Inspection of the resettlement project in Hoa Binh discovered a series of violations

Đặng Tình - Khánh Linh |

Hoa Binh - The Inspectorate has just concluded the implementation of the Project to stabilize the population in the disaster-hit area of ​​Loi village, Phu Vinh commune, Tan Lac district.

A series of violations are pointed out

Recently, the Hoa Binh Provincial Inspectorate has just issued an Inspection Conclusion on the implementation of the Project to stabilize the population in natural disaster areas in Loi hamlet, Phu Vinh commune, Tan Lac district.

Through inspection, it was found that for compensation, support and resettlement, Tan Lac District People's Committee did not notify or issue land recovery decisions according to regulations.

Regarding construction investment, the inspection discovered an error of 278 million VND. In particular, the estimate did not adjust the distance of stone transportation by dump truck, leading to acceptance and overpayment of the value of the volume of stone transported by dump truck within a range of over 1,000m by 12-ton truck with amount of 261 million VND.

In addition, violations of project management costs were 5 million VND, construction supervision consulting costs were 5 million VND, design consulting costs, and preparation of technical and economic reports were 6.6 million VND. .

"For the above errors to occur, the main responsibility belongs to the Investor implementing the project; the District Compensation, Support and Resettlement Council in advising on the implementation of compensation, resettlement support, responsibility of the Department of Natural Resources and Environment of Tan Lac district and relevant individuals" - the conclusion clearly states.

Regarding remedial work, in February 2024, during the process of reviewing the implementation of granting land use rights certificates to households in Loi hamlet, Phu Vinh commune, the District People's Committee discovered a number of cases where households had receive compensation and support for land areas but do not actually have to recover land to implement the project.

The District People's Committee has issued a Decision on the recovery of compensation and resettlement support with the recovered amount of 674 million VND. After full recovery, the District Construction Investment and Land Fund Development Project Management Board paid the entire amount mentioned above into the custody account of the District Finance - Planning Department.

Request the return of the budget and sanction violating organizations and individuals

The Inspectorate of Hoa Binh province requested the Management Board of Construction Investment and Land Fund Development of Tan Lac district to recover and pay the amount of more than 278 million VND to the temporary, pending account of the Provincial Inspectorate at the State Treasury of Hoa Binh province.

In addition, the People's Committee of Tan Lac district is requested to direct relevant organizations and individuals to complete the procedures to return the amount of 674 million VND to the state budget.

The Provincial Inspectorate also requested the Chairman of Tan Lac District People's Committee, based on the violations, to strictly handle relevant organizations and individuals according to regulations. At the same time, there are drastic measures to rectify capital construction investment, compensation and resettlement support for projects in the district...

Previously, Lao Dong Newspaper published an article "For more than a decade, people have not dared to settle in the resettlement area" reflecting on the fact that the resettlement area still has many inadequacies that prevent people from daring to settle down.

The project to stabilize residents in natural areas in Loi hamlet, Phu Vinh commune, Tan Lac district, Hoa Binh province was approved by the People's Committee of Hoa Binh province with the task of relocating and arranging accommodation for 45 households. population, total investment is expected to be about 15 billion VND.

The project will be implemented from 2011 to 2020, of which part of the project will be constructed from 2011 to 2013. From May 10, 2013 to June 23, 2019, the project stopped and did not start construction due to not being able to arrange capital.

From June 2019, construction will continue and the project will be completed in December 2020.

By the time of inspection, the project had been completed and handed over for use.

Đặng Tình - Khánh Linh
TIN LIÊN QUAN

154 dự án điện mặt trời được nêu trong kết luận thanh tra

PHẠM ĐÔNG |

Nhiều dự án điện mặt trời do địa phương đề xuất chưa được cập nhật vào kế hoạch là do thuộc danh sách 154 dự án được nêu trong kết luận của Thanh tra Chính phủ.

Kết luận thanh tra Chủ tịch huyện Vĩnh Cửu về tiếp công dân

HÀ ANH CHIẾN |

Đồng Nai - Kết luận thanh tra trách nhiệm Chủ tịch UBND huyện Vĩnh Cửu nêu rõ các thiếu sót về tiếp công dân, xử lý đơn, giải quyết khiếu nại tố cáo…

Thanh tra công tác bổ nhiệm lãnh đạo tại Quảng Bình

LƯƠNG HẠNH |

Thanh tra Bộ Nội vụ tiến hành thanh tra công tác bổ nhiệm công chức giữ chức vụ lãnh đạo giai đoạn từ ngày 1.1.2022 đến ngày 30.6.2024.

Dự báo thời điểm bão Trà Mi đạt cường độ cực đại giật cấp 15

AN AN |

Dự báo bão Trà Mi sẽ đạt cường độ cực đại khoảng cấp 12, giật cấp 15 khi tiến đến vùng biển quần đảo Hoàng Sa trong ngày 26.10.

Giờ thứ 9: Đứa con bất hạnh - Phần 1

Nhóm PV |

Giờ thứ 9 - Bé gái trong câu chuyện ngày hôm nay phải ở với bố dượng của mình sau khi mẹ đẻ ly hôn. Đứa bé sẽ lớn lên như thế nào và có cuộc sống ra sao?

Diễn biến mới vụ hóa đơn nước cao bất thường ở Thái Bình

TRUNG DU |

Thái Bình - Trước hàng loạt hành động khó hiểu từ phía Công ty CP Nước sạch Thái Bình, khách hàng cho biết sẽ tiếp tục kiến nghị đến các cơ quan chức năng.

Phụ huynh cho con đi học trở lại sau khi nhà trường nhận sai

NGUYỄN TRƯỜNG |

Ninh Bình - Sau 2 ngày cho con nghỉ học để làm rõ thông tin nhà trường dùng sữa hết hạn cho học sinh uống, ngày 23.10, các phụ huynh đã cho con đi học trở lại.

Biển Đông vẫn là điểm nóng với các tranh chấp lãnh thổ

Ngọc Vân |

Biển Đông vẫn là điểm nóng với các vấn đề tranh chấp lãnh thổ và khác biệt về yêu sách biển, cùng với tình hình quân sự hoá tại khu vực.

154 dự án điện mặt trời được nêu trong kết luận thanh tra

PHẠM ĐÔNG |

Nhiều dự án điện mặt trời do địa phương đề xuất chưa được cập nhật vào kế hoạch là do thuộc danh sách 154 dự án được nêu trong kết luận của Thanh tra Chính phủ.

Kết luận thanh tra Chủ tịch huyện Vĩnh Cửu về tiếp công dân

HÀ ANH CHIẾN |

Đồng Nai - Kết luận thanh tra trách nhiệm Chủ tịch UBND huyện Vĩnh Cửu nêu rõ các thiếu sót về tiếp công dân, xử lý đơn, giải quyết khiếu nại tố cáo…

Thanh tra công tác bổ nhiệm lãnh đạo tại Quảng Bình

LƯƠNG HẠNH |

Thanh tra Bộ Nội vụ tiến hành thanh tra công tác bổ nhiệm công chức giữ chức vụ lãnh đạo giai đoạn từ ngày 1.1.2022 đến ngày 30.6.2024.