The Quang Ngai - Hoai Nhon expressway section is 88km long, passing through Quang Ngai province (60.3km) and Binh Dinh (27.7km). This is the project with the largest total investment and scale among the 12 component projects. Total investment: 20,400 billion VND, of which construction value is 14,400 billion VND. Investor: Project Management Board 2 (Ministry of Transport). General construction contractor: Deo Ca Group.
According to information Deo Ca Group provided to reporters of Lao Dong Newspaper, the entire project has deployed 45 construction steps, mobilizing nearly 4,000 personnel and more than 1,700 machinery and equipment to the construction site. All 3 bidding packages (XL1, XL2, XL3) are constructed in 3 shifts. As for the tunnel items, the contractor carries out construction continuously 24/24, with engineers and workers taking turns working non-stop.
At package XL01, contractors mobilized nearly 500 pieces of equipment and more than 1,100 engineers and workers, deploying 11 road construction tasks, including excavation works, soft soil treatment, K95 foundation filling, and material filling. granular K95, K98,... In particular, the average daily volume of K95 embankment is nearly 30,000m³, it is expected that by September 30, soil embankment will be completed.
Sharing with reporters, Mr. Tran Van Chi - Commander of the XL01 package said that the contractor is determined to complete the road embankment by September 2024, bringing the project to the finish line in 2025. Immediately after handing over the site. , the contractor already has one and a half times more motorbikes and equipment than required to speed up progress. For the asphalt concrete item, the contractor is also focusing on designing and commissioning the station. The plan is to cover the first meters of package XL01 by the end of August 2024.
According to the reporter, at the XL02 package passing through Duc Pho town and the XL03 package is about 30.8km long, extending from Duc Pho town to Hoai Nhon town, currently on the construction site, contractors mobilize hundreds of machinery, with about 1,450 employees, working day and night on the project.
Talking to reporters, Mr. Ngo Van Dung - Director of the Provincial Transportation Construction Investment Project Management Board said that the unit is accelerating the progress to complete the entire relocation of the works. public area within the construction scope of the main Quang Ngai - Hoai Nhon expressway, ensuring it does not affect the construction progress of the contractors.
Sharing with reporters, Mr. Nguyen Quang Huy - Deputy General Director of Deo Ca Group said that in order to complete the K95 soil embankment before the rainy season and complete tunnels No. 1 and No. 2 before December 31, 2024, the contractor has added Added 7 new construction jobs at the cutting scope, reducing the volume of contractors behind schedule. Mobilizing 13 cement concrete mixing plants along the route to serve the construction of cement reinforced aggregate layer. The output of the entire project reached nearly 5,200 billion VND, equivalent to more than 38% of the total volume.