700 billion VND road in Son La completes 40% of the roadbed

Trường Sơn |

Son La - The 700 billion VND Yen Chau - Ta Khoa road project has constructed about 40% of the roadbed, contractors organize 2 shifts/day, striving to complete ahead of schedule.

Recorded by Lao Dong Newspaper reporters at the construction site in early September 2026, many excavators, bulldozers, trucks transporting soil and workers were mobilized at locations that already have land.

The items of excavation, foundation embankment, road surface construction, culverts and drainage systems are being implemented simultaneously.

To date, more than 14km of foundation and road surface of the route have been completed. At the locations where the site has been handed over, contractors are focusing manpower and equipment to speed up progress.

Lãnh đạo xã Tạ Khoa nắm tình hình và tiến độ triển khai Dự án đường tỉnh 120C đoạn qua địa phận bản Suối Nhạn. Ảnh: Hoàng Sây chụp ngày 11.9.2026
Construction unit leveling the base of provincial road 120C section passing through Suoi Nhan village, Ta Khoa commune. Photo: Hoang Say taken on September 11, 2026

In Ta Khoa commune, more than 8km of foundation and road surface have been constructed. Many items such as culverts, drainage ditches and foundation treatment are also being implemented.

Meanwhile, in Yen Chau commune, more than 6km of road surface has been completed. The entire site of the route passing through the commune has been cleared, creating conditions for contractors to focus on construction.

The Km0 - Km16+200 section through Yen Chau commune has a total investment of more than 312 billion VND. The starting point of the project connects to Chu Van An road, sub-area 3/2, the ending point is in Pa Sang area, Doan Ket village.

Contractors maintain construction in 2 shifts/day, proactively arrange manpower and equipment in accordance with the site handover schedule.

Mr. Nguyen Tien Duc - Director of Tien Anh Construction and Trading Co., Ltd. - said: "Where the site is handed over, we organize construction there, currently the roadbed has been constructed 40% of the entire route.

Vị trí thi công mặt đường và ta luy dương Dự án đường tỉnh 120C thuộc địa phận bản Suối Nhạn, xã Tạ Khoa, tỉnh Sơn La. Ảnh: Hoàng Sây chụp ngày 11.9.2026
Construction location of the road surface and positive slope of Provincial Road 120C Project in Suoi Nhan village, Ta Khoa commune, Son La province. Photo: Hoang Say taken on September 11, 2026

In parallel with construction, site clearance work in Ta Khoa commune continues to be implemented. In June 2026, the locality paid more than 17.4 billion VND to 49 organizations, households, and individuals affected by the project.

For the remaining areas, functional agencies continue to complete dossiers and implement compensation, support, and resettlement steps.

In mid-August 2026, the Bac Yen Construction Investment Project Management Board in coordination with the Ta Khoa Commune People's Committee publicly announced the draft plan for compensation, support, and resettlement for the 3rd time in Ta Do village.

According to the plan, there are 41 affected cases, with more than 82,900m2 of land expected to be recovered. Compensation and support costs are more than 12.5 billion VND.

Lấy ý kiến, niêm yết công khai dự thảo phương án bồi thường, hỗ trợ, tái định cư dự án Đường tỉnh 120C tại bản Tà Đò, xã Tạ Khoa. Ảnh: Hoàng Sây chụp ngày 11.8.2026
Ta Khoa commune collects opinions and publicly lists the draft plan for compensation, support, and resettlement for the provincial road 120C project in Ta Do village, Ta Khoa commune. Photo: Hoang Say taken on August 11, 2026

Mr. Dinh Van Khanh - Secretary of the Party Cell, Head of Ta Do village - shared that information related to land, assets and compensation plans is made public for people to follow, exchange and propose.

Mr. Nguyen Dang Thuc - Vice Chairman of Ta Khoa Commune People's Committee - informed that the locality regularly inspects the site, coordinates with the investor and contractor to handle arising problems, ensure progress, quality and safety of the project.

Currently, contractors continue to complete the ground, taking advantage of construction at locations that meet the conditions. The acceleration of items is expected to help the Yen Chau - Ta Khoa provincial road project be completed ahead of schedule in 2028.

The Yen Chau - Ta Khoa provincial road 120C project started construction in June 2025, has a length of 34.3km, a total investment of 700 billion VND, and is expected to be completed in 2028.

In which, the section from Km0 to Km16+200 (equivalent to 16.2km) is invested by Yen Chau Commune People's Committee, with a total investment of 319.7 billion VND.

The section from Km16+200 to Km34+200 (equivalent to 18.1km) is invested by Ta Khoa Commune People's Committee, with a total investment of more than 376 billion VND.

The project is expected to strengthen regional traffic connections and contribute to reducing dependence on National Highway 37.

Trường Sơn
RELATED NEWS

Changing the road ban time on National Highway 6 in Son La to handle landslides

|

Son La - From September 12, functional forces changed the time frame for temporarily prohibiting vehicles from passing Moc Chau Pass to serve the handling of landslide-prone points.

Nearly 100 households in Son La are waiting anxiously for clean water

|

Son La - Nearly 100 households in group 1, Chieng Coi ward have not had clean water for many years, having to use source water, rainwater and irrigation dam water.

Fragrant winter melon enters the season, Son La farmers are busy harvesting

|

Son La - Green squash with fragrant yellow flesh in the highlands is entering the peak season, farmers are busy harvesting and selling to traders, bringing stable income.

Live Vietnam women's team vs Thailand at ASIAD 20

|

Live broadcast of Vietnam women's team vs Thailand at ASIAD 20 taking place at 5:30 PM today (September 21).

New Secretary of Quang Tri Provincial Party Committee proposes not to organize a congratulatory delegation

|

Quang Tri - Provincial Party Secretary Vuong Quoc Tuan requested agencies and units not to organize delegations to visit and present flowers to congratulate on the occasion of receiving new assignments.

Russia attacks Ukrainian strategic port in Black Sea, hitting military cargo ship

|

The Russian Ministry of Defense said that Russian forces attacked logistics centers, warehouses and Ukrainian seaports, hitting cargo ships to the port of Odessa.

Proposal to transfer EVN to the Ministry of Industry and Trade: The Ministry needs to give a convincing reason

|

According to experts, the Ministry of Industry and Trade needs to provide specific and convincing explanations about the objectives, operating mechanisms, and effectiveness of the plan to transfer EVN to the Ministry.

Changing the road ban time on National Highway 6 in Son La to handle landslides

Trường Sơn |

Son La - From September 12, functional forces changed the time frame for temporarily prohibiting vehicles from passing Moc Chau Pass to serve the handling of landslide-prone points.

Nearly 100 households in Son La are waiting anxiously for clean water

Trường Sơn |

Son La - Nearly 100 households in group 1, Chieng Coi ward have not had clean water for many years, having to use source water, rainwater and irrigation dam water.

Fragrant winter melon enters the season, Son La farmers are busy harvesting

Trường Sơn |

Son La - Green squash with fragrant yellow flesh in the highlands is entering the peak season, farmers are busy harvesting and selling to traders, bringing stable income.