A series of border area projects are "buried" because of land clearance problems

Nhóm PV |

Cao Bang - Many projects have been under construction for decades but still cannot be completed because of site clearance problems .

First of all, we can mention the project to build a bypass road in Cao Bang city approved in 2008. After nearly 2 decades of construction, this road has still not been completed.

After many adjustments, the Cao Bang city bypass construction project is invested by the Department of Transport of Cao Bang province. The project has a total investment of 221.88 billion VND. This route passes through 4 wards: Duyet Trung, Tan Giang, Hoa Chung and Song Hien. The starting point of the route is in Duyet Trung ward, the ending point intersects with National Highway 3 in Song Hien ward, the total length of the route is about 7.56km.

Dusty construction scenes have lasted for many years on the Cao Bang City bypass.
Dusty construction scenes have lasted for many years on the Cao Bang City bypass.

Up to now, this project still has about 20% of the land that cannot be cleared, causing construction delays. On July 13, talking to reporters, Mr. Le Van Chinh (residing in group 18, Song Hien ward) expressed his frustration when the construction project lasted too long, and had to walk every day on the unfinished, muddy road. Dusty land surrounds the people.

"Not to mention the construction process of lowering the slope along with the rain caused the land of some households to collapse" - Mr. Chinh said. According to research, due to the long implementation time, the site clearance compensation unit price has many changes, causing difficulties in the negotiation process with people.

Construction of the Cao Bang City bypass route has been delayed for many years.
Construction of the Cao Bang City bypass route has been delayed for many years.

"On the other hand, many plots of land have errors when on paper they are land for perennial crops, but in reality people have built houses to live on them, causing many difficulties in the land clearance process" - representative of the City People's Committee. Cao Bang informed the reporter.

The second project is called Cao Bang Provincial Traditional Medicine Hospital , newly built on a land area of ​​more than 3.5 hectares in Song Hien ward and De Tham ward, Cao Bang city. The investor of the project is the Investment and Construction Project Management Board of Cao Bang province. This hospital has a construction period of 24 months.

Images recorded on the Cao Bang City bypass.
The project to build a new traditional medicine hospital in Cao Bang province is also dormant and not under construction.
The project to build a new traditional medicine hospital in Cao Bang province is also dormant and not under construction.

Approved from the beginning of 2022, but up to now, site clearance has only reached nearly 1ha/3.43ha that needs to be done. The freed areas are not concentrated in one place, so the only construction move of this project is to erect a project information sign.

Inside the new construction area of ​​the traditional hospital, a local wood workshop still stands.
Inside the new construction area of ​​the traditional hospital, a local wood workshop is still blocked and the site cannot be cleared.

In Cao Bang city, the project at Cao Bang Provincial Vocational School is also facing difficulties. In report No. 1213 of the Department of Planning and Investment of Cao Bang province, this project encountered difficulties when 4 households living on the school's land had not been resettled.

This land that cannot be released is used to build multi-purpose houses, swimming pools and auxiliary works, tourism and hotel rooms, and outdoor sports fields. Because of the land clearance delay , the project's 2024 capital plan of over 45 billion VND has not yet been disbursed (data dated May 26).

Cao Bang Provincial Vocational School has not been able to build new projects as planned.
Cao Bang Provincial Vocational School has not been able to build new projects as planned.

On July 12, during a meeting to evaluate the results of the first 6 months of implementing the Infrastructure Development Program, Chairman of Cao Bang Provincial People's Committee Hoang Xuan Anh requested units of the Department of Planning and Investment to advise Cao Bang Provincial People's Committee calculates and allocates resources for projects; Focus on completing investment preparation procedures for new construction projects; Coordinate well the implementation of site clearance work. The Department of Natural Resources and Environment of Cao Bang province needs to continue to advise the Provincial People's Committee on planning, forecasting, and arranging common construction materials to serve projects.

Nhóm PV
TIN LIÊN QUAN

Mất 8 năm giải phóng mặt bằng vành đai 1.800 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Hà Nội - Đến tháng 2.2025, 6.000m2 mặt bằng còn lại sẽ được bàn giao để thi công hoàn thiện dự án Vành đai 3,5 (đoạn qua Hoài Đức) sau nhiều năm chậm trễ.

Dự án hạ tầng cửa khẩu Trà Lĩnh chậm giải ngân, vướng mắc giải phóng mặt bằng

Tân Văn |

Cao Bằng - Mặc dù cửa khẩu Trà Lĩnh đã là cửa khẩu quốc tế nhưng loạt dự án xây dựng hạ tầng tại đây vẫn đang ì ạch giải phóng mặt bằng.

Cao Bằng đưa nhiều giải pháp để giải phóng mặt bằng

Tân Văn |

Để sớm hiện thực hóa giấc mơ cao tốc, tỉnh Cao Bằng đang phối hợp tích cực với tỉnh Lạng Sơn thực hiện nhiều cách làm, giải pháp.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Mất 8 năm giải phóng mặt bằng vành đai 1.800 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Hà Nội - Đến tháng 2.2025, 6.000m2 mặt bằng còn lại sẽ được bàn giao để thi công hoàn thiện dự án Vành đai 3,5 (đoạn qua Hoài Đức) sau nhiều năm chậm trễ.

Dự án hạ tầng cửa khẩu Trà Lĩnh chậm giải ngân, vướng mắc giải phóng mặt bằng

Tân Văn |

Cao Bằng - Mặc dù cửa khẩu Trà Lĩnh đã là cửa khẩu quốc tế nhưng loạt dự án xây dựng hạ tầng tại đây vẫn đang ì ạch giải phóng mặt bằng.

Cao Bằng đưa nhiều giải pháp để giải phóng mặt bằng

Tân Văn |

Để sớm hiện thực hóa giấc mơ cao tốc, tỉnh Cao Bằng đang phối hợp tích cực với tỉnh Lạng Sơn thực hiện nhiều cách làm, giải pháp.