Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

195m of land left

On September 27, the People's Committee of Quang Binh province said that recently, the site clearance work for the North-South Expressway Construction Project in the Eastern Region, phase 2021-2025, through Quang Binh province, has been implemented synchronously and resolutely by Party committees and authorities at all levels in the province, ensuring progress according to the set plan.

The North-South Expressway project through Quang Binh province is 126.43km long, passing through 6 districts, towns, cities and 35 communes and wards with 3,772 affected households. Of these, 551 households are subject to resettlement.

To date, 5 districts, towns and cities have completed the clearance work and handed over 100% of the cleared land to the Project Management Boards (reaching 99.85%). Currently, only about 195m in Le Thuy district (accounting for 0.15%) is still stuck because households have not agreed with the resettlement plan or received money.

The Council for Site Clearance of the North-South Expressway Project in Quang Binh province and in districts, towns and cities have fully implemented policies to ensure compliance with legal regulations, and built concentrated resettlement areas to ensure synchronization and modernity according to the general policy of the Government.

Speed ​​up construction progress

Mr. Dang Dai Tinh - Chairman of Le Thuy District People's Committee - said that the site clearance work in Le Thuy district is more difficult because it is the longest area in the province, the project passes through the most densely populated area with nearly 1,000 households. Along with that, the land history is complicated, land transferred from forestry farms, encroached land, disputed land, no origin of land use time... so it takes a lot of time to handle. Along with that, the district is also stuck with solar power and nearly 700 graves.

Viec vuong mat bang khien mot so doan cao toc Bac - Nam qua tinh Quang Binh chua thi cong duoc. Anh: Cong Sang
Land acquisition issues have prevented some sections of the North-South Expressway through Quang Binh province from being constructed. Photo: Cong Sang

Recently, Le Thuy district has carried out forced evictions against 2 households. In the coming time, it will continue to implement forced eviction measures to hand over the land on schedule.

After inspecting the progress of the North-South Eastern Expressway project, phase 2021-2025 through Quang Binh in Phu Thuy commune (Le Thuy), Secretary of the Quang Binh Provincial Party Committee Vu Dai Thang made proposals related to compensation, site clearance, and resettlement.

The Provincial Party Secretary emphasized that it is necessary to continue considering solutions to ensure harmony of interests for people and businesses.

For households subject to compensation and site clearance, after being informed, mobilized, and fully implementing policies but still not agreeing and handing over the site to the construction unit, it is necessary to implement solutions in accordance with regulations to clear the route, avoiding affecting the entire project because of a few individuals.

Difficulties in site clearance greatly affect construction work when the flood season has arrived.

Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project, with a length of 33.55 km.

Mr. Chu Van Long - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board - said that the weather has been unfavorable recently, so from the afternoon of September 25, the unit has just started to continue implementing the concrete content, the earthwork cannot be done because it is wet.

To help minimize the impact of the weather at the end of the year, from the beginning, the units strive to complete the software as soon as possible. In adverse weather conditions, focus on construction on contents such as concrete structures.

At the construction site, there are more than 1,400 officers, workers, and operators with about 700 locomotives and equipment of all kinds. "The project has now achieved nearly 60%. In the coming time, the unit will prioritize the implementation of concrete items to speed up progress," said Mr. Long.

CÔNG SÁNG
RELATED NEWS

Gold prices increase rapidly, people who have not been able to buy for 3 days, buyers save enough 50 taels

|

Gold prices increased rapidly, many stores announced that they would not trade, people still lined up in the hope of buying gold.

Forecast of very heavy rain in the next 3 days, some places exceed 500mm

|

The Central region is about to face a widespread heavy rain; in particular, it is important to note that Hue city has a rainfall in the next 3 days that may exceed 500mm.

Man breaks into emergency room, threatens female doctor has left the area

|

Nghe An - The police verified that the man who broke into the emergency room of Dien Chau General Hospital, used a pen to threaten the female doctor, had left the locality.

Parks in Hanoi change to new shirts after renovation, people excitedly dance and exercise

|

Hanoi - The Cau Giay Park renovation project has been completed 40 days ahead of schedule, bringing a completely new, spacious and modern look.

Son Hai Group junior and Miss Do Thi Ha at the talent admission ceremony in Thanh Hoa

|

Thanh Hoa - On the morning of October 16, Miss Do Thi Ha's private home was held a talent admission ceremony, attracting the attention of many people and guests.

The possibility of Miss Yen Nhi being top in the Miss Grand International 2025 final

|

With what she has shown recently, can Yen Nhi enter the top at the Miss Grand International 2025 final on October 18?

Stopping receiving international cruise ship visitors, Ho Chi Minh City faces serious damage

|

HCMC - Enterprises propose to suddenly stop receiving tourist cruise ships at Cai Mep - Thi Vai port cluster, affecting the reception of international visitors to HCMC.

Cưỡng chế hơn 3.000m2 mặt bằng cao tốc tại Quảng Bình

CÔNG SÁNG |

Hơn 3.000m2 mặt bằng cao tốc Bắc – Nam qua huyện Lệ Thủy (tỉnh Quảng Bình) vừa được cưỡng chế thu hồi.

Mặt bằng cao tốc Bắc - Nam tại miền Trung: Nơi hoàn thành, chỗ gặp khó

CÔNG SÁNG - HƯNG THƠ |

Việc giải phóng mặt bằng cao tốc Bắc - Nam qua tỉnh Quảng Bình và Quảng Trị đến nay vẫn còn vướng. Trong khi một số địa phương đã hoàn thành công tác bàn giao mặt bằng, vẫn còn nơi đang gặp khó trong quá trình triển khai.

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.