Proposal to add 2,200 billion VND for the Huu Nghi - Chi Lang expressway

Khánh Linh |

Lang Son - The investor proposed that the Government soon allocate 2,200 billion VND to accelerate the progress of the Huu Nghi - Chi Lang expressway project.

The information was reported by the representative of the investor to the working delegation of the Ministry of Construction, led by Minister Tran Hong Minh, during the field inspection of the Huu Nghi - Chi Lang border gate expressway project, May 6.

To date, the project is implementing 4 design and construction packages (EC). The total realized value reaches 70.29% of the contract.

The main items all reached 93-100% of the plan. Notably, the disbursement rate of state budget capital reached 92.03% according to the capital allocation plan until the end of 2026.

Đại diện chủ đầu tư dự án báo cáo những hạng mục đã thi công hoàn thành trên tuyến cao tốc cửa khẩu Hữu Nghị - Chi Lăng. Ảnh: Khánh Linh
Representatives of the project investor report on the completed items on the Huu Nghi - Chi Lang expressway. Photo: Khanh Linh

Entering the final stage of construction, the project faces great pressure due to the sudden increase in material and fuel prices. In addition, there are still 7 households on the route that have not handed over land, hindering synchronous construction progress.

In order to ensure the goal of completing the entire project on May 19, 2026 as directed by the Prime Minister, the investor representative proposed that the Ministry of Construction give opinions so that the Government can soon allocate 2,200 billion VND of central budget capital, as previously proposed by the People's Committee of Lang Son province.

Công trường cao tốc đang trong giai đoạn nước rút. Ảnh: Vũ Linh
The expressway construction site is in the final sprint stage. Photo: Vu Linh

This is an important resource to help investors accelerate construction and put the project into operation soon.

This unit also proposed that the Government soon issue a decree amending and supplementing regulations in the field of roads, creating a legal corridor to unify the investment plan for building rest stops on the route.

Recognizing the efforts of Lang Son province and the investor, Minister of Construction Tran Hong Minh requested the locality to soon thoroughly handle land issues.

He requested contractors and project enterprises to focus maximum resources, increase shifts, increase crews, and increase construction teams. The resolute goal is that by May 19, 2026, the route must be cleared from Km45 (Nhan Ly commune) to the IC03 intersection (Ky Lua ward - intersecting with National Highway 4B), and at the same time accelerate the construction of the remaining sections.

Khánh Linh
RELATED NEWS

Huu Nghi - Chi Lang expressway construction site focuses all efforts on construction throughout holidays

|

Lang Son - At the Huu Nghi - Chi Lang expressway construction site, workers and engineers are still diligently sticking to the route.

Bottlenecks surround the progress of the Huu Nghi - Chi Lang expressway

|

Lang Son - Huu Nghi - Chi Lang Expressway is entering the acceleration phase of completion but still faces many difficulties.

Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress

|

Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.

Live football Nam Dinh vs Selangor in the Southeast Asian semi-finals

|

Live match between Nam Dinh club and Selangor in the semi-finals of the Southeast Asian Club Championship 2025-2026, taking place at 8:00 PM tonight (May 6).

Health insurance drug list will be updated soon, and many cancer treatment drugs will be added

|

The list of drugs paid for by the Health Insurance Fund (HI) is expected to add 84 new drugs. In which, 30 cancer treatment drugs are added.

Despite the ban, openly trading and using e-cigarettes

|

Despite penalty regulations, e-cigarettes are still secretly traded online, publicly used in many places, with increasingly sophisticated methods.

Chuong Duong bridge is overloaded for many days, Long Bien bridge accelerates to complete repairs

|

Hanoi - Chuong Duong bridge is congested for a long time due to increased traffic pressure, Long Bien bridge is being quickly repaired to soon reduce the load on the area.

Huu Nghi - Chi Lang expressway construction site focuses all efforts on construction throughout holidays

Khánh Linh |

Lang Son - At the Huu Nghi - Chi Lang expressway construction site, workers and engineers are still diligently sticking to the route.

Bottlenecks surround the progress of the Huu Nghi - Chi Lang expressway

Khánh Linh |

Lang Son - Huu Nghi - Chi Lang Expressway is entering the acceleration phase of completion but still faces many difficulties.

Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress

Khánh Linh |

Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.