Khanh Hoa Provincial People's Committee has requested relevant departments, branches, sectors and localities to urgently hand over the land for the two expressway projects Van Phong - Nha Trang, Khanh Hoa - Buon Ma Thuot.
For the Van Phong - Nha Trang component project, Khanh Hoa Provincial People's Committee assigned localities where the expressway passes through to continue to mobilize remaining households to promptly hand over the site to the expressway construction unit and construct the rest stop at Km334+900; coordinate with the Department of Industry and Trade and Khanh Hoa Electricity Joint Stock Company to handle technical issues and adjust the design of power line relocation.
The Department of Natural Resources and Environment has instructed Project Management Board 7 (under the Ministry of Transport) to remove difficulties and obstacles related to the extension of the exploitation period of Ho Sau stone mine (Van Ninh district) to ensure the supply of construction materials for the project...
For Component Project 1 of the Khanh Hoa - Buon Ma Thuot Expressway Project, the Khanh Hoa Provincial People's Committee assigned the Ninh Hoa Town People's Committee to urgently review and summarize difficulties to find solutions, especially difficulties related to compensation and resettlement support according to the provisions of the 2024 Land Law.
The Khanh Hoa Province Traffic Construction Investment Management Board needs to make a list of priority locations for highway construction so that the Ninh Hoa Town People's Committee can focus resources on site clearance in these locations...
According to the report of the Department of Transport, up to now, the site clearance work of the Van Phong - Nha Trang Component Project has basically completed the main expressway route.
However, there is still 1.44km that has not been constructed due to technical infrastructure and site clearance problems. Regarding site clearance for the construction of the rest stop at Km334+900, Ninh Hoa Town People's Committee is implementing procedures for compensation, support, and land recovery, but the progress is still slow compared to requirements. Regarding the construction of resettlement areas, 6/6 resettlement areas serving the project have been basically completed...
For Component Project 1 of the Khanh Hoa - Buon Ma Thuot Expressway Project, up to now, Ninh Hoa Town Land Fund Development Center has handed over 28.17/31.5km of land; handed over 17/35 locations of the technical infrastructure system.
Regarding the construction of Ha Thanh resettlement area, the town has handed over 6.715ha/7.182ha of land. Regarding the progress of the highway construction, contractors are carrying out the items of leveling the ground, roadbed, drainage culverts of construction package No. 1 (KM0+00 - KM22+00) and construction package No. 2 (KM22+00 - KM32+00)...