Sa Pa Airport construction schedule delayed by another year

Đinh Đại |

Lao Cai - Since breaking ground in 2022, the 7,000 billion VND Sa Pa airport construction project has continued to miss its scheduled start date.

According to the Lao Dong Newspaper's reporter in early December, dozens of houses in the planning area, subject to site clearance in Cam Con commune, Bao Yen district, Lao Cai province, were dismantled and demolished to implement the Sa Pa airport project.

Through observation, around the project area, the construction site has cleared a large volume.

Nha cua, truong hoc cua nguoi dan deu da giai duoc giai phong de phuc vu viec trien khai xay dung san bay Sa Pa. Anh: Dinh Dai
Schools and people's houses have been liberated to serve the construction of Sa Pa airport. Photo: Dinh Dai

According to research, hundreds of households in Cam Con commune have given up their land to serve the Sa Pa airport construction project. Currently, these households have been moved to a new, clean and beautiful resettlement site.

However, since the project's groundbreaking in 2022, now the last month of 2024, this trillion-dollar airport super project has remained motionless.

Mr. Nguyen Van Toan (Cam Con commune, Bao Yen district) wondered: "People in the commune are very sympathetic and supportive of the construction of Sa Pa airport. But I don't understand why, even though the land is available, there is still no activity."

According to Mr. Toan, most of the households whose land had to be cleared moved to new resettlement areas near the riverbank. Many families built spacious houses after receiving compensation...

Nhung ngoi nha khang trang duoc nguoi dan xay dung canh cao toc Noi Bai - Lao Cai tai vi tri tai dinh cu moi. Anh: Dinh Dai
Spacious houses were built by people next to Noi Bai - Lao Cai highway at the new resettlement site. Photo: Dinh Dai

It is known that on October 21, 2021, the Prime Minister decided on the investment policy for the Sa Pa airport construction project under the PPP (public-private partnership) form.

The project is divided into 2 investment phases, in which phase 1 - construction of Sa Pa airport to meet the standards of a level 4C airport and a level II military airport, reaching a capacity of 1.5 million passengers/year; phase 2 will complete the project items to reach a capacity of 3 million passengers/year.

The project implementation period is 50 years, of which the construction period is 4 years; the operation, exploitation and capital recovery period is 46 years. Phase 1 of the project will be implemented from 2021; Phase 2 will be implemented after 2028.

Sa Pa Airport has a land use area of ​​371 hectares with a total investment capital of nearly 7,000 billion VND. Of which, the State capital accounts for about 2,700 billion VND, the rest is capital mobilized by investors.

Du an dong tho nam 2022, nhung den nay van chua tim duoc nha dau tu. Anh: Dinh Dai
The project is scheduled to break ground in 2022, but has yet to find an investor. Photo: Dinh Dai

On December 9, speaking to a reporter from Lao Dong Newspaper, Chairman of Cam Con Commune People's Committee Ho Viet Hung said: "The commune government coordinated and promoted land clearance for the project. Up to now, most households have agreed to hand over land and move to the new resettlement area. However, after many years of having land, the airport has not been able to start construction. Therefore, households have taken advantage of farming and agricultural cultivation."

According to the Chairman of Cam Con Commune People's Committee, the start date of the project depends on the district and province, the commune does not know. Regarding the cultivation of the people, the locality also creates favorable conditions, when the project is implemented, the people will return the land.

Many houses were built in the resettlement area after land clearance.

The leader of Lao Cai Province's Department of Transport informed that the project could not be implemented because it could not find a partner despite two bidding invitations. The reason was that businesses found the investment capital to be large and it was difficult to make a profit, so they did not do it.

"It is impossible to start construction in 2024 and complete it by the middle of next year. We are striving to attract investors so that we can start the project in early 2025," the representative added.

Đinh Đại
TIN LIÊN QUAN

More than 1,000m3 of soil collapsed at Sa Pa airport bypass

|

Lao Cai - Many landslides and subsidence locations on the Sa Pa airport bypass road make travel difficult for people.

Why ChatGPT is Having Global Issues

|

ChatGPT has experienced a global outage that has left users unable to access and use it.

There are still shortcomings in issuing retail invoices for gasoline and oil

|

The issuance of electronic invoices for each sale at gas stations has been actively implemented by many businesses, but there are still shortcomings.

Audience spent tens of millions of dong to watch Anh Trai's concert in Hung Yen

|

As December 14 approaches, the audience is ready to burn out at the Call Me by Fire concert held in Hung Yen.

Maintain the "green, clean, beautiful" movement at the workplace for employees

|

Over the years, union members of the Hanoi Construction Trade Union have always been active in environmental protection work, maintaining a "green, clean, and beautiful" workplace.

7,000 billion VND airport bypass in Lao Cai eroded after storm and flood

|

Lao Cai - Many landslides and subsidence points on the Sa Pa Airport bypass road make it difficult for people to travel.

Ministry of Health warns of "mysterious" disease appearing in Congo

|

"Mysterious" epidemic in Congo causes 406 cases, including 31 deaths.

Farmers worried about volatile coffee prices

|

Dak Lak is considered the coffee capital of Vietnam. This year’s harvest, people here are both happy and worried because coffee prices are constantly fluctuating unpredictably.

More than 1,000m3 of soil collapsed at Sa Pa airport bypass

Đinh Đại |

Lao Cai - Many landslides and subsidence locations on the Sa Pa airport bypass road make travel difficult for people.

Tây Bắc cuối ngày: Lý do sân bay Sa Pa chưa thể khởi công

Nhóm PV |

Sân bay Sa Pa chưa thể khởi công; Đường nông thôn mới dùng đã hỏng; Phú Thọ tìm nhà thầu dự án 75 tỉ đồng là một số tin tức nổi bật.

2 lần mời thầu vẫn "ế", sân bay Sa Pa lại lỗi hẹn khởi công

Đinh Đại |

Lào Cai - Sau ba năm kể từ khi được phê duyệt chủ trương đầu tư, dự án xây dựng sân bay Sa Pa 7.000 tỉ đồng vẫn khó thể khởi công trong năm 2024 như mong muốn.