On August 7, according to the Dong Nai City Construction Investment Project Management Board, the Ring Road 3 - Ho Chi Minh City project section passing through the city has achieved a construction output of 74% of the signed contract value.
In which, 2 packages are basically completed, especially construction package No. 26 is behind schedule. The investor has worked with the main contractor and added a subcontractor to speed up the construction progress.
Regarding site clearance work, the City Construction Investment Project Management Board requested Phuoc An commune to soon handle the area still facing problems in the area of the intersection with Huong Lo 19.
Ring Road 3 - Ho Chi Minh City section passing through Dong Nai is more than 11km long.
Dong Nai City sets a target to complete the Ring Road 3 - Ho Chi Minh City project by the end of September 2026.
Previously, on August 4, Deputy Secretary of the Dong Nai City Party Committee Vo Tan Duc inspected the reality and worked with relevant units on the construction progress and site clearance of Ring Road 3 - Ho Chi Minh City projects and said that Ring Road 3 - Ho Chi Minh City is a strategic transport infrastructure project that plays an important role in urban development, logistics in the Nhon Trach - Long Thanh area as well as transport connection for Long Thanh airport and Phuoc An port.
In the context that the Ben Luc - Long Thanh expressway is expected to be put into synchronous operation in September 2026, and Long Thanh airport phase 1 will be put into operation at the end of 2026, the early completion of projects to connect synchronous traffic becomes even more urgent.
Therefore, Phuoc An commune and related units need to urgently review and complete site clearance and infrastructure relocation to serve the construction of projects before August 10.
The investor unit needs to direct the contractor to increase construction by 3 shifts, 4 teams to complete the projects according to the committed schedule.
Previously, in December 2025, the main section of more than 5km of the expressway of the project was technically opened to traffic.