Non-stop construction on the Noi Bai - Lao Cai expressway construction site

Nhóm PV |

In the context of difficult construction, thousands of engineers and workers on the Noi Bai - Lao Cai expressway expansion project still maintain the construction pace to ensure progress.

In the early days of April, in the area of Dong Cuong commune, Lao Cai province, prolonged light rain made the construction site of Ngoi Buc bridge muddy. Vehicles carrying materials moved slowly, and machines sometimes had to "brace themselves" to overcome mud. However, the construction pace at the construction site has never slowed down.

Engineers and workers divide shifts to work continuously, taking advantage of each dry hour to speed up the construction progress of bridge piers before the peak of floods in 2026. Nearly ten bridge and underpass items belonging to package XL1-NBLC are also being deployed simultaneously.

Dự án mở rộng cao tốc Nội Bài – Lào Cai có tổng chiều dài 121km, tổng mức đầu tư gần 7.700 tỉ đồng. Ảnh: Hà Thắng
The Noi Bai - Lao Cai expressway expansion project has a total length of 121km, with a total investment of nearly 7,700 billion VND. Photo: An Trinh

In the roadbed sections from Km 142 to Km 152, the crushed gravel layer has been completed, the first asphalt strips have begun to be spread, gradually shaping the 4-lane expressway in the future.

Materials are scarce, but we have proactively implemented many plans to ensure supply and not interrupt construction," said engineer Tran Ngoc Duong, Site Commander.

Riêng phần đường đã triển khai 15 mũi thi công với tổng chiều dài hơn 57km. Ảnh: Duy Dũng
The road section alone has deployed 15 construction teams with a total length of more than 57km. Photo: An Trinh

Not far away, at package XL2-NBLC (Km 190-Km 209), the construction atmosphere is also no less bustling. From early morning to late at night, workers of Corporation 319 (Ministry of National Defense) are still clinging to each construction front, completing the roadbed, bridge and drainage system.

This is a section with complex terrain, the expansion from 2 lanes to 4 lanes with a roadbed width of 24m, adding a median strip requires a large amount of work. On the entire section, there are up to 8 bridges and 18 underpasses.

We maintain construction in 3 consecutive shifts to compensate for difficult terrain conditions. Up to this point, the progress is basically being well controlled" - engineer Ngo Tuan Nghia shared.

Công nhân giữ nhịp thi công, đảm bảo tiến độ dự án trước mùa mưa lũ. Ảnh: Hà Thắng
Workers maintain the construction pace, ensuring project progress before the rainy and flood season. Photo: An Trinh

The most important highlight of the project is Dai Viet tunnel, about 530m long, located in a complex hilly area. Currently, the tunnel is being constructed simultaneously from both sides to shorten the time.

No days off, construction teams work shifts continuously for 24 hours. The sound of drilling machines, explosions, and trucks transporting soil and rocks echoed non-stop in the heart of the mountain.

To date, the construction direction on the Hanoi side has been excavated more than 130m, and on the Lao Cai side about 132m. If the progress is maintained, it is expected that by the end of June 2026, the tunnel will be opened.

Nhiều đoạn nền đường thẳng tắp đã được phủ lớp nhựa đầu tiên. Ảnh: Duy Dũng
Many straight roadbed sections have been covered with the first layer of asphalt. Photo: Duy Dung
Các hạng mục cầu, hầm chui được đẩy nhanh tiến độ thi công. Ảnh: An Trịnh
Bridge and underpass items are being accelerated in construction progress. Photo: An Trinh

After more than 5 months of implementation, the entire project has reached over 40% of the volume. Many sections have been covered with the first layer of asphalt, bridges, culverts, taluy, and drainage ditches are gradually being completed, and the shape of the 4-lane expressway is increasingly clear.

Mr. Tran Ngoc Hai - Deputy Director of the Northern Expressway Project Management Board (Vietnam Expressway Development Investment Corporation) said: In mid-March, a delegation from the Vietnam Road Administration inspected the entire route and pointed out some shortcomings such as incomplete traffic signs, and some locations without nighttime warning systems.

Công tác bảo đảm an toàn giao thông trên tuyến đang khai thác cũng được siết chặt. Ảnh: Duy Dũng
Traffic safety assurance on the route is tightened. Photo: Duy Dung

Immediately after that, Vietnam Expressway Development Investment Corporation requested construction units to review and install additional signs, warning lights, reflective strips and adjust traffic speed appropriately.

It is expected that by the end of 2026, the completed road will contribute to meeting the increasing traffic demand on the Kunming - Lao Cai - Hanoi - Hai Phong economic corridor axis.

Thereby, promoting socio-economic development, opening the door to development for Lao Cai and the Northwest region.

Nhóm PV
RELATED NEWS

Scattered construction, Noi Bai - Lao Cai expressway poses risk of accidents

|

The construction process of expanding the Noi Bai - Lao Cai expressway is revealing a series of inadequacies, posing a potential risk of traffic unsafety.

Bustling construction of provincial road 153 leading to organic tea area in Lao Cai

|

Lao Cai - Provincial road 153 from Bac Ha commune to Ban Lien commune with an investment of more than 127 billion VND is bustling with construction to put it into use soon.

Worry about traffic unsafety at the Noi Bai - Lao Cai expressway expansion site

|

After many accidents occurred on the Noi Bai - Lao Cai expressway during construction, units have added a series of solutions to ensure safety.

Changing SIMs to new phones requires facial verification

|

From June 15, users when switching SIMs to another device will have to verify faces. If not completed, the subscriber will be temporarily suspended from the service according to the roadmap.

Explosives discovered near Russian gas pipeline, Hungary holds emergency meeting before elections

|

Hungary held an emergency meeting after Serbia discovered explosives with great destructive power only a few hundred meters from the Russian gas pipeline.

Party and State leaders, National Assembly deputies visit President Ho Chi Minh's Mausoleum

|

Party and State leaders, National Assembly deputies enter the Mausoleum to pay respects to President Ho Chi Minh before the opening session of the First Session of the 16th National Assembly.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Trump warns of destroying Iranian infrastructure

|

Mr. Trump on April 5 (local time) issued a warning that he would destroy Iran's important civilian infrastructure.

Scattered construction, Noi Bai - Lao Cai expressway poses risk of accidents

Bảo Nguyên |

The construction process of expanding the Noi Bai - Lao Cai expressway is revealing a series of inadequacies, posing a potential risk of traffic unsafety.

Bustling construction of provincial road 153 leading to organic tea area in Lao Cai

Đinh Đại |

Lao Cai - Provincial road 153 from Bac Ha commune to Ban Lien commune with an investment of more than 127 billion VND is bustling with construction to put it into use soon.

Worry about traffic unsafety at the Noi Bai - Lao Cai expressway expansion site

Đinh Đại |

After many accidents occurred on the Noi Bai - Lao Cai expressway during construction, units have added a series of solutions to ensure safety.