Land clearance problems, National Highway 32C Upgrade Project has been under construction for 13 years and has not been completed

Bảo Nguyên - Văn Đức |

Lao Cai - The National Highway 32C upgrade project started in 2012 but has not yet completed site clearance.

The project to upgrade National Highway 32C, Hien Luong section - Yen Bai city, invested by the Department of Transport of Yen Bai province (old) with a total cost of over 500 billion VND.

Phase 1 started construction in 2012, the section from Km79 - Km87; Phase 2 started construction in 2021, the section from Km87+150 - Km96+500, passing through Au Lau ward (Lao Cai province).

On September 16, Lao Dong noted that the National Highway 32C Upgrade Project is still under construction, and site clearance is still slow.

Some sections are being paved, many locations have to stop due to problems with houses. Along the route, many machines and materials are gathered waiting for construction. In particular, there are construction sections that are unfinished after many years, overgrown with grass.

Du an nang cap Quoc lo 32, doan Km79 – Km96+500 thi cong do dang do vuong mat bang. Anh: Van Duc
The National Highway 32C upgrade project, section Km79 - Km96+500, is under construction due to land clearance problems. Photo: Van Duc

Mr. Duong Duc Vien ( Au Lau ward) said that this road has been under construction for nearly 13 years but is still unfinished. The contractor has paved some places with asphalt, some places are still laden with grass, many houses still live in the middle of the road, so people are wondering when the project will be completed.

According to Mr. Vien, the people who previously obstructed the construction were due to not accepting the compensation plan as well as the desire to soon have a resettlement area for relocation.

Mr. Nong Van Hien - Deputy Head of the Lao Cai Province No. 1 Investment and Construction Project Management Board - said: From July 1, 2025, the two-level local government will come into operation, the merger of agencies related to site clearance along with changes in instructions and policies has caused this work to be interrupted, not meeting progress requirements.

Currently, the project still has 1.2 km of land to implement construction, with a total of 53 households still stuck; the sections of the route are handed over on a small scale, not continuously, causing difficulties for construction and affecting the overall progress of the project.

May moc duoc tap trung tren cong truong de san sang thi cong nhung doan co mat bang. Anh: Van Duc
Machinery is concentrated at the construction site to be ready to construct sections with land. Photo: Van Duc

"The project has been extended by the Ministry of Transport (now the Ministry of Construction) until the end of 2025. However, the remaining workload is very large, if the site clearance is not completed by the end of September, the risk of not being able to complete the project in 2025 is very high", informed the Deputy Head of the Lao Cai Province No. 1 Investment and Construction Project Management Board.

Regarding the National Highway 32C Upgrade Project, Permanent Vice Chairman of Lao Cai Provincial People's Committee Nguyen The Phuoc requested the No. 1 Construction Investment Project Management Board to coordinate with Au Lau Ward People's Committee and relevant departments and branches to focus on removing obstacles to site clearance.

In particular, it is necessary to promptly develop a compensation plan, publicize the resettlement plan and arrange accommodation for affected households, creating conditions for smooth construction, ensuring the goal of completing the entire project before December 31, 2025.

Bảo Nguyên - Văn Đức
RELATED NEWS

Russia approves Europe's longest high-speed railway project

|

Russia has just approved a 4,500km long high-speed railway super project, the largest in Europe, with domestic trains reaching speeds of 400 km/h.

Assigning responsibility to livestream entities

|

The draft Law on E-commerce stipulates the responsibility of entities operating livestream and affiliate marketing.

Liverpool beat Atletico Madrid thanks to an extra-minute goal

|

In the early morning of September 18 (Vietnam time), Liverpool won a dramatic victory with a score of 3-2 against Atletico Madrid in the Champions League.

Boarding doctor tuition fees in 2025 for schools are over VND932 million/year

|

Tuition fees for inpatient programs vary widely between schools. Many qualified candidates still carefully consider the cost in some places of nearly 1 billion VND/year.

Information from inpatient and semi-resident nursing homes and elderly care centers

|

In the busy modern life, with a busy work schedule, the demand for nursing care services for the elderly is increasing.

Prime Minister requests to handle the plan to exploit 2 large airports after Lao Dong Newspaper's reflection

|

After the article of Lao Dong Newspaper, the Prime Minister requested an inspection and handling of the plan to exploit Long Thanh and Tan Son Nhat airports.

Cuộc sống người dân đảo lộn vì cải tạo Quốc lộ 32C dang dở

Đinh Đại |

Yên Bái - Hơn 1 năm qua, cuộc sống của người dân thôn Phúc Thịnh, xã Giới Phiên, thành phố Yên Bái bị đảo lộn do việc cải tạo tuyến đường Quốc lộ 32C chậm trễ, dù đoạn chạy qua chỉ còn 100m cuối.

Yên Bái: 2 dự án bị theo dõi đặc biệt vẫn vỡ kế hoạch về đích

Văn Đức |

Dự án nâng cấp QL32C đoạn Hiền Lương - TP Yên Bái (Km79 - Km96+500) và dự án đầu tư xây dựng nâng cấp QL37 đoạn Km280 - Km340 đoạn qua địa phận tỉnh Yên Bái đã bị “vỡ” kế hoạch về đích dù Bộ Giao thông Vận tải đã cho vào diện theo dõi đặc biệt đối với các công trình phải hoàn thành trong năm 2022.

Dự án ở Yên Bái 10 năm chưa xong đền bù giải phóng mặt bằng

Văn Đức |

Dự án nâng cấp tuyến Quốc lộ 32C Hiền Lương - TP Yên Bái, khởi công từ năm 2012, nhưng đến nay vẫn chưa hoàn thành do vướng mắc giải phóng mặt bằng.