Speed ​​up the construction of a 20,400 billion VND expressway in Quang Ngai - Hoai Nhon

VIÊN NGUYỄN |

Quang Ngai has handed over 100% of the clean ground for the Quang Ngai - Hoai Nhon expressway . Currently, the contractor is speeding up construction, with the goal of having the technical route open by the end of 2025.

The Quang Ngai - Hoai Nhon expressway section is 88km long, passing through Quang Ngai province (60.3km) and Binh Dinh (27.7km). This is the project with the largest total investment and scale among the 12 component projects. Total investment: 20,400 billion VND, of which construction value is 14,400 billion VND. Investor: Project Management Board 2 (Ministry of Transport). General construction contractor: Deo Ca Group.

The entire project deployed 45 construction steps, mobilizing nearly 4,000 personnel and more than 1,700 machinery and equipment to the construction site. Photo: Vien Nguyen
The entire project deployed 45 construction steps, mobilizing nearly 4,000 personnel and more than 1,700 machinery and equipment to the construction site. Photo: Vien Nguyen

According to information Deo Ca Group provided to reporters of Lao Dong Newspaper, the entire project has deployed 45 construction steps, mobilizing nearly 4,000 personnel and more than 1,700 machinery and equipment to the construction site. All 3 bidding packages (XL1, XL2, XL3) are constructed in 3 shifts. As for the tunnel items, the contractor carries out construction continuously 24/24, with engineers and workers taking turns working non-stop.

At package XL01, contractors mobilized nearly 500 pieces of equipment and more than 1,100 engineers and workers, deploying 11 road construction tasks, including excavation works, soft soil treatment, K95 foundation filling, and material filling. granular K95, K98,... In particular, the average daily volume of K95 embankment is nearly 30,000m³, it is expected that by September 30, soil embankment will be completed.

Sharing with reporters, Mr. Tran Van Chi - Commander of the XL01 package said that the contractor is determined to complete the road embankment by September 2024, bringing the project to the finish line in 2025. Immediately after handing over the site. , the contractor already has one and a half times more motorbikes and equipment than required to speed up progress. For the asphalt concrete item, the contractor is also focusing on designing and commissioning the station. The plan is to cover the first meters of package XL01 by the end of August 2024.

According to the reporter, at the XL02 package passing through Duc Pho town and the XL03 package is about 30.8km long, extending from Duc Pho town to Hoai Nhon town, currently on the construction site, contractors mobilize hundreds of machinery, with about 1,450 employees, working day and night on the project.

All 3 bidding packages (XL1, XL2, XL3) are constructed in 3 shifts, especially for tunnel items, the contractor performs construction continuously 24/24, engineers and workers take shifts to work continuously. stop. Photo: Vien Nguyen
Engineers and workers work in shifts without stopping. Photo: Vien Nguyen

Talking to reporters, Mr. Ngo Van Dung - Director of the Provincial Transportation Construction Investment Project Management Board said that the unit is accelerating the progress to complete the entire relocation of the works. public area within the construction scope of the main Quang Ngai - Hoai Nhon expressway, ensuring it does not affect the construction progress of the contractors.

Sharing with reporters, Mr. Nguyen Quang Huy - Deputy General Director of Deo Ca Group said that in order to complete the K95 soil embankment before the rainy season and complete tunnels No. 1 and No. 2 before December 31, 2024, the contractor has added Added 7 new construction jobs at the cutting scope, reducing the volume of contractors behind schedule. Mobilizing 13 cement concrete mixing plants along the route to serve the construction of cement reinforced aggregate layer. The output of the entire project reached nearly 5,200 billion VND, equivalent to more than 38% of the total volume.

VIÊN NGUYỄN
TIN LIÊN QUAN

Quảng Ngãi nỗ lực gỡ khó các dự án giao thông nghìn tỉ đồng

VIÊN NGUYỄN |

Nhiều dự án giao thông nghìn tỉ đồng ở Quảng Ngãi đang vướng do người dân vẫn chưa đồng ý nhận tiền bồi thường, bàn giao mặt bằng.

Quảng Ngãi đặt mục tiêu hình thành Trung tâm Lọc hóa dầu

VIÊN NGUYỄN |

Quảng Ngãi đề nghị Bộ Công Thương tạo điều kiện để tỉnh hình thành Trung tâm Lọc hóa dầu và Năng lượng quốc gia ở Khu kinh tế Dung Quất.

Từ chối nhận tiền bồi thường Dự án cao tốc Quảng Ngãi - Hoài Nhơn vì khung giá quá thấp

Viên Nguyễn |

Hàng chục hộ dân với hàng trăm nhân khẩu ở xã Nghĩa Kỳ, huyện Tư Nghĩa, tỉnh Quảng Ngãi chấp nhận tháo dỡ nhà cửa để nhường đất làm dự án cao tốc Quảng Ngãi - Hoài Nhơn nhưng không nhận tiền đền bù vì cho rằng, khung giá bồi thường quá thấp. Không còn nhà cửa, họ phải dựng lều, thuê nhà để ở, rơi vào tình cảnh khổ sở.

Trực tiếp bóng đá Argentina 2-0 Bolivia: Martinez nhân đôi cách biệt

tam nguyên |

Trực tiếp trận Argentina vs Bolivia lúc 07h00 ngày 16.10, tại vòng loại World Cup 2026 khu vực Nam Mỹ.

Ông Trump nhún nhảy 40 phút trong cuộc vận động tranh cử

Song Minh |

Cựu Tổng thống Donald Trump kết thúc cuộc vận động tranh cử ở Pennsylvania bằng cách nhún nhảy theo nhạc suốt 40 phút.

Vàng phát huy vai trò như một loại tiền tệ toàn cầu

Phương Anh (Theo Kitco) |

Theo Kitco - trước diễn biến căng thẳng địa chính trị, các ngân hàng trung ương có thể sử dụng vàng để thanh toán thương mại quốc tế.

Hezbollah kêu gọi ngừng bắn, nếu không sẽ giáng đòn "đau đớn"

Bùi Đức |

Hezbollah quyết giáng một đòn “đau đớn” lên Israel nếu chiến tranh vẫn tiếp tục ở Lebanon.

Nhạc sĩ Nguyễn Văn Chung nói về "ca sĩ giàu nhờ 1 bài hát"

Nhóm Pv |

Nhạc sĩ Nguyễn Văn Chung tiết lộ việc ca sĩ/nhạc sĩ giàu lên, mua nhà mua xe bằng 1 bản hit là điều có thể.

Quảng Ngãi nỗ lực gỡ khó các dự án giao thông nghìn tỉ đồng

VIÊN NGUYỄN |

Nhiều dự án giao thông nghìn tỉ đồng ở Quảng Ngãi đang vướng do người dân vẫn chưa đồng ý nhận tiền bồi thường, bàn giao mặt bằng.

Quảng Ngãi đặt mục tiêu hình thành Trung tâm Lọc hóa dầu

VIÊN NGUYỄN |

Quảng Ngãi đề nghị Bộ Công Thương tạo điều kiện để tỉnh hình thành Trung tâm Lọc hóa dầu và Năng lượng quốc gia ở Khu kinh tế Dung Quất.

Từ chối nhận tiền bồi thường Dự án cao tốc Quảng Ngãi - Hoài Nhơn vì khung giá quá thấp

Viên Nguyễn |

Hàng chục hộ dân với hàng trăm nhân khẩu ở xã Nghĩa Kỳ, huyện Tư Nghĩa, tỉnh Quảng Ngãi chấp nhận tháo dỡ nhà cửa để nhường đất làm dự án cao tốc Quảng Ngãi - Hoài Nhơn nhưng không nhận tiền đền bù vì cho rằng, khung giá bồi thường quá thấp. Không còn nhà cửa, họ phải dựng lều, thuê nhà để ở, rơi vào tình cảnh khổ sở.