Continue to review and handle responsibilities in accordance with regulations.
On October 1, regarding the violations in the Ba Ho - Ban Chua Irrigation System project (Ba Ho - Ban Chua project) that Lao Dong Newspaper had reported in articles, the People's Committee of Quang Tri province confirmed and clarified the causes leading to the violations.
Accordingly, in addition to objective causes related to site clearance, COVID-19 pandemic, natural disasters, scarcity and increase in material prices, there are subjective causes from the investor, contractor, and consulting unit - leading to the project not being completed according to the approved scale. As the project investor realizes, legal research is still limited and lacks uniformity, leading to self-organization of appraisal and approval of adjustments to construction drawing designs that do not meet regulations and have quality errors; construction supervision, contract management, quality management, and construction progress are not strict...
On August 2, 2024, the Quang Tri Provincial Construction Investment Project Management Board held a review meeting and agreed on the shortcomings, limitations, and shortcomings of the collective and individuals. However, this unit believes that the shortcomings, limitations, and shortcomings are not serious enough to require disciplinary action, so it only requires the relevant collectives and individuals to seriously review and learn from experience.
The Quang Tri Provincial Investment and Construction Project Management Board and the Planning - Technical and Project Management Departments of this unit seriously reviewed and learned from experience. 13 individuals reviewed and received the form of review and learned from experience, including Mr. Nguyen Thanh Binh - Director of the Quang Tri Provincial Investment and Construction Project Management Board; Mr. Duong Huu Trung, Tran Hoang Viet, Nguyen Van Hoang, Phan Anh, Nguyen Dinh Ha, Nguyen Quoc Dat...
However, to properly implement the order, process and form of review, the Provincial People's Committee requests relevant units to review and propose measures and forms of handling in accordance with regulations.
Must overcome, put the project into operation and effective use
The Ba Ho - Ban Chua project has a total investment after adjustment and supplementation of more than 262 billion VND, the implementation period is from 2018 to 2020 and has been allowed by the People's Committee of Quang Tri province to extend the project implementation period twice, until December 31, 2021.
The project is tasked with providing water and creating a source to irrigate 80 hectares of the Winter-Spring crop, providing domestic water for 160 households; raising water levels, improving the ecological environment, and aquaculture, and includes 24 items implemented in 8 communes of Cam Lo district and 2 wards of Dong Ha city.
At the end of the project (December 31, 2021), the People's Committee of Quang Tri province proposed that central ministries and branches consider and report to the Prime Minister for permission to extend the implementation period, but so far it has not been approved.
By the time the collective and individuals met to review the above responsibilities, the project had only completed construction, handed over, put into operation and promoted investment efficiency for 13/24 works; 8/24 construction items had been completed but had not been accepted; 3/24 works had not been completed. In particular, some works had been completed and put into use but had been degraded, damaged, and not promoted their functions... Because of these violations, voters in Cam Lo district continuously expressed their opinions.
Faced with the situation of slow project implementation, limited investment efficiency, and waste of support resources from the Central Government, the People's Committee of Quang Tri province has directed the investor and related units to review and evaluate the overall situation of the project; identify the causes and promptly propose solutions to overcome existing problems and obstacles in order to soon complete and put the project into effective exploitation and use.