Current status of 300 billion VND anti-erosion embankment on the bank of Red River

Đinh Đại |

The embankment to prevent landslides on the banks of the Red River in Lao Cai city has been invested with 300 billion VND but the construction is still sluggish and cannot be completed on schedule.

The Red River section flowing through Lao Cai province is an area that regularly faces riverbank erosion, especially in low-lying communes and wards along the river.

The Red River embankment project in Lao Cai is a key project to protect the lives and property of people living along the river from the increasingly serious risk of landslides.

However, after many years of implementation, the project progress is still sluggish due to problems in site clearance. This not only delays the project but also makes people live in anxiety as the rainy and stormy season approaches.

Nhieu du an da duoc trien khai nham han che sat lo bo song Hong qua dia ban Lao Cai. Anh: Dinh Dai
Many projects have been implemented to limit erosion of the Red River banks through Lao Cai. Photo: Dinh Dai

On December 14, at the foot of Lang Giang bridge (in Xuan Tang ward, Lao Cai city), according to the reporter of Lao Dong Newspaper, workers and a series of machines were constructing the iron frame, embankment foundation...

Through observation, at the foot of the bridge there is an excavator operating continuously, along with many trucks coming in and out one after another to carry soil to dump.

Mot doan bo ke dang thi cong tai phuong Xuan Tang (thanh pho Lao Cai). Anh: Dinh Dai
A section of embankment under construction in Xuan Tang ward (Lao Cai city). Photo: Dinh Dai

Mr. Nguyen Van Thang (Lao Cai city) said: "The anti-erosion embankment project plays a very important role in ensuring the safety of the Red River bank.

After the storm and flood in early September, ensuring the safety of households living along the banks of the Red River became more urgent than ever. Therefore, people hope that the construction unit will complete the project soon, helping to minimize damage when floods occur."

Other households also said that the embankment construction project shows the concern of the authorities at all levels for the riverbank landscape and the safety of the people. The early use of the project helps limit landslides on the Red River bank, creating a more open landscape.

According to research, the project to build embankments to prevent landslides on the Red River bank (phase 2) was approved by the Ministry of Agriculture and Rural Development, with a total investment of 300 billion VND, sourced from the state budget. The Lao Cai Provincial Construction Investment Project Management Board is the investor.

The embankment construction was carried out in Xuan Tang ward, Lao Cai city, on a land area of ​​14.9 hectares, of which 9.4 hectares were for the main project and 6.2 hectares for auxiliary items.

Viec xay ke khong chi giup ngan sat lo ma con dam bao an toan cho cac ho dan ven song. Anh: Dinh Dai
Building embankments not only helps prevent landslides but also ensures safety for households living along the river. Photo: Dinh Dai

The project was built to prevent erosion, enhance flood resistance, ensure the safety of life and property of residential areas along the Red River and public works and administrative agencies of Lao Cai city.

The embankment has a total length of 3,270 m, running along the right bank of the Red River, starting from the Ngoi Duong stream outlet and ending at Lang Giang bridge. The units in charge of the construction are the 319 Corporation of the Ministry of National Defense, Dai An Construction Investment Joint Stock Company and Construction Joint Stock Company.

The project was started in February 2023 and is expected to be completed in December 2024. However, due to site clearance issues, it remains unfinished.

Cac cap chinh quyen dang phoi hop tuyen truyen de nhan dan dong thuan ban giao mat bang. Anh: Dinh Dai
Authorities at all levels are coordinating propaganda to get people to agree to hand over the land. Photo: Dinh Dai

According to information from the Lao Cai Provincial Construction Investment Project Management Board, the investor and construction unit have coordinated with local authorities to mobilize and propagate people to clear trees, crops and hand over the site with a length of 1,937/3,209.6 m (about 60% of the route length); the remaining 1,273 m along the route has no site.

Currently, the Board is coordinating with local authorities to continue to propagate, mobilize, and dialogue so that people can clear up their assets on the land and hand over the site to implement the project on schedule.

In case of intentional non-handover, a record of administrative violation will be drawn up and a decision will be issued to sanction the encroachment and use of public land.

Đinh Đại
RELATED NEWS

Red River Delta District Expects 492 Billion VND Industrial Cluster

|

Phu Tho - Dong Phi Industrial Cluster in Xuan Ang Commune with a total investment of 492 billion VND has started construction, bringing many expectations to Ha Hoa District.

Overloaded inner-city roads in Hanoi await rescue of Red River overpass

|

Hanoi - The bridge project across the Red River has not been built yet, putting traffic pressure on the main road in the inner city.

Billionaire Pham Nhat Vuong's assets increase sharply

|

The net assets of billionaire Pham Nhat Vuong, Chairman of Vingroup Corporation, increased sharply, up to 19.7 billion USD, ranking 124th on the ranking of the richest people on the planet.

Urgent requirements for merging the 2018 Law on Cyber Security and the 2015 Law on Cyber Information Security

|

In the face of the urgent practical requirements of ensuring network security, the merger of the 2018 Law on Cyber Security and the 2015 Law on Network Information Security becomes an inevitable requirement. The unification of laws aims to overcome overlapping functions, improve the efficiency of state management and suit the new organizational model in the spirit of Resolution 18.

Warning of the risk of Ukraine lasting only 3 months

|

Ukraine risks running out of budget in February 2026 if the EU fails to approve a 140 billion euros compensation loan based on frozen Russian assets.

Vietnam's coffee exports in the first 10 months of 2025 grow positively

|

Vietnam's coffee exports achieved impressive growth with turnover in the first 10 months of 2025 reaching 7.42 billion USD.

Portugal lost the match on the day Ronaldo received a red card

|

In the early morning of November 14 (Vietnam time), Portugal lost 0-2 to Ireland and missed the opportunity to qualify for the 2026 World Cup.

The profiteering tricks of land brokers in Phu Quoc

|

Phu Quoc - The proposal to divide the portion is not only an insult to the ethics of journalism, but also exposes the nature of the thief in the lawsuit to profit under the guise of the subject.

Bắt quả tang tàu cát tặc đang "rút ruột" lòng sông Hồng

TRUNG DU |

Thái Bình - Công an tỉnh Thái Bình phối hợp với Công an tỉnh Hà Nam, Nam Định bắt quả tang 1 tàu đang có hành vi khai thác cát trái phép trên sông Hồng.

Red River Delta District Expects 492 Billion VND Industrial Cluster

Tô Công |

Phu Tho - Dong Phi Industrial Cluster in Xuan Ang Commune with a total investment of 492 billion VND has started construction, bringing many expectations to Ha Hoa District.

Overloaded inner-city roads in Hanoi await rescue of Red River overpass

NHÓM PV |

Hanoi - The bridge project across the Red River has not been built yet, putting traffic pressure on the main road in the inner city.