More than 11km of Ring Road 3 - Ho Chi Minh City through Dong Nai completed in September

HÀ ANH CHIẾN |

Dong Nai - Ring Road 3 - Ho Chi Minh City project section passing through the city, more than 11km long, will be completed in September 2026.

On August 7, according to the Dong Nai City Construction Investment Project Management Board, the Ring Road 3 - Ho Chi Minh City project section passing through the city has achieved a construction output of 74% of the signed contract value.

In which, 2 packages are basically completed, especially construction package No. 26 is behind schedule. The investor has worked with the main contractor and added a subcontractor to speed up the construction progress.

Regarding site clearance work, the City Construction Investment Project Management Board requested Phuoc An commune to soon handle the area still facing problems in the area of the intersection with Huong Lo 19.

Ring Road 3 - Ho Chi Minh City section passing through Dong Nai is more than 11km long.

Dong Nai City sets a target to complete the Ring Road 3 - Ho Chi Minh City project by the end of September 2026.

Previously, on August 4, Deputy Secretary of the Dong Nai City Party Committee Vo Tan Duc inspected the reality and worked with relevant units on the construction progress and site clearance of Ring Road 3 - Ho Chi Minh City projects and said that Ring Road 3 - Ho Chi Minh City is a strategic transport infrastructure project that plays an important role in urban development, logistics in the Nhon Trach - Long Thanh area as well as transport connection for Long Thanh airport and Phuoc An port.

In the context that the Ben Luc - Long Thanh expressway is expected to be put into synchronous operation in September 2026, and Long Thanh airport phase 1 will be put into operation at the end of 2026, the early completion of projects to connect synchronous traffic becomes even more urgent.

Therefore, Phuoc An commune and related units need to urgently review and complete site clearance and infrastructure relocation to serve the construction of projects before August 10.

The investor unit needs to direct the contractor to increase construction by 3 shifts, 4 teams to complete the projects according to the committed schedule.

Previously, in December 2025, the main section of more than 5km of the expressway of the project was technically opened to traffic.

HÀ ANH CHIẾN
RELATED NEWS

Hanoi Department of Health warns about the use of products and biological preparations from stem cells

|

Hanoi Department of Health has just issued a warning about the use of products and biological preparations from stem cells.

Fire in a house on the central street of Hai Phong, suspected of being caused by an electrical short circuit

|

Hai Phong - On the morning of August 7, Ngo Quyen ward initially announced that a fire occurred at 118 Tran Khanh Du.

Suspected nanny threads elastic band to shoot children in Ho Chi Minh City: School temporarily suspends operations

|

Ho Chi Minh City - While functional agencies are verifying and clarifying the case of a nanny suspected of beating a child, the kindergarten - where the incident is said to have occurred - is currently temporarily suspended.

Live Vietnamese women's volleyball vs Indonesia at SEA V.Cup 2026

|

Live match between Vietnam women's volleyball team and Indonesia at SEA V.Cup 2026, taking place at 13:00 today (August 7).

Ủng hộ đề xuất nhập cát từ Campuchia làm dự án đường Vành đai 3 - TPHCM

Lê Thanh Phong |

Một trong những khó khăn vướng mắc trong việc thực hiện dự án đường Vành đai 3 ở TPHCM là thiếu cát, và giải pháp đưa ra là nhập cát từ Campuchia.

Bàn giao hơn 14 ha mặt bằng dự án Vành đai 3 - TPHCM đoạn qua tỉnh Đồng Nai

HÀ ANH CHIẾN |

Đồng Nai - Ngày 12.10, UBND huyện Nhơn Trạch cho biết, đã bàn giao mặt bằng cho chủ đầu tư hơn 14,5 ha trên tổng diện tích hơn 49 ha cần thu hồi, đạt gần 30%, thuộc dự án thành phần 1A đường Vành đai 3 - TPHCM.

Tháng 10.2023 bàn giao xong mặt bằng dự án 1A Vành đai 3 - TPHCM qua Đồng Nai

HÀ ANH CHIẾN |

Đồng Nai - Ngày 23.8, UBND huyện Nhơn Trạch đã công khai phương án bồi thường, hỗ trợ dự án thành phần 1A, đoạn Tân Vạn - Nhơn Trạch thuộc vành đai 3 - TPHCM và chậm nhất tháng 10.2023 sẽ hoàn thành công tác giải phóng mặt bằng đối với dự án này.