Removing difficulties for key projects in Quang Ngai

VIÊN NGUYỄN |

The Quang Ngai Provincial Traffic Construction Project Management Board wants to speed up the progress of key projects, but faces difficulties in site clearance.

Currently, most key projects in Quang Ngai province are invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board, including: Sub-project on compensation and resettlement support for the Quang Ngai - Hoai Nhon expressway component project, the section passing through Quang Ngai province; downstream dam of Tra Khuc river; embankment against landslides combined with creating land fund for the North bank of Tra Khuc river, the section passing through Tinh An commune and Tinh Long commune (Quang Ngai city); embankment against landslides combined with creating land fund for the North bank of Tra Khuc river, the section passing through Tinh Long and Tinh Khe communes (Quang Ngai city); the entire route of the Dung Quat - Huong Bridge project; Thach Phuc bridge from Binh An and Hoang Doi bridge; Hoang Doi - Hoang Doi road.

Nhieu nguoi dan van chua ban giao mat bang de thi cong du an duong noi tu cau Thach Bich den Tinh Phong, mot trong nhung du an trong diem cua tinh Quang Ngai. Anh: Vien Nguyen.
Many people have not yet handed over the site to construct the road project connecting Thach Bich bridge to Tinh Phong, one of the key projects of Quang Ngai province. Photo: Vien Nguyen.

In recent times, the Standing Committee of the Provincial Party Committee and the Provincial People's Committee have regularly focused on leadership and direction; localities, relevant departments and branches have also been determined and responsible in implementing key and important projects and works. However, up to this point, most projects have been implemented more slowly than planned. One of the reasons is that the work of developing compensation plans for site clearance and resettlement has encountered many difficulties and problems...

According to the Provincial Traffic Construction Investment Project Management Board, in 2025, the Board will be allocated more than VND1,150 billion in capital. By March 13, the disbursement had reached 1.7% and it is estimated that by March 31, it would be 4.7% of the assigned capital plan. During the implementation of the projects, the leaders of the Provincial Traffic Construction Investment Project Management Board assigned the responsible staff to monitor and urge the contractors to speed up the progress of the projects.

Regularly inspect projects to promptly detect projects that are behind schedule and have low disbursement rates to find appropriate solutions. Grasp the difficulties and obstacles of each project to coordinate with departments, branches, sectors and localities to find solutions to ensure the progress of the projects. The goal is to complete works and projects on schedule, ensure disbursement progress, improve the efficiency of public investment capital use and meet the requirements of socio-economic development of the province in the current period.

Faced with the reality of key projects facing many difficulties, Mr. Nguyen Hoang Giang - Chairman of the People's Committee of Quang Ngai province has requested the leaders of the Board to have a new thinking and new approach in accordance with the actual situation to speed up the progress of the work. It is necessary to develop a work table associated with the implementation time so that the Provincial People's Committee office, together with relevant departments, branches and sectors, can monitor and advise, report to the provincial leaders for timely direction; promptly advise the provincial People's Committee leaders for direction, ensuring effective disbursement of public investment capital in 2025...

VIÊN NGUYỄN
RELATED NEWS

Unfinished projects for decades in Quang Ngai

|

Although not a major project, some roads and schools in Quang Ngai are still stagnant after decades of construction. This delay not only hinders economic development and wastes land, but also causes people to suffer and suffer for a whole decade.

The project is behind schedule, the Quang Ngai City Party Committee hopes that people will share

|

The Thach Bich green park project with a total investment of VND 893 billion is behind schedule, the Secretary of the Quang Ngai City Party Committee hopes that people will share.

Construction of the 640 billion VND social housing project in Quang Ngai is about to start

|

The 750-apartment social housing area with 2,500 residents, with a total investment of about VND640 billion, is expected to start construction in October 2025 in Quang Ngai.

Road worth over 1,300 billion VND in Hanoi completed all items in March

|

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.

Ho Chi Minh City traffic police ambush and film violating motorbikes

|

Ho Chi Minh City - Traffic police deploy ambushes, filming many motorbikes intentionally crossing the railway when red lights and barriers have lowered, posing a risk of traffic accidents.

National Assembly candidates concerned about "weak networks" in mountainous Da Nang

|

Da Nang - Mountainous voters have to use their phones to send petitions when holding online meetings, raising great concerns about the development gap between mountainous and delta areas.

The mother burst into tears when she first heard her child call "mother" after 3 years of waiting

|

During the days of persistently accompanying her congenitally hearing impaired child, the mother burst into tears when she first heard her child call "mother" after 3 years.

Iranian President apologizes to Gulf neighboring countries

|

Iranian President Masoud Pezeshkian apologizes to Gulf neighboring countries in his latest speech on March 7.

Unfinished projects for decades in Quang Ngai

Viên Nguyễn |

Although not a major project, some roads and schools in Quang Ngai are still stagnant after decades of construction. This delay not only hinders economic development and wastes land, but also causes people to suffer and suffer for a whole decade.

The project is behind schedule, the Quang Ngai City Party Committee hopes that people will share

VIÊN NGUYỄN |

The Thach Bich green park project with a total investment of VND 893 billion is behind schedule, the Secretary of the Quang Ngai City Party Committee hopes that people will share.

Construction of the 640 billion VND social housing project in Quang Ngai is about to start

VIÊN NGUYỄN |

The 750-apartment social housing area with 2,500 residents, with a total investment of about VND640 billion, is expected to start construction in October 2025 in Quang Ngai.