Many billion-dollar projects in Lao Cai are stuck in site clearance

Đinh Đại |

Through survey, in Lao Cai area, there are still many projects facing difficulties in the process of site clearance.

For example, the project to level the area of ​​Doi Co temple, Binh Minh ward, Lao Cai city with an area of ​​about 14.8 hectares, total investment of 350 billion VND.

The goal is to create a space to attract investment in construction of works and projects according to the plan; contribute to building Lao Cai city "Bright-Green-Clean-Beautiful", meeting the criteria of a type I urban area.

Mot so ho dan tai khu vuc den Co Doi da ban giao mat bang, tuy nhien nhieu ho van chua dong y do chua co tai dinh cu. Anh: Dinh Dai
Some households in the Co Doi temple area have handed over the land, but many households have not agreed because there has been no resettlement. Photo: Dinh Dai

During the implementation process, 340 households were affected, with a total of 288 resettlement lots.

The reason the project encountered difficulties was that the resettlement land fund had not been fully arranged, so households had not coordinated to count (only 10 lots/288 lots of land were arranged).

Along with that is the project to level the ground on both sides of D1 road, from Km0+750 - Km9+353 (intersection of Tran Hung Dao Avenue), in Binh Minh ward, Lao Cai city, with an area of ​​10.8 hectares, a total investment of 344.4 billion VND and about 190 households affected. Currently, only 63 households have been issued a notice of land recovery.

The project is also facing difficulties because households have not agreed to the census because they believe the compensation price is low.

Du an san gat mat bang hai ben duong D1cung lam canh kho khan trong giai phong mat bang. Anh: Dinh Dai
Du an san gat mat bang hai ben duong D1cung lam canh kho khan trong giai phong mat bang. Anh: Dinh Dai
The project to level both sides of D1 road is also facing difficulties in site clearance. Photo: Dinh Dai

In addition, the project's resettlement location is unclear, leading to difficulties in continuing to carry out statistical and inventory work for households that have been issued land recovery notices.

Next, we can mention the Ngoi Duong Stream Residential Area Infrastructure Project, the total land area within the project is 11.9 hectares with 143 households and individuals affected.

Currently, there are 6 households having problems with site clearance, 3 households have received compensation and resettlement land, but have not yet handed over the land because the request to hand over land to children arose after the time the main household had the decision to reclaim the land and before the main household received the resettlement land (because at the time of land reclamation, the project did not have a resettlement land fund).

Currently, payment has been made to 136/143 households, with a budget of 28.1 billion VND. The site has been handed over to 136/143 households.

Not only that, in Lao Cai city, there is also the Residential Area Project behind Block 2 Headquarters, the Technical Infrastructure Project behind Block II Headquarters, Lao Cai - Cam Duong New Urban Area in Group 10, Nam Cuong Ward. The project was approved in 2015 with an investment of more than 80 billion VND.

The land area within the project's recovery scope is about 3 hectares with 91 households affected. However, only 19/91 households have been inspected, counted for land recovery and approved for funding.

Du an nan suoi Ngoi Duong cung bi anh huong boi toc do giai phong mat bang. Anh: Dinh Dai
The Ngoi Duong stream straightening project is also affected by the speed of land clearance. Photo: Dinh Dai

It is known that land management faces many difficulties because households divide agricultural land plots in violation of regulations and build houses on agricultural land that has not been converted to residential land use.

Some households have land use right certificates and their houses are located within the clearance boundary. However, at the time of construction, the households did not have a permit application, leading to most of the houses being built in a location different from the issued land use right certificates.

From the above reality, it can be seen that the main reason is due to inappropriate regulations on compensation, support and resettlement payments, causing land clearance to be prolonged.

Do do, Pho Chu tich UBND tinh Lao Cai yeu cau day nhanh giai phong mat bang de thuc hien cac du an tren dia ban tinh. Anh: Dinh Dai
Vice Chairman of Lao Cai Provincial People's Committee requested to speed up site clearance to implement projects in the province. Photo: Dinh Dai

Regarding this, according to Vice Chairman of Lao Cai Provincial People's Committee Nguyen Trong Hai, localities need to organize propaganda, mobilization, and compliance in site clearance work. Regarding project resettlement, investors should consider reporting to the Provincial People's Committee on the policy of arranging resettlement locations for households that must move as a basis for project implementation.

"In case households still refuse to comply, complete the documents to organize enforcement according to prescribed procedures," informed the Vice Chairman of Lao Cai Provincial People's Committee.

Đinh Đại
TIN LIÊN QUAN

Hundred billion VND stadium in Lao Cai becomes buffalo grazing ground

|

Lao Cai - After 7 years of operation, Lao Cai province stadium with an investment capital of 146 billion VND has become a place for people to graze livestock.

Many infrastructure construction projects are stuck due to raw materials

|

In addition to large projects and national key projects, infrastructure construction projects across the country are being stalled due to material problems.

Increased protection for Mr. Trump and Ms. Harris during the US election

|

During the 2024 US presidential election, security was increased around the residences of Donald Trump and Kamala Harris as well as around the White House and the Capitol.

Timely rescue of a fisherman in an accident at sea

|

Ba Ria - Vung Tau - On the morning of November 5, the Command of Coast Guard Region 3 said it had just provided timely first aid to a fisherman of fishing boat BV 4643 TS who had an accident at sea.

What did the commune chairman say about sand mining causing landslides on the Cong River bank

|

Thai Nguyen - The sand and gravel mining activities of Mai Linh Construction Company Limited are taking place vigorously right next to the Cong River bank, causing landslides that need to be clarified.

Tornado appeared in Quang Tri during heavy rain

|

Quang Tri - The tornado appeared when it was raining heavily, fortunately it happened in a short time, so the damage was insignificant.

Cai luong artist died in collision with truck

|

In the eyes of many colleagues, cai luong artist Le Phuong is a gentle and emotional person.

Cận cảnh sân vận động trăm tỉ thành bãi thả trâu ở Lào Cai

Đinh Đại |

Sân vận động tỉnh Lào Cai được đầu tư với số vốn gần 150 tỉ đồng trên quy mô 75 ha, nhưng biến thành nơi chăn trâu do ít hoạt động thể thao được tổ chức.

Hundred billion VND stadium in Lao Cai becomes buffalo grazing ground

Đinh Đại |

Lao Cai - After 7 years of operation, Lao Cai province stadium with an investment capital of 146 billion VND has become a place for people to graze livestock.

Lan can đá tiền tỉ ở Lào Cai lộ bất thường sau bão số 3

Nhóm PV |

Lào Cai - Sau bão số 3, hệ thống lan can, vỉa hè và cây xanh thuộc dự án cải tạo cảnh quan 2 bên bờ sông Hồng bị hư hỏng nặng nề, qua đó lộ nhiều bất thường.