Lang Son considers terminating contract for expressway rest stop project

Khánh Linh |

Lang Son - The Huu Lung Rest Stop project contract was signed in September 2023, but after nearly three years, it is still necessary to review obligations, progress and termination conditions.

On August 12, the Office of Lang Son Provincial People's Committee said that the leaders of the Provincial People's Committee assigned the Department of Finance to review and advise on handling the termination of the Huu Lung Rest Stop project contract.

The direction was issued after the Provincial Construction Investment Project Management Board had three documents related to the termination of the contract with this project.

Huu Lung rest stop was prepared to select investors from 2019, including two areas arranged on both sides of the Bac Giang - Lang Son expressway, section Km81+280 to Km81+920. The project location is in Tan Hoa village, Ho Son commune, former Huu Lung district, now belonging to Huu Lung commune.

According to preliminary selection documents, the project uses more than 99,000 m2 of land, with initial estimated implementation costs of 99.8 billion VND.

By 2021, the investor selection plan will determine an area of 99,200 m2, with a total estimated investment of 102 billion VND.

In September 2023, Lang Son Provincial People's Committee signed a project implementation contract with a joint venture of Ha Thanh Co., Ltd. and Ha Tay Transport Automobile Joint Stock Company.

However, in August 2024, the Provincial People's Committee determined that the investor had not fulfilled some obligations under the contract, including paying value to the state budget and handing over the measurement dossiers for site clearance.

Relevant state management agencies, especially the Provincial Construction Investment Project Management Board, were also commented on for not closely coordinating, and not fully and promptly implementing the responsibilities of contract management agencies.

The province at that time requested to work directly with the investor. If the enterprise continues to be slow to fulfill its responsibilities or does not show determination to implement, the Project Management Board must advise on procedures to temporarily suspend or terminate the contract.

In case of continuing the project, the parties must review the extension of guarantees, financial obligations, site clearance dossiers and adjust contracts if necessary, according to the conclusion of the Provincial People's Committee.

By the end of 2025, Lang Son still aims to complete site clearance, construction and put the rest stop into operation in 2026.

However, the contract processing process continued to be prolonged, leading to a proposal to consider termination in August this year.

Khánh Linh
RELATED NEWS

Only 4/21 rest stops on the North - South expressway in the East have electric vehicle charging stations operating

|

Only 4/21 rest stops on the North - South expressway in the East have put part of the electric vehicle charging station system into operation.

An investor has built the 2nd rest stop on the expressway in Quang Ninh

|

Quang Ninh - Quang Ninh Department of Construction has just announced the results of investor selection for the Van Don - Mong Cai expressway rest stop project in Duong Hoa commune.

Slow progress, 2 highway rest stops through Ha Tinh are still unfinished

|

Ha Tinh - Two rest stops on the North-South expressway are still under construction even though the completion milestone is approaching, the Road Administration sent an official dispatch requesting to speed up progress.

Benchmark scores for Pedagogy majors in Ho Chi Minh City, many majors approach 30 points

|

The benchmark score for Pedagogy majors in Ho Chi Minh City in 2026 continues to be high, with many majors having admission scores close to 30 points.

Hanoi studies traffic infrastructure along 126km of the Red River

|

Hanoi assesses traffic infrastructure on the section of the Red River about 126km long to recline the route, improve elevation and ensure flood drainage safety.

Product matrix for treating erectile dysfunction with "complete cure" commitment

|

Faced with the "matrix" of erectile dysfunction treatment products on the market, doctors warn men not to arbitrarily use the product without examination.

Only 4/21 rest stops on the North - South expressway in the East have electric vehicle charging stations operating

Tô Thế |

Only 4/21 rest stops on the North - South expressway in the East have put part of the electric vehicle charging station system into operation.

An investor has built the 2nd rest stop on the expressway in Quang Ninh

Nguyễn Hùng |

Quang Ninh - Quang Ninh Department of Construction has just announced the results of investor selection for the Van Don - Mong Cai expressway rest stop project in Duong Hoa commune.

Slow progress, 2 highway rest stops through Ha Tinh are still unfinished

TRẦN TUẤN |

Ha Tinh - Two rest stops on the North-South expressway are still under construction even though the completion milestone is approaching, the Road Administration sent an official dispatch requesting to speed up progress.