Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress

Khánh Linh |

Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.

On the nearly 60km long route through the mountains and forests of Lang land, convoys of dump trucks line up to carry soil and rocks, and compactors diligently compress the foundation.

The Huu Nghi - Chi Lang expressway project has a total length of 60 km, passing through 7 communes and wards of Lang Son province with a total adjusted investment of 11,808 billion VND.

According to the project enterprise, on a scope of more than 59km that has been handed over land, contractors are mobilizing 2,599 personnel, 1,195 equipment, deploying 131 construction teams on 5 bidding packages.

a
Construction workers on the construction site. Photo: Khanh Linh

The accumulated realized value reached approximately 4,956.26/7,949.8 billion VND, equivalent to 62.34% of the contract value.

At package EC02 (Km14+500 - Km30+087) undertaken by Lizen Joint Stock Company, many roadbed items have been basically completed.

Mr. Nguyen Manh Tuan - Commander of the bidding package - said that right from the 3rd day of Tet, the unit simultaneously launched operations.

“We arranged overtime, working through noon in conditional sections, focusing on completing the foundation, spreading crushed stone grades and accelerating asphalt concrete paving. The goal is to compensate for the slow progress and aim for the completion milestone of the entire route before April 30, 2026,” Mr. Tuan said.

According to data, many items achieved high rates such as excavating the foundation over 92%, filling the K95 foundation over 97%, drilled piles and prestressed concrete girder casting approximately 98%.

a
Road sections are simultaneously paved with asphalt concrete. Photo: Khanh Linh

In the sections undertaken by Deo Ca Group, the construction teams of bridges, civil tunnels, and taluy reinforcement are organized "3 shifts, 4 teams".

Mr. Tran Van Quan - Director of the Management Board - said that the Management Board has reviewed the entire roadmap, flexibly coordinated human resources between bidding packages, prioritizing completing sections that can be asphalt concrete paved early.

We determine that this is the final sprint stage. Teams are required to both ensure quality, labor safety, and accelerate to maximize volume," Mr. Quan emphasized.

In parallel with construction, site clearance work still has some shortcomings.

a
The Huu Nghi - Chi Lang expressway, after completion, is expected to reduce traffic pressure on National Highway 1. Photo: Vu Linh

Currently, there are still 28 households that have not moved houses according to FS documents, 16 households have land problems and 66 households are related to supplements according to technical design documents, along with some locations of technical infrastructure and landfills that have not been handed over.

Previously, on the 4th day of Binh Ngo Tet 2026, Prime Minister Pham Minh Chinh directly surveyed the field and inspected the implementation of the two expressway projects Dong Dang (Lang Son) - Tra Linh (Cao Bang) and Huu Nghi - Chi Lang.

Here, the Prime Minister emphasized that the Huu Nghi - Chi Lang expressway project is of particular importance to Lang Son province and the Northeast region; contributing to completing the border gate expressway, promoting socio-economic development, ensuring national defense and security and strengthening trade connections.

a
The Prime Minister requests the completion of the Huu Nghi - Chi Lang expressway before April 30, 2026. Photo: Vu Linh

The head of the Government requested quick construction, completing as soon as possible so that the project can be put into operation soon.

At the same time, requesting contractors, along with taking care of workers' lives, to increase productivity, increase shifts, accelerate further, create a vibrant emulation atmosphere at the construction site, and be determined to complete the Huu Nghi - Chi Lang expressway before April 30, 2026.

Khánh Linh
RELATED NEWS

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

|

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.

Prime Minister requests technical opening of Huu Nghi - Chi Lang expressway before April 30, 2026

|

Lang Son - Prime Minister Pham Minh Chinh requested Deo Ca Group to mobilize human resources and machinery to clear the Huu Nghi - Chi Lang expressway before April 30, 2026.

Tet without holidays at the expressway construction site connecting 2 border provinces

|

The Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway has started construction from the 3rd day of Tet to ensure progress.

Proposing a land fund large enough to attract Meta, Arizona State University to Hanoi

|

Hanoi - The Management Board of High-Tech Parks and Industrial Parks of the city proposes planning a land fund large enough to attract Arizona State University, Meta Group...

Continue to complete the plan to adjust the organization and staffing of the Army

|

General Phan Van Giang clearly stated the continued completion of the plan to adjust the organization and staffing of the Army in the period 2026-2030.

Live broadcast of Vietnam women's futsal team against Australia at the Southeast Asian Championship

|

Live football match between Vietnam women's futsal team and Australia women's futsal team at the 2026 Southeast Asian Women's Futsal Championship at 1:30 PM today (February 24).

List of candidates for National Assembly Deputies of the 16th term belonging to the Vietnam Fatherland Front bloc

|

Candidates for National Assembly deputies of the 16th term belonging to the Vietnam Fatherland Front bloc include 36 people.

Initial cause of car plunging into canal killing 2 people in Gia Lai

|

Gia Lai - The initial cause of the 2 bodies and car under the Van Phong canal was determined to be due to the driver not being familiar with the road, causing an accident when entering a sharp bend.

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

Tân Văn |

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.

Prime Minister requests technical opening of Huu Nghi - Chi Lang expressway before April 30, 2026

Khánh Linh |

Lang Son - Prime Minister Pham Minh Chinh requested Deo Ca Group to mobilize human resources and machinery to clear the Huu Nghi - Chi Lang expressway before April 30, 2026.

Tet without holidays at the expressway construction site connecting 2 border provinces

Khánh Linh |

The Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway has started construction from the 3rd day of Tet to ensure progress.