The reason why the highway through Quang Binh is not completed yet

CÔNG SÁNG |

Quang Binh - Currently, the land clearance for the North-South expressway through the area still has more than 100m left to be cleared.

More than 100m of land has not been handed over yet.

On November 28, the Department of Transport of Quang Binh province said that up to now, more than 100m of the North-South Expressway passing through the locality has not been cleared to hand over to the Project Management Boards.

The North-South Expressway construction project in the Eastern phase 2021 - 2025, the section through Quang Binh province, includes 3 component projects; length 126.43km through 6 districts, towns, cities and 35 communes and wards.

The Vung Ang - Bung section is about 42.95km long. The Bung - Van Ninh section is 49.93km long. The Van Ninh - Cam Lo section is 33.55km long. There are 8 intersections in the province.

Up to now, the length handed over to Project Management Board 6 and Ho Chi Minh Road Project Management Board - Ministry of Transport is 126.33km/126.43km (reaching 99.92%); more than 100m in Le Thuy district of the Van Ninh - Cam Lo component project has not been handed over.

The Department of Natural Resources and Environment of Le Thuy district said that there are still 115m of land in the area that have not been cleared to hand over to the Ho Chi Minh Road Project Management Board.

Of which, 105m is the residential area where people are living. The household has agreed to hand over the site, however, due to unfavorable weather, the site has not been demolished yet.

Nha thau tranh thu thuc hien cac cong viec trong dieu kien thoi tiet khong thuan loi tai xa Kim Thuy (huyen Le Thuy). Anh: Cong Sang
Contractors take advantage of unfavorable weather conditions to carry out work in Le Thuy district. Photo: Cong Sang

In addition, the decision to adjust 10m of the ground level needs to be adjusted to match the data in the red book and land information. After completing the adjustment, the household will be notified. If they do not agree, enforcement will be carried out.

Another family with a length of about 3-5m has received compensation and handed over the land. This family is requesting road support, the unit has made a plan for the family, but has not agreed yet.

Recently, the weather has been continuously rainy, with periods of flooding, making it difficult to restore the site.

Permanent solution

Le Thuy District People's Committee informed that it has directed the Department of Natural Resources and Environment to reorganize the site clearance council. Immediately after reorganization, a meeting will be held to quickly resolve difficulties, in the spirit of resolving them as quickly as possible.

Recently, the locality has focused on overcoming natural disasters, so in the near future, it will try to completely resolve the problems of the North-South expressway.

The North-South Expressway Construction Project in the Eastern Region, Phase 2021-2025, through Quang Binh Province, has a total land area occupied by component projects of about 1,128.9 hectares. The forest area in the province that needs to change its purpose of use is 659.74 hectares.

About 3,772 households were affected, of which 551 households were resettled; about 4,642 graves were affected, of which 3,885 graves had to be relocated to new locations; affected technical infrastructure works: 500kV power line system with 15 locations; 220kV power line with 15 locations; 110kV power line with 21 locations intersecting with the expressway and many medium-voltage and low-voltage power line systems; telecommunications system...

CÔNG SÁNG
TIN LIÊN QUAN

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Solution for the last 0.15% of the highway area through Quang Binh

|

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

Proposal to urgently open Soi Sim beach to rescue Ti-Top beach

|

Quang Ninh - Because there is only one open-up beach in Ti-Top, tourist boats often hit to pick up and drop off visitors, while visitors sweat and jostle at this beach.

Promoting the ranks of 8 officers, 5 Army Colonels to new assignments

|

Last week, 8 officers were promoted; many officers' salaries were raised and 5 Colonels and 2 Lieutenant Colonels were transferred and appointed to new positions.

serious hot air balloon accident, 8 people killed

|

2 survivors, 8 people died in the hot air balloon crash in Brazil.

Vietnamese musician owns a 1,000m2 space to reveal his real income

|

The musician Khanh Don has a 1,000m2 resting place in Da Lat, bought a house for 10 billion VND as a gift for his wife, all thanks to his income from music.

Organic durian growers in Gia Lai face output difficulties, profits decrease

|

Gia Lai - Clean, organic durian cannot be exported to foreign markets, causing farmers to lose profits.

The new Miss Universe Vietnam is an IT engineer, graduated from a prestigious school in the US

|

Surpassing many contestants, information technology engineer Nguyen Hoang Phuong Linh was crowned Miss Cosmo Vietnam - Miss Universe Vietnam 2025.

Bắt đối tượng cướp tài sản trên cao tốc Nội Bài - Lào Cai

Trần Bùi |

Vĩnh Phúc - Một đối tượng vừa bị Công an huyện Lập Thạch bắt giữ vì hành vi cướp tài sản trên cao tốc Nội Bài - Lào Cai.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.