 resettlement plots, while the land at 15/6C Dang Van Bi, Truong Tho ward, is expected to provide from 55 to 83 plots.

The Ho Chi Minh City Traffic Construction Investment Project Management Board (investor) said that if the site is handed over by Thu Duc City on schedule, these two sections of Ring Road 2 will start construction in the second quarter of 2025 and be completed in 2027.

Ho Chi Minh City Ring Road 2 has a total length of 64km, of which 50km has been completed and put into use, the remaining 14km has not been closed, divided into 4 sections.

Besides the two sections being implemented in Thu Duc City, section 3, over 2.7 km long from Pham Van Dong Street to Go Dua intersection, also in Thu Duc City, is being implemented under the BT (build-transfer) form but is still unfinished.

The final section (section 4) is 5.3km long, located in the South of Ho Chi Minh City, connecting National Highway 1 through Nguyen Van Linh Street, and has not yet been allocated investment capital for construction.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City builds 7,000 billion VND, 50,000-seat stadium in Thu Duc

|

HCMC - Project of a 50,000-seat stadium, integrated with an athletics track, with an investment capital of 7,000 billion VND at Rach Chiec Sports Complex (Thu Duc City).

Ho Chi Minh City will change the design of the 2km long bridge connecting Thu Duc and District 7

|

Ho Chi Minh City is adjusting the plan to build Thu Thiem 4 bridge connecting Thu Duc and District 7, more than 2km long, after Nha Rong - Khanh Hoi Port built an international passenger ship port.

It is expected that in April 2026, the National Assembly will decide on personnel work

|

The 1st Session of the 16th National Assembly is expected to open on April 6, 2026. In which, the National Assembly will spend time on organization and personnel work.

Experience making Christmas pine trees from fruit, priced at millions of VND still attracts customers

|

Despite the price of more than 1 million VND, the experience of making Christmas trees from fruit still attracts a large number of participants during the Christmas season.

Bustling Christmas atmosphere around the world

|

The Christmas 2025 atmosphere has been bustling in many countries around the world, with streets, churches, and shopping malls decorated brilliantly.

Fire at a group of children in Da Lat, rescue forces promptly controlled

|

Lam Dong - The fire broke out at the Nhan Dao Youth Group of the Society of the Holy Mother in village 3, Cam Ly ward - Da Lat.

Ring Road 3 is about to limit a series of vehicles during rush hour, people hope to escape congestion

|

Hanoi - The Department of Construction will pilot the limitation of cars with a load capacity of over 10 tons from Thang Long Avenue, National Highway 32 to the elevated Ring Road 3 from January 1, 2026.

Ho Chi Minh City builds 7,000 billion VND, 50,000-seat stadium in Thu Duc

MINH QUÂN |

HCMC - Project of a 50,000-seat stadium, integrated with an athletics track, with an investment capital of 7,000 billion VND at Rach Chiec Sports Complex (Thu Duc City).

Ho Chi Minh City will change the design of the 2km long bridge connecting Thu Duc and District 7

MINH QUÂN |

Ho Chi Minh City is adjusting the plan to build Thu Thiem 4 bridge connecting Thu Duc and District 7, more than 2km long, after Nha Rong - Khanh Hoi Port built an international passenger ship port.

TPHCM hoàn thành 2 nút giao 7.000 tỉ đồng ở Thủ Đức năm 2025

MINH QUÂN |

TPHCM - Dự án nút giao An Phú và nút giao Mỹ Thủy (TP Thủ Đức) tổng vốn hơn 7.000 tỉ đồng sẽ hoàn thành năm 2025 giúp giảm kẹt xe cho khu Đông.