Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

195m of land left

On September 27, the People's Committee of Quang Binh province said that recently, the site clearance work for the North-South Expressway Construction Project in the Eastern Region, phase 2021-2025, through Quang Binh province, has been implemented synchronously and resolutely by Party committees and authorities at all levels in the province, ensuring progress according to the set plan.

The North-South Expressway project through Quang Binh province is 126.43km long, passing through 6 districts, towns, cities and 35 communes and wards with 3,772 affected households. Of these, 551 households are subject to resettlement.

To date, 5 districts, towns and cities have completed the clearance work and handed over 100% of the cleared land to the Project Management Boards (reaching 99.85%). Currently, only about 195m in Le Thuy district (accounting for 0.15%) is still stuck because households have not agreed with the resettlement plan or received money.

The Council for Site Clearance of the North-South Expressway Project in Quang Binh province and in districts, towns and cities have fully implemented policies to ensure compliance with legal regulations, and built concentrated resettlement areas to ensure synchronization and modernity according to the general policy of the Government.

Speed ​​up construction progress

Mr. Dang Dai Tinh - Chairman of Le Thuy District People's Committee - said that the site clearance work in Le Thuy district is more difficult because it is the longest area in the province, the project passes through the most densely populated area with nearly 1,000 households. Along with that, the land history is complicated, land transferred from forestry farms, encroached land, disputed land, no origin of land use time... so it takes a lot of time to handle. Along with that, the district is also stuck with solar power and nearly 700 graves.

Viec vuong mat bang khien mot so doan cao toc Bac - Nam qua tinh Quang Binh chua thi cong duoc. Anh: Cong Sang
Land acquisition issues have prevented some sections of the North-South Expressway through Quang Binh province from being constructed. Photo: Cong Sang

Recently, Le Thuy district has carried out forced evictions against 2 households. In the coming time, it will continue to implement forced eviction measures to hand over the land on schedule.

After inspecting the progress of the North-South Eastern Expressway project, phase 2021-2025 through Quang Binh in Phu Thuy commune (Le Thuy), Secretary of the Quang Binh Provincial Party Committee Vu Dai Thang made proposals related to compensation, site clearance, and resettlement.

The Provincial Party Secretary emphasized that it is necessary to continue considering solutions to ensure harmony of interests for people and businesses.

For households subject to compensation and site clearance, after being informed, mobilized, and fully implementing policies but still not agreeing and handing over the site to the construction unit, it is necessary to implement solutions in accordance with regulations to clear the route, avoiding affecting the entire project because of a few individuals.

Difficulties in site clearance greatly affect construction work when the flood season has arrived.

Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project, with a length of 33.55 km.

Mr. Chu Van Long - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board - said that the weather has been unfavorable recently, so from the afternoon of September 25, the unit has just started to continue implementing the concrete content, the earthwork cannot be done because it is wet.

To help minimize the impact of the weather at the end of the year, from the beginning, the units strive to complete the software as soon as possible. In adverse weather conditions, focus on construction on contents such as concrete structures.

At the construction site, there are more than 1,400 officers, workers, and operators with about 700 locomotives and equipment of all kinds. "The project has now achieved nearly 60%. In the coming time, the unit will prioritize the implementation of concrete items to speed up progress," said Mr. Long.

CÔNG SÁNG
RELATED NEWS

Fireworks explosion causes 141 people to be hospitalized after 4 days of Tet holiday

|

Accidents caused by firecrackers and fireworks continue to increase during Tet. In just 24 hours, 66 people had to be hospitalized for emergency treatment, and 34 cases were hospitalized.

Warehouse fire on the 2nd night of Tet in Ho Chi Minh City

|

Ho Chi Minh City - On the evening of the 2nd day of Tet, the Ho Chi Minh City Fire and Rescue Force promptly controlled the fire at a warehouse in Long Binh ward, preventing the fire from spreading.

9th Hour No. 189: Reunion - Part 1

|

Hour 9 - A cold home just because the wife gave birth to two daughters. The husband neglects and forces his wife to give birth to a son. What will happen to this family?

The outskirts of Hai Phong are heavily congested, the line of cars going to wish Tet is kilometers long

|

Hai Phong - From noon on the 2nd day of Tet, the roads leading to the outskirts of Tien Lang, Vinh Bao are in a state of congestion, at times congested for hours.

Violating the limit of alcohol concentration but requesting traffic police not to temporarily seize the vehicle

|

Nghe An - Wishing Tet to both paternal and maternal relatives on the 2nd day of Tet, a 54-year-old man in Hop Minh commune violated the limit of alcohol concentration, and was recorded and fined by traffic police.

Gold price update closing session 18. 2: Unexpected reversal, signs of recovery

|

Gold price update closing session 18. 2: World gold prices decreased compared to the previous day but are showing signs of recovery.

Restaurant opens throughout Tet, slightly increases prices to pay employee salaries

|

Hanoi - Many eateries simultaneously adjusted selling prices, slightly increasing compared to normal days to compensate for costs and pay salaries to employees working throughout Tet.

Lao Cai traffic police use flycams to monitor pubs and handle alcohol concentration violations

|

Lao Cai - Road Traffic Police Team No. 3, Traffic Police Department of the Provincial Police uses flycams to detect and handle alcoholism during the Lunar New Year.

Cưỡng chế hơn 3.000m2 mặt bằng cao tốc tại Quảng Bình

CÔNG SÁNG |

Hơn 3.000m2 mặt bằng cao tốc Bắc – Nam qua huyện Lệ Thủy (tỉnh Quảng Bình) vừa được cưỡng chế thu hồi.

Mặt bằng cao tốc Bắc - Nam tại miền Trung: Nơi hoàn thành, chỗ gặp khó

CÔNG SÁNG - HƯNG THƠ |

Việc giải phóng mặt bằng cao tốc Bắc - Nam qua tỉnh Quảng Bình và Quảng Trị đến nay vẫn còn vướng. Trong khi một số địa phương đã hoàn thành công tác bàn giao mặt bằng, vẫn còn nơi đang gặp khó trong quá trình triển khai.

Giải pháp nào cho mặt bằng cao tốc Bắc - Nam qua Quảng Bình?

CÔNG SÁNG |

Tỉnh Quảng Bình sẽ cưỡng chế những trường hợp không đồng ý với chính sách bồi thường, giải phóng mặt bằng theo quy định của pháp luật tại cao tốc Bắc - Nam.