Vinh Long Provincial Department of Construction proposes to remove difficulties for Dinh Khao bridge project

Quyên Phạm |

Vinh Long - The Dinh Khao bridge project has encountered many difficulties in the implementation process, the Department of Construction has proposed solutions to remove difficulties.

On July 15, a source from a reporter from Lao Dong Newspaper said that Mr. Nguyen Quoc Huy - Deputy Director of the Department of Construction of Vinh Long province - had just signed report No. 11 to the Provincial People's Committee, informing about the progress of the investment project to build Dinh Khao bridge under the form of public-private partnership (PPP).

According to the report, by July 5, 2025, the Department of Construction had submitted Document No. 02/TTr-SXD to the Board of Appraisal at the grassroots level on the appraisal of the Feasibility Study Report of the Dinh Khao Bridge Construction Investment Project under the public-private partnership method. It is expected that from now until July 20, 2025, the grassroots appraisal council will review and submit for approval the project Feasibility Study Report, announce the Dinh Khao bridge project in the form of public-private partnership.

According to the Department of Construction of Vinh Long province, the work to be carried out in the coming time is as follows: Organizing the selection of investors to implement the project; Establishing enterprises to implement PPP projects, negotiating PPP contracts; Organizing the implementation of surveys, technical design of projects; Organizing the selection of construction contractors, supervision consultants, project management consultants; Organizing site clearance work.

 Nguoi dan mong moi som trien khai xay dung cau Dinh Khao hoan thanh va dua vao su dung de thay the pha Dinh Khao. Anh: Quyen Pham
People hope to soon deploy the construction of Dinh Khao bridge and put it into use to replace Dinh Khao ferry across Co Chien river. Photo: Quyen Pham

During the implementation of the Dinh Khao bridge project, there were difficulties and problems such as: The Dinh Khao bridge project is the first project in the province to be invested in the form of PPP, so departments, branches and localities do not have experience; at the same time, relevant legal documents at this time are constantly changing, so there needs to be time to study, leading to some prolonged work. On the other hand, during the implementation process, many situations arose that departments, branches and localities did not foresee, leading to a prolonged time. The appraisal work of the council has been basically completed (respected on May 8, 2025, and the appraisal results report was released on May 19, 2025).

According to a preliminary survey, the number of houses affected by the Dinh Khao bridge project that had to be cleared was about 78. To approve the compensation plan, the number of households affected by the clearance must be resettled. Currently, the Management Board of Civil and Industrial Projects of Vinh Long province (formerly the Management Board of Vinh Long province) is adjusting the investment policy (due to the relocation from Mang Thit district) to report on the feasibility study of the Mang Thit District Residential Area, Resettlement and Social Housing Project (phase 1) as prescribed in Clause 6, Article 91 of the 2024 Land Law.

The Department of Construction proposed that the People's Committee of Vinh Long province consider promptly completing and organizing a meeting of the Steering Committee for the implementation of the Dinh Khao bridge project, the meeting is expected to be held in July 2025, to promptly direct the resolution of difficulties and problems.

In addition, the Provincial People's Committee has established the Vinh Long Provincial Traffic Project Management Board, therefore, the Department of Construction recommends that the Provincial People's Committee assign the Vinh Long Provincial Traffic Project Management Board to carry out the next steps of the project after the project is approved. At the same time, it is recommended that the People's Committee of Vinh Long province direct the Management Board of Civil and Industrial Projects of Vinh Long province to preside over and coordinate with relevant departments, branches and units to urgently deploy the construction of a resettlement area for the Dinh Khao bridge construction investment project.

In addition, the Department also recommended that the People's Committee of Vinh Long province assign the Department of Finance to preside over and coordinate with relevant departments, branches and units to urgently study and draft PPP contracts to implement the Dinh Khao bridge project, because this is the basis for organizing the selection of investors.

Quyên Phạm
TIN LIÊN QUAN

Looking forward to Dinh Khao bridge connecting the two banks of Vinh Long - Ben Tre

|

Ben Tre - Dinh Khao Bridge, a key project connecting Ben Tre and Vinh Long, promises to solve traffic congestion at Dinh Khao ferry.

Dinh Khao ferry traffic jam stretches over 1.5 km

|

Vinh Long - At noon on January 18, a traffic jam of more than 1.5 km occurred at Dinh Khao Ferry, in the direction from Cho Lach (Ben Tre province) to Vinh Long.

Super-small neighborhood in the heart of Ho Chi Minh City has a fire fighting system, people are still not assured

|

HCMC - Although the micro-neighborhood in the middle of HCMC has been installed with a fire fighting system by the locality, people are still worried about the risk of fire and explosion, so they open additional escape routes themselves.

Dead pigs dumped on the streets of Hanoi, Ministry of Agriculture and Environment speaks out

|

The Deputy Minister of Agriculture and Environment requested to resolutely prevent the situation of throwing dead pigs onto the road, causing the spread of the epidemic.

Top 10 localities with the most scores in 10 Math subjects, Hanoi leads

|

In the 2025 high school graduation exam, Hanoi is the leading locality in the country in terms of 10 points in Math.

Associate high school graduation exam scores: No 10 Literature scores

|

The Ministry of Education and Training has announced the scores for the 2025 high school graduation exam. Literature did not record a score of 10.

Experts: Can consider supporting 30 - 50% of the cost of buying electric vehicles for people

|

Experts say that it is necessary to soon have solutions to support people to switch to electric vehicles when banning gasoline motorbikes from entering Hanoi's Ring Road 1.

Looking forward to Dinh Khao bridge connecting the two banks of Vinh Long - Ben Tre

Thành Nhân |

Ben Tre - Dinh Khao Bridge, a key project connecting Ben Tre and Vinh Long, promises to solve traffic congestion at Dinh Khao ferry.

Dinh Khao ferry traffic jam stretches over 1.5 km

Thành Nhân |

Vinh Long - At noon on January 18, a traffic jam of more than 1.5 km occurred at Dinh Khao Ferry, in the direction from Cho Lach (Ben Tre province) to Vinh Long.

Hơn 1.200 tỉ đồng làm 7km đường dẫn cầu Đình Khao

Tạ Quang |

Vĩnh Long - Dự án làm đường dẫn cầu Đình Khao chiều dài tuyến khoảng 7km có tổng mức đầu tư hơn 1.200 tỉ đồng nguồn vốn từ ngân sách trung ương và ngân sách tỉnh. Dự án quy mô đường cấp III đồng bằng.