On August 31, information from the Long Thanh Airport Project Management Board said that during the National Day holiday of September 2, at the Long Thanh Airport Project construction site in Binh Son commune, Long Thanh district, Dong Nai province, the construction of packages such as 5.10 passenger terminal, 4.6 runway, 6.12 construction of 2 connecting traffic routes... were still maintained throughout.
According to Vietnam Airports Corporation (ACV), a large construction site has been formed on the project site with the participation of hundreds of construction teams with more than 6,000 personnel and 2,200 construction equipment.
The packages currently being implemented at the construction site have been strictly inspected, controlled, and supervised for acceptance in accordance with the project's technical standards, ensuring the required quality and progress.
The expected progress is to complete the entire construction before December 2025, complete the facade installation before March 2026, in parallel with the completion and installation of test equipment from the beginning of 2026 and strive to complete all items before August 31, 2026.
Mr. Lai Xuan Thanh, Chairman of the Board of Directors of Vietnam Airports Corporation (ACV), said that the Long Thanh airport project phase 1 is expected to be completed and test run before August 31, 2026. By September 2, 2026, Long Thanh airport will welcome its first commercial flight.