Violations in Ba Ho - Ban Chua project, 13 individuals were disciplined

HƯNG THƠ |

QUANG TRI - Regarding serious violations in the Ba Ho - Ban Chua project, 13 related individuals and groups have initially been reviewed for responsibility.

Continue to review and handle responsibilities in accordance with regulations.

On October 1, regarding the violations in the Ba Ho - Ban Chua Irrigation System project (Ba Ho - Ban Chua project) that Lao Dong Newspaper had reported in articles, the People's Committee of Quang Tri province confirmed and clarified the causes leading to the violations.

Accordingly, in addition to objective causes related to site clearance, COVID-19 pandemic, natural disasters, scarcity and increase in material prices, there are subjective causes from the investor, contractor, and consulting unit - leading to the project not being completed according to the approved scale. As the project investor realizes, legal research is still limited and lacks uniformity, leading to self-organization of appraisal and approval of adjustments to construction drawing designs that do not meet regulations and have quality errors; construction supervision, contract management, quality management, and construction progress are not strict...

On August 2, 2024, the Quang Tri Provincial Construction Investment Project Management Board held a review meeting and agreed on the shortcomings, limitations, and shortcomings of the collective and individuals. However, this unit believes that the shortcomings, limitations, and shortcomings are not serious enough to require disciplinary action, so it only requires the relevant collectives and individuals to seriously review and learn from experience.

The Quang Tri Provincial Investment and Construction Project Management Board and the Planning - Technical and Project Management Departments of this unit seriously reviewed and learned from experience. 13 individuals reviewed and received the form of review and learned from experience, including Mr. Nguyen Thanh Binh - Director of the Quang Tri Provincial Investment and Construction Project Management Board; Mr. Duong Huu Trung, Tran Hoang Viet, Nguyen Van Hoang, Phan Anh, Nguyen Dinh Ha, Nguyen Quoc Dat...

However, to properly implement the order, process and form of review, the Provincial People's Committee requests relevant units to review and propose measures and forms of handling in accordance with regulations.

Must overcome, put the project into operation and effective use

The Ba Ho - Ban Chua project has a total investment after adjustment and supplementation of more than 262 billion VND, the implementation period is from 2018 to 2020 and has been allowed by the People's Committee of Quang Tri province to extend the project implementation period twice, until December 31, 2021.

Du an chua su dung da hu hong. Anh: Hung Tho.
The project has been damaged before it was used. Photo: Hung Tho

The project is tasked with providing water and creating a source to irrigate 80 hectares of the Winter-Spring crop, providing domestic water for 160 households; raising water levels, improving the ecological environment, and aquaculture, and includes 24 items implemented in 8 communes of Cam Lo district and 2 wards of Dong Ha city.

At the end of the project (December 31, 2021), the People's Committee of Quang Tri province proposed that central ministries and branches consider and report to the Prime Minister for permission to extend the implementation period, but so far it has not been approved.

By the time the collective and individuals met to review the above responsibilities, the project had only completed construction, handed over, put into operation and promoted investment efficiency for 13/24 works; 8/24 construction items had been completed but had not been accepted; 3/24 works had not been completed. In particular, some works had been completed and put into use but had been degraded, damaged, and not promoted their functions... Because of these violations, voters in Cam Lo district continuously expressed their opinions.

Faced with the situation of slow project implementation, limited investment efficiency, and waste of support resources from the Central Government, the People's Committee of Quang Tri province has directed the investor and related units to review and evaluate the overall situation of the project; identify the causes and promptly propose solutions to overcome existing problems and obstacles in order to soon complete and put the project into effective exploitation and use.

HƯNG THƠ
RELATED NEWS

National Assembly finalizes birth certificates, marriage certificates must be signed by the Chairman of the Commune People's Committee

|

The Law on Civil Status (amended) stipulates that the Chairman of the Commune-level People's Committee must directly sign birth certificates and marriage certificates.

Lao Cai gold - the first gold enterprise to list on the stock exchange fluctuates due to debt

|

Losing the right to exploit Minh Luong gold mine, accumulated losses exceeding charter capital, Lao Cai Gold Company is facing the most difficult period since listing on the stock exchange.

The role of trade unions in protecting workers in the digital transformation era

|

Quang Ninh - On the morning of April 23, in Bai Chay, the Vietnam General Confederation of Labor organized a workshop "Trade Unions innovate and improve the efficiency of occupational safety and health in the digital age".

Whales reappear, opening their mouths to hunt prey in Mui Ne sea

|

Lam Dong - People again see whales heading up to the sea surface and continuously opening their mouths to hunt prey in Mui Ne sea. This is the 2nd time in the past week.

It is necessary to soon have regulations on recalling and recycling used electric vehicle batteries

|

National Assembly deputies proposed to soon issue regulations requiring businesses producing, assembling, and importing electric vehicles to recall and recycle used batteries.

Minister of Finance: The tax threshold of 1 billion VND for business households is harmonious

|

Minister of Finance Ngo Van Tuan said that the taxable revenue threshold of 1 billion VND is harmonious, affecting the budget by about 7,000 billion VND.

Implementing data protection regulations, creating a safe and transparent digital environment

|

Lao Dong Newspaper organizes a seminar "Implementing data protection regulations, creating a safe and transparent digital environment".

Bad news

|

Ms. Hoang Thi Tia, born in 1936, from Thuong Tin commune, Hanoi city (Mother-in-law of comrade Nguyen Thu Ha - Head of the Social Work Department of Lao Dong Newspaper) passed away at 8:00 PM on April 22, 2026 (March 6, Binh Ngo year).

Khô khát bên loạt công trình của dự án Ba Hồ - Bản Chùa bỏ hoang

HƯNG THƠ |

Từ năm 2020, tỉnh Quảng Trị triển khai xây dựng dự án Hệ thống thủy lợi Ba Hồ - Bản Chùa có tổng mức đầu tư hơn 262 tỉ đồng. Sau 3 năm triển khai, hiện còn nhiều hạng mục là các công trình trạm bơm cấp nước tưới cho cây trồng cạn, nước sinh hoạt cho người dân dù đã hoàn thành cơ bản, nhưng vì có tồn tại hạn chế nên chưa được bàn giao sử dụng, hiện bỏ hoang, gây lãng phí.

Bao giờ các hạng mục dang dở dự án Ba Hồ - Bản Chùa đi vào hoạt động?

HƯNG THƠ |

Dự án Ba Hồ - Bản Chùa ở tỉnh Quảng Trị sử dụng nguồn vốn trung ương hỗ trợ theo Chương trình mục tiêu ứng phó với biến đổi khí hậu và tăng trưởng xanh. Dự án này có nhiều hạng mục dù đã thi công xong từ lâu nhưng hiện đang bỏ hoang, chưa đưa vào sử dụng.

Lãng phí nghiêm trọng nhiều hạng mục ở dự án Ba Hồ - Bản Chùa

HƯNG THƠ |

Dự án Ba Hồ - Bản Chùa tại tỉnh Quảng Trị được đầu tư hàng trăm tỉ đồng, nhưng tìm hiểu cho thấy, có không ít hạng mục chưa được nghiệm thu vì nhiều lý do, phơi mưa phơi nắng nhiều năm, gây lãng phí, bức xúc trong nhân dân.