Violations in Ba Ho - Ban Chua project, 13 individuals were disciplined

HƯNG THƠ |

QUANG TRI - Regarding serious violations in the Ba Ho - Ban Chua project, 13 related individuals and groups have initially been reviewed for responsibility.

Continue to review and handle responsibilities in accordance with regulations.

On October 1, regarding the violations in the Ba Ho - Ban Chua Irrigation System project (Ba Ho - Ban Chua project) that Lao Dong Newspaper had reported in articles, the People's Committee of Quang Tri province confirmed and clarified the causes leading to the violations.

Accordingly, in addition to objective causes related to site clearance, COVID-19 pandemic, natural disasters, scarcity and increase in material prices, there are subjective causes from the investor, contractor, and consulting unit - leading to the project not being completed according to the approved scale. As the project investor realizes, legal research is still limited and lacks uniformity, leading to self-organization of appraisal and approval of adjustments to construction drawing designs that do not meet regulations and have quality errors; construction supervision, contract management, quality management, and construction progress are not strict...

On August 2, 2024, the Quang Tri Provincial Construction Investment Project Management Board held a review meeting and agreed on the shortcomings, limitations, and shortcomings of the collective and individuals. However, this unit believes that the shortcomings, limitations, and shortcomings are not serious enough to require disciplinary action, so it only requires the relevant collectives and individuals to seriously review and learn from experience.

The Quang Tri Provincial Investment and Construction Project Management Board and the Planning - Technical and Project Management Departments of this unit seriously reviewed and learned from experience. 13 individuals reviewed and received the form of review and learned from experience, including Mr. Nguyen Thanh Binh - Director of the Quang Tri Provincial Investment and Construction Project Management Board; Mr. Duong Huu Trung, Tran Hoang Viet, Nguyen Van Hoang, Phan Anh, Nguyen Dinh Ha, Nguyen Quoc Dat...

However, to properly implement the order, process and form of review, the Provincial People's Committee requests relevant units to review and propose measures and forms of handling in accordance with regulations.

Must overcome, put the project into operation and effective use

The Ba Ho - Ban Chua project has a total investment after adjustment and supplementation of more than 262 billion VND, the implementation period is from 2018 to 2020 and has been allowed by the People's Committee of Quang Tri province to extend the project implementation period twice, until December 31, 2021.

Du an chua su dung da hu hong. Anh: Hung Tho.
The project has been damaged before it was used. Photo: Hung Tho

The project is tasked with providing water and creating a source to irrigate 80 hectares of the Winter-Spring crop, providing domestic water for 160 households; raising water levels, improving the ecological environment, and aquaculture, and includes 24 items implemented in 8 communes of Cam Lo district and 2 wards of Dong Ha city.

At the end of the project (December 31, 2021), the People's Committee of Quang Tri province proposed that central ministries and branches consider and report to the Prime Minister for permission to extend the implementation period, but so far it has not been approved.

By the time the collective and individuals met to review the above responsibilities, the project had only completed construction, handed over, put into operation and promoted investment efficiency for 13/24 works; 8/24 construction items had been completed but had not been accepted; 3/24 works had not been completed. In particular, some works had been completed and put into use but had been degraded, damaged, and not promoted their functions... Because of these violations, voters in Cam Lo district continuously expressed their opinions.

Faced with the situation of slow project implementation, limited investment efficiency, and waste of support resources from the Central Government, the People's Committee of Quang Tri province has directed the investor and related units to review and evaluate the overall situation of the project; identify the causes and promptly propose solutions to overcome existing problems and obstacles in order to soon complete and put the project into effective exploitation and use.

HƯNG THƠ
TIN LIÊN QUAN

Taking his child to do high school graduation exam procedures, father in Binh Dinh died, child seriously injured

|

Binh Dinh - Father drove a motorbike carrying his son to the high school graduation exam preparation point when he suddenly crashed into an electric pole, causing him to die on the spot and seriously injuring his son.

Mobilized with the message to 2k7 students before the graduation exam day of the principal in Nha Trang

|

Khanh Hoa - The principal of a high school in Nha Trang sent to 2k7 students with many emotions from the boat drivers before the special boat trip in 2025.

Hour 9: Unexpected meeting - Part 1

|

Hour 9 No. 160 - The wife waited for her missing husband for 10 years and then took another step. One day, if the husband returns, what will happen to this family?

Unbelievable confusion on the day of completing the procedures for taking the high school graduation exam in Hanoi

|

Hanoi - Some candidates confused the exam scores between My Dinh High School and My Dinh 1 Secondary School in the afternoon to complete the procedures for taking the high school graduation exam.

HCMC will auction land along 5 metro lines, expected to collect 152,000 billion VND

|

Ho Chi Minh City plans to collect about VND152,000 billion from the auction of land along 5 metro lines, including lines 1, 2, 3a, 4 and 5.

Bac Kan Secretary Hoang Duy Chinh becomes a member of the National Assembly Standing Committee

|

Mr. Hoang Duy Chinh - Secretary of the Bac Kan Provincial Party Committee was elected by the National Assembly to hold the position of Member of the National Assembly Standing Committee.

The Government finalizes the plan to merge 2 corporations into VNPT

|

Telecommunication Services Corporation, Communications Corporation officially merged into the Parent Company - Vietnam Post and Telecommunication Group (VNPT Group).

Khô khát bên loạt công trình của dự án Ba Hồ - Bản Chùa bỏ hoang

HƯNG THƠ |

Từ năm 2020, tỉnh Quảng Trị triển khai xây dựng dự án Hệ thống thủy lợi Ba Hồ - Bản Chùa có tổng mức đầu tư hơn 262 tỉ đồng. Sau 3 năm triển khai, hiện còn nhiều hạng mục là các công trình trạm bơm cấp nước tưới cho cây trồng cạn, nước sinh hoạt cho người dân dù đã hoàn thành cơ bản, nhưng vì có tồn tại hạn chế nên chưa được bàn giao sử dụng, hiện bỏ hoang, gây lãng phí.

Bao giờ các hạng mục dang dở dự án Ba Hồ - Bản Chùa đi vào hoạt động?

HƯNG THƠ |

Dự án Ba Hồ - Bản Chùa ở tỉnh Quảng Trị sử dụng nguồn vốn trung ương hỗ trợ theo Chương trình mục tiêu ứng phó với biến đổi khí hậu và tăng trưởng xanh. Dự án này có nhiều hạng mục dù đã thi công xong từ lâu nhưng hiện đang bỏ hoang, chưa đưa vào sử dụng.

Lãng phí nghiêm trọng nhiều hạng mục ở dự án Ba Hồ - Bản Chùa

HƯNG THƠ |

Dự án Ba Hồ - Bản Chùa tại tỉnh Quảng Trị được đầu tư hàng trăm tỉ đồng, nhưng tìm hiểu cho thấy, có không ít hạng mục chưa được nghiệm thu vì nhiều lý do, phơi mưa phơi nắng nhiều năm, gây lãng phí, bức xúc trong nhân dân.