Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

195m of land left

On September 27, the People's Committee of Quang Binh province said that recently, the site clearance work for the North-South Expressway Construction Project in the Eastern Region, phase 2021-2025, through Quang Binh province, has been implemented synchronously and resolutely by Party committees and authorities at all levels in the province, ensuring progress according to the set plan.

The North-South Expressway project through Quang Binh province is 126.43km long, passing through 6 districts, towns, cities and 35 communes and wards with 3,772 affected households. Of these, 551 households are subject to resettlement.

To date, 5 districts, towns and cities have completed the clearance work and handed over 100% of the cleared land to the Project Management Boards (reaching 99.85%). Currently, only about 195m in Le Thuy district (accounting for 0.15%) is still stuck because households have not agreed with the resettlement plan or received money.

The Council for Site Clearance of the North-South Expressway Project in Quang Binh province and in districts, towns and cities have fully implemented policies to ensure compliance with legal regulations, and built concentrated resettlement areas to ensure synchronization and modernity according to the general policy of the Government.

Speed ​​up construction progress

Mr. Dang Dai Tinh - Chairman of Le Thuy District People's Committee - said that the site clearance work in Le Thuy district is more difficult because it is the longest area in the province, the project passes through the most densely populated area with nearly 1,000 households. Along with that, the land history is complicated, land transferred from forestry farms, encroached land, disputed land, no origin of land use time... so it takes a lot of time to handle. Along with that, the district is also stuck with solar power and nearly 700 graves.

Viec vuong mat bang khien mot so doan cao toc Bac - Nam qua tinh Quang Binh chua thi cong duoc. Anh: Cong Sang
Land acquisition issues have prevented some sections of the North-South Expressway through Quang Binh province from being constructed. Photo: Cong Sang

Recently, Le Thuy district has carried out forced evictions against 2 households. In the coming time, it will continue to implement forced eviction measures to hand over the land on schedule.

After inspecting the progress of the North-South Eastern Expressway project, phase 2021-2025 through Quang Binh in Phu Thuy commune (Le Thuy), Secretary of the Quang Binh Provincial Party Committee Vu Dai Thang made proposals related to compensation, site clearance, and resettlement.

The Provincial Party Secretary emphasized that it is necessary to continue considering solutions to ensure harmony of interests for people and businesses.

For households subject to compensation and site clearance, after being informed, mobilized, and fully implementing policies but still not agreeing and handing over the site to the construction unit, it is necessary to implement solutions in accordance with regulations to clear the route, avoiding affecting the entire project because of a few individuals.

Difficulties in site clearance greatly affect construction work when the flood season has arrived.

Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project, with a length of 33.55 km.

Mr. Chu Van Long - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board - said that the weather has been unfavorable recently, so from the afternoon of September 25, the unit has just started to continue implementing the concrete content, the earthwork cannot be done because it is wet.

To help minimize the impact of the weather at the end of the year, from the beginning, the units strive to complete the software as soon as possible. In adverse weather conditions, focus on construction on contents such as concrete structures.

At the construction site, there are more than 1,400 officers, workers, and operators with about 700 locomotives and equipment of all kinds. "The project has now achieved nearly 60%. In the coming time, the unit will prioritize the implementation of concrete items to speed up progress," said Mr. Long.

CÔNG SÁNG
TIN LIÊN QUAN

Cưỡng chế hơn 3.000m2 mặt bằng cao tốc tại Quảng Bình

CÔNG SÁNG |

Hơn 3.000m2 mặt bằng cao tốc Bắc – Nam qua huyện Lệ Thủy (tỉnh Quảng Bình) vừa được cưỡng chế thu hồi.

Mặt bằng cao tốc Bắc - Nam tại miền Trung: Nơi hoàn thành, chỗ gặp khó

CÔNG SÁNG - HƯNG THƠ |

Việc giải phóng mặt bằng cao tốc Bắc - Nam qua tỉnh Quảng Bình và Quảng Trị đến nay vẫn còn vướng. Trong khi một số địa phương đã hoàn thành công tác bàn giao mặt bằng, vẫn còn nơi đang gặp khó trong quá trình triển khai.

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.

Vẫn khó giao dịch vàng nhẫn ở TPHCM

HẠ MÂY |

Nhiều người dân TPHCM đến các cửa hàng giao dịch vàng nhẫn, nhưng không thành, vì thời điểm này, các thương hiệu vàng lớn không có hàng để bán.

Chủ tịch nước quyết định đặc xá cho 3.765 phạm nhân

Ái Vân |

Chủ tịch nước đã quyết định đặc xá cho 3.763 phạm nhân đang chấp hành án phạt tù và 2 người đang được tạm đình chỉ chấp hành án phạt tù.

Đề án thí điểm sắp xếp mô hình tổ chức CĐ trực thuộc CĐ Ngân hàng Việt Nam

Kiều Vũ - Hải Nguyễn |

Hà Nội - Ngày 30.9, Đoàn Chủ tịch Tổng LĐLĐVN họp lần thứ 7, khóa XIII dưới sự chủ trì của đồng chí Nguyễn Đình Khang - Ủy viên Trung ương Đảng, Chủ tịch Tổng LĐLĐVN. Một trong những nội dung được thảo luận, cho ý kiến là Tờ trình Đề án thí điểm sắp xếp mô hình tổ chức công đoàn trực thuộc Công đoàn Ngân hàng Việt Nam tập trung, xuyên suốt, hiệu quả.

Tọa đàm "Để ô nhiễm môi trường sau bão lũ không còn là nỗi lo"

Nhóm PV |

Bên cạnh những mất mát, đau thương về người và của, một vấn đề khác nhận được rất nhiều sự quan tâm đó chính là vấn ô nhiễm môi trường sau bão lũ. Và một trong những nơi đang phải chịu áp lực từ nguồn rác thải khổng lồ đó chính là Vịnh Hạ Long (Quảng Ninh). Trước tình hình này, Báo Lao Động đã tổ chức buổi tọa đàm "Để ô nhiễm môi trường sau bão lũ không còn là nỗi lo".

Erik ten Hag chưa nghĩ đến chuyện bị Man United sa thải

NGUYỄN ĐĂNG |

Huấn luyện viên Erik ten Hag vẫn có những phát biểu cứng rắn, dù Man United phải trải qua trận thua 0-3 trước Tottenham.

Enforced acquisition of more than 3,000m2 of highway land in Quang Binh

CÔNG SÁNG |

More than 3,000 square meters of the North-South expressway through Le Thuy district (Quang Binh province) have just been forcibly reclaimed.

North-South Expressway site in Central Vietnam: Some places are completed, some are facing difficulties

CÔNG SÁNG - HƯNG THƠ |

The site clearance for the North-South Expressway through Quang Binh and Quang Tri provinces is still stuck. While some localities have completed the site handover, there are still places facing difficulties in the implementation process.

What is the solution for the North-South expressway through Quang Binh?

CÔNG SÁNG |

Quang Binh Province will enforce cases that do not agree with the compensation and site clearance policy according to the provisions of law at the North-South Expressway .