Progress of 3 trillion-dollar ring roads to relieve traffic jams in Ho Chi Minh City

MINH QUÂN |

Ho Chi Minh City - Along with Belt 2 and 3 being implemented, Belt 4 is about to be invested in to help reduce traffic congestion in the city and increase regional connectivity for Ho Chi Minh City.

Belt 2

Ring Road 2 of Ho Chi Minh City surrounds the inner city with a total length of 64 km. After 17 years of planning, about 14 km of the route remains unfinished, divided into 4 sections.

Of which, section 3, 2.7km long from Pham Van Dong street to Go Dua intersection, started construction in 2017 with a total capital of more than 2,700 billion VND, invested in the form of BT (build - transfer).

According to the original plan, the above belt section was expected to be completed in 2020. But the project only reached 44% and stopped construction in March 2020 due to land problems and land fund payment to investors.

After 4 years of stagnation, many sections of the Belt 2 construction site (section 3) became cattle grazing areas. Photo: Minh Quan
After 4 years of stagnation, many sections of the Belt 2 construction site (section 3) became cattle grazing areas. Photo: Minh Quan

The project's completion date has been adjusted by the Ho Chi Minh City People's Committee to 2026. Currently, Ho Chi Minh City departments are reviewing to sign contract addendums and land funds to pay investors to restart the project soon.

Section 1 is 3.5km long, from Phu Huu bridge to Vo Nguyen Giap street (formerly Hanoi Highway) with a total capital of about 9,328 billion VND and section 2 from Vo Nguyen Giap street to Pham Van Dong is 2.8km long, total capital of 4,543 billion VND. billion. These two sections are invested with Ho Chi Minh City budget capital, expected to start construction in 2025 and complete in 2027.

Section 4, 5.3km long, connecting National Highway 1 through Nguyen Van Linh street, has an estimated investment cost of about 13,000 billion VND using Ho Chi Minh City budget capital, to be implemented in the period 2024 - 2030.

Belt 3

Belt 3 passes through Ho Chi Minh City, Binh Duong, Dong Nai, Long An, phase one is more than 76km long, has 4 expressway lanes, total investment is nearly 75,400 billion VND. The project is divided into 8 component projects, each locality carries out two projects, including site clearance and construction.

In particular, the Belt 3 project through Ho Chi Minh City is more than 47km long, with a total investment of more than 41,000 billion VND (site clearance cost is nearly 19,000 billion VND).

4 bidding packages starting in June 2023 reached about 17.51%. The remaining 6 bidding packages started earlier this year currently reach about 5.1%.

Belt Construction Site 3 through Thu Duc City (HCMC). Photo: Minh Quan
Belt Construction Site 3 through Thu Duc City (HCMC). Photo: Minh Quan

The lack of sand for foundation is greatly affecting the project progress. The investor is urging the contractor to focus and urgently search for more domestic sand sources and sand sources from Cambodia to bring to the construction site to serve construction in July and August as well as the next stages. according to.

At the same time, the investor is coordinating with the Materials Working Group, the Government's interdisciplinary working group and the localities of Vinh Long, Tien Giang and Ben Tre to speed up the progress of supplying sand for leveling for the Ring Road 3 project. .

The project aims to open to traffic at the end of 2025, and be fully completed and put into operation in 2026.

Belt 4

Belt 4 passes through Ho Chi Minh City, Long An, Binh Duong, Dong Nai and Ba Ria - Vung Tau with a length of nearly 207km, phase one investment with a total capital of more than 127,000 billion VND.

Of which, Belt 4 through Ho Chi Minh City is 17.3km long, from the bridge over the Saigon River (Phu Thuan bridge, Binh Duong) to the bridge over Thay Cai canal (Long An province).

The route is built with 4 expressway lanes (with emergency stopping lanes throughout the route), parallel roads with 2 lanes on both sides. Ho Chi Minh City will clear the site once according to the planning of more than 74m wide.

Alignment of Belt 4 of Ho Chi Minh City. Graphics: Ho Chi Minh City Department of Transport
Alignment of Belt 4 of Ho Chi Minh City. Graphics: Ho Chi Minh City Department of Transport

Total project investment capital is more than 14,000 billion VND under the BOT contract. Of which, Ho Chi Minh City's budget is about 7,251 billion VND, the remaining more than 6,800 billion VND was mobilized by investors.

According to the Ho Chi Minh City Department of Transport, the project has completed a pre-feasibility study report, expected to submit to the authorities for approval of investment policy this year, striving to start construction on April 30, 2025, completed in 2028.

MINH QUÂN
TIN LIÊN QUAN

TPHCM sắp làm 2 dự án gần 27.000 tỉ đồng kết nối Tây Ninh

MINH QUÂN |

Dự án cao tốc TPHCM - Mộc Bài và mở rộng Quốc lộ 22 có tổng vốn gần 27.000 tỉ đồng sắp triển khai giúp tăng kết nối TPHCM và Tây Ninh.

Dự án cải tạo kênh dài nhất TPHCM cần thêm gần 1.600 tỉ đồng

MINH QUÂN |

Dự án cải tạo kênh Tham Lương - Bến Cát - rạch Nước Lên dài nhất TPHCM cần bổ sung gần 1.600 tỉ đồng cho giải phóng mặt bằng, xây thêm cầu, công viên...

TPHCM và 4 tỉnh thống nhất phương án làm Vành đai 4 hơn 100.000 tỉ đồng

MINH QUÂN |

TPHCM - Dự án Vành đai 4 TPHCM dài 207km, đi qua TPHCM và các tỉnh Bình Dương, Đồng Nai, Long An, Bà Rịa - Vũng Tàu, tổng mức đầu tư khoảng 106.000 tỉ đồng. Mỗi địa phương sẽ chủ trì thực hiện đoạn đi qua địa bàn.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

Ngầm tràn ngập sâu, Quảng Bình cảnh báo dân không di chuyển

CÔNG SÁNG |

Do ảnh hưởng bão số 4, từ 7 giờ sáng 20.9, địa bàn tỉnh Quảng Bình vẫn còn nhiều ngầm tràn nước ngập sâu, chảy xiết và chia cắt cục bộ.