Building embankment to prevent landslides on 500kV power pole foundation, circuit 3

TRẦN TUẤN |

Ha Tinh - Currently, at some locations of 500kV circuit 3 power poles in Ha Tinh, workers are building embankments around the pole foundations to prevent landslides.

On December 2, according to a reporter from Lao Dong Newspaper, at power pole No. 174 of the 500kV line circuit 3 in Cam My commune (Cam Xuyen district, Ha Tinh province), a group of nearly 10 workers from the North Central Power Construction Company (a subcontractor of Song Da Construction and Service Joint Stock Company) were constructing a stone embankment around the foundation area of ​​this power pole.

Mr. Nguyen Xuan That - the investor's supervisor present at the construction site - said that the construction of the reinforced stone embankment around the column foundation has been carried out since the column was erected until now.

According to Mr. That, the stone embankment work at column 174 is expected to be completed in a few days. After that, the area around the construction site will be cleaned up and restored.

Viec xay ke nham bao ve mong cot dien han che sat lo quanh mong. Anh: Tran Tuan.
The embankment construction aims to protect the foundation of the electric poles and limit landslides around the foundation. Photo: Tran Tuan

However, the restoration will take a long time because it is necessary to agree on a plan with the forest owner (acacia plantation) before it can be implemented.

According to Mr. That, at column 175, the embankment around the column foundation has been completed. At the next column 176, a group of about a dozen workers are also constructing a stone embankment around the column foundation.

Mr. Mai Vu Tran Quang - technical officer of Song Da Construction and Service Joint Stock Company - said that the construction of embankment around the foundation of 500kV power pole circuit 3 is to carry out the design item with the purpose of ensuring the stability of the pole foundation, limiting landslides affecting the pole foundation.

Cong nhan dang xay ke. Anh: Tran Tuan.
Workers are building a dike. Photo: Tran Tuan.

According to Mr. Quang, the construction of this embankment was supposed to be completed in November 2024, but due to the heavy rain, it was delayed and is expected to be completed by the end of this week.

Regarding the landslide and the erosion of a part of the soil previously used to dig the column foundation, Mr. Quang informed that the construction unit had transported and filled the area around the column foundation to balance it. In addition, some remaining soil locations will be covered with a layer of roof surface to limit landslides.

Sat lo, dat tren khu vuc cot dien troi xuong rung trong keo cua nguoi dan. Anh: Tran Tuan.
Landslide in the area where an electric pole fell into a local acacia forest. Photo: Tran Tuan

Mr. Quang added that regarding the restoration, the forest owner will have to agree on a plan, possibly compensating the forest owner for the trees affected by the construction of the electric pole, or replanting the affected or damaged part of the forest if requested by the forest owner.

Bun dat tu tren mong cot dien troi xuong theo suon doi. Anh: Tran Tuan.
Mud from the electric pole's foundation flows down the hillside. Photo: Tran Tuan
Duong vao vi tri cot dien so 174 va 175 thuoc duong day 500kV mach 3 lay loi do xe tai cho vat lieu len cong truong de thi cong ke mong cot. Anh: Tran Tuan.
The road to the location of electric poles 174 and 175 of the 500kV line 3 is muddy due to trucks carrying materials to the construction site to construct the pole foundation. Photo: Tran Tuan

Mr. Bui Xuan Thai - Deputy Head of Technical Department, Central Power Project Management Board - said that the construction of stone embankments around the foundation of the 500kV power pole circuit 3 is to limit landslides and rock slides, and will then be restored according to the Government's direction.

According to Mr. Thai, the construction of the foundation embankment and restoration work is scheduled to be completed in December 2024.

TRẦN TUẤN
TIN LIÊN QUAN

500kV line circuit 3 and the miracle of speed, economy and efficiency

|

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Korean fireworks stir up the Han River night with Dragon dance and G-Dragon rap music

|

Da Nang - Inspired by the symbol of Dragon and modern Da Nang, the Korean fireworks team told the story through light, imbued with cinematic style called "Dragon Dance".

2-level government model in Ho Chi Minh City after 2 weeks of testing

|

HCMC - The 2-level government model has given positive signals after 2 weeks of testing in new wards in HCMC, officials are ready to serve people from July 1.

Hour 9: Unexpected meeting - Part 2

|

Hour 9 No. 160 - The wife waited for her husband to go missing for 10 years before getting remarried. Suddenly, her ex-husband returned. What direction will her family's life turn after this incident?

Ho Chi Minh City launches new city after merging Binh Duong and Ba Ria - Vung Tau on the morning of June 30

|

HCMC - The ceremony to announce the establishment of the new HCMC after the merger of Binh Duong and Ba Ria - Vung Tau will take place at 8:00 a.m. on June 30 at the Ho Chi Minh City Police Academy.

Hue tightens protection of national treasures after the incident of the throne being violated

|

HUE - After the Nguyen Dynasty throne was attacked, Hue City has increased many measures to protect national treasures currently kept in the area.

500kV line circuit 3 and the miracle of speed, economy and efficiency

Cường Ngô |

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Đường dây 500kV mạch 3 có bị ảnh hưởng bởi bão số 3?

Anh Tuấn |

Theo EVNNPT, đường dây 500kV mạch 3 từ Quảng Trạch (Quảng Bình) đến Phố Nối (Hưng Yên) không bị ảnh hưởng, hư hỏng bởi bão số 3.

66 tập thể và cá nhân xây dựng đường dây 500kV mạch 3 được nhận Bằng khen

Hà Anh |

Ngày 29.8, dự án đường dây 500kV mạch 3 chính thức khánh thành. Dự án có ý nghĩa đặc biệt quan trọng bảo đảm an ninh năng lượng quốc gia.