The super project to prevent tides in Ho Chi Minh City is about to reach the finish line after 6 years of delay.

MINH QUÂN |

The super tidal dam project in Ho Chi Minh City with a total investment of nearly 10,000 billion VND, after being delayed for 6 years, has been targeted for completion on April 30, 2025.

" The project to solve flooding caused by high tides in Ho Chi Minh City area taking into account climate change factors" has just been included by the Ho Chi Minh City People's Committee in the list of typical city-level projects competing to celebrate the 50th anniversary of the Liberation of the South and National Reunification Day (April 30, 1975 - April 30, 2025).

Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong was assigned to be in charge of the project with the goal of completing it by April 30, 2025.

The project started in mid-2016 and is expected to be completed in 2018 to control tidal flooding and respond to climate change over an area of ​​570 km², serving about 6.5 million people along the Saigon River and the central area of ​​Ho Chi Minh City.

However, the project has been delayed for up to 6 years, although the project is now more than 90% complete. The project construction process has been suspended three times, the first time lasting 10 months, the second time for 8 months and the most recent time from November 15, 2020 to present.

According to Trung Nam Construction Investment Joint Stock Company (investor), many procedural problems have not been resolved. Notably, the total investment of the project has not been adjusted.

Investors calculate that the total investment is expected to increase from VND 9,976 billion to VND 14,398 billion . Interest alone, by July 26, 2024, has reached VND 2,369 billion, with an average daily interest rate of more than VND 1.7 billion.

In early May 2024, BIDV Bank - the intermediary unit receiving re-lending capital from the State Bank to finance Trung Nam Company to implement the project, announced that the investor's loan of VND 7,095 billion was overdue for principal payment of VND 6,008 billion and interest debt of VND 1,715 billion.

Tan Thuan tidal sluice (Districts 4 and 7). Photo: Minh Quan
Tan Thuan tidal sluice (Districts 4 and 7). Photo: Minh Quan

In addition, the issue of land fund payment to investors has not been implemented by the Ho Chi Minh City People's Committee. Although there are no specific regulations on the payment ratio in land fund and cash, the Ho Chi Minh City People's Committee signing a BT (build - transfer) contract with a land fund payment ratio of only 16% of the total project cost, the rest in cash, has been assessed as not entirely appropriate.

In April 2023, when working with the Prime Minister, Ho Chi Minh City proposed to allow the city to balance its own land fund and budget capital to pay for BT contracts, not applying the fixed rate of 16% in land and 84% in cash as before. For the interest incurred, the city will negotiate with the investor and can pay with land fund.

Ho Chi Minh City wants to complete the super tide prevention project by 2025. Photo: Minh Quan
Ho Chi Minh City wants to complete the super tide prevention project by 2025. Photo: Minh Quan

The Government has also established a special task force to resolve the project’s problems. The task force has proposed three options, of which the option of entrusting the budget for investors to continue borrowing and completing the project is considered the most feasible.

According to Mr. Quach Ngoc Tuan - Deputy Director of the Department of Planning and Investment of Ho Chi Minh City, the city has reported to the Government Working Group on the difficulties in paying for BT contracts, as well as proposed solutions to issue a new Resolution. This is to remove obstacles in payment mechanisms, mobilize capital to complete the project, adjust the total investment, etc.

Mr. Tuan also emphasized that if the difficulties are resolved, the investor commits to completing the project within 6 to 8 months from the date of disbursement.

MINH QUÂN
TIN LIÊN QUAN

Dự án ngăn triều 10.000 tỉ ở TPHCM tăng lên 14.000 tỉ và tăng bao nhiêu nữa

Lê Thanh Phong |

Theo tính toán của nhà đầu tư, việc tạm dừng và kéo dài quá lâu khiến tổng mức đầu tư dự án ngăn triều 10.000 tỉ đồng đã tăng lên hơn 14.000 tỉ đồng.

Chủ tịch UBND TPHCM nói dự án ngăn triều 10.000 tỉ đồng là vấn đề nhức nhối

MINH QUÂN |

TPHCM - Trả lời cử tri về dự án ngăn triều 10.000 tỉ đồng hoàn thành hơn 90% nhưng “đắp chiếu” gần 4 năm qua, Chủ tịch UBND TPHCM Phan Văn Mãi cho biết, so với lần tiếp xúc cử tri trước, đến nay, dự án không có gì tiến triển hơn và đây là vấn đề nhức nhối.

Toàn cảnh dự án ngăn triều 10.000 tỉ đồng chờ gỡ vướng bước cuối để về đích

MINH QUÂN |

TPHCM - Dự án ngăn triều gần 10.000 tỉ đồng đã hoàn thành hơn 93% khối lượng. Vướng mắc lớn nhất của dự án là phụ lục hợp đồng gia hạn thời gian hoàn thành đã được ký. Dự án đang đợi phía Ngân hàng Nhà nước và ngân hàng BIDV làm các thủ tục, giải ngân để tái khởi động hoàn thành công việc còn lại.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

Ngầm tràn ngập sâu, Quảng Bình cảnh báo dân không di chuyển

CÔNG SÁNG |

Do ảnh hưởng bão số 4, từ 7 giờ sáng 20.9, địa bàn tỉnh Quảng Bình vẫn còn nhiều ngầm tràn nước ngập sâu, chảy xiết và chia cắt cục bộ.