At the meeting, the district heard the results of the results and progress of the implementation of the investment project to build the road connecting Nguyen Luong Bang Street with Tran Nhan Tong Street; Investment project on construction of Ring Road 2, the section of Tan Vu - Hung Dao - Bui Vien street through Dong Hoa ward.
Regarding the road project connecting Nguyen Luong Bang Street with Tran Nhan Tong Street, by the end of 2024, 2 contractors have implemented more than 40% of the construction volume. Currently, there are 13 households with recovery land that has not received compensation and support for site clearance, 8 households have received money but have not dismantled works and handed over the ground.
Regarding the investment project to build Ring Road 2, the section of Tan Vu - Hung Dao - Bui Vien Street, out of 271 households with agricultural land subject to the project recovery, 201 cases have received money and discussion Delivery of premises. The biggest problem of the project so far is the site clearance work with cases related to tombs and residential land.
At the conference, Vice Chairman of Kien An District People's Committee Pham Van Dien noted that related wards continue to propagate and mobilize democratic households to actively hand over the ground to implement the project; review and resolve citizens' recommendations. The coordinating authorities focus on accelerating the progress of the tasks and tasks related to site clearance. In particular, fully apply the current policy framework in compensation for site clearance, ensuring citizens' interests. If the citizen still deliberately fails to comply, the authorities shall coercive in accordance with the law, ensuring the project progress.