Building embankment to prevent landslides on 500kV power pole foundation, circuit 3

TRẦN TUẤN |

Ha Tinh - Currently, at some locations of 500kV circuit 3 power poles in Ha Tinh, workers are building embankments around the pole foundations to prevent landslides.

On December 2, according to a reporter from Lao Dong Newspaper, at power pole No. 174 of the 500kV line circuit 3 in Cam My commune (Cam Xuyen district, Ha Tinh province), a group of nearly 10 workers from the North Central Power Construction Company (a subcontractor of Song Da Construction and Service Joint Stock Company) were constructing a stone embankment around the foundation area of ​​this power pole.

Mr. Nguyen Xuan That - the investor's supervisor present at the construction site - said that the construction of the reinforced stone embankment around the column foundation has been carried out since the column was erected until now.

According to Mr. That, the stone embankment work at column 174 is expected to be completed in a few days. After that, the area around the construction site will be cleaned up and restored.

Viec xay ke nham bao ve mong cot dien han che sat lo quanh mong. Anh: Tran Tuan.
The embankment construction aims to protect the foundation of the electric poles and limit landslides around the foundation. Photo: Tran Tuan

However, the restoration will take a long time because it is necessary to agree on a plan with the forest owner (acacia plantation) before it can be implemented.

According to Mr. That, at column 175, the embankment around the column foundation has been completed. At the next column 176, a group of about a dozen workers are also constructing a stone embankment around the column foundation.

Mr. Mai Vu Tran Quang - technical officer of Song Da Construction and Service Joint Stock Company - said that the construction of embankment around the foundation of 500kV power pole circuit 3 is to carry out the design item with the purpose of ensuring the stability of the pole foundation, limiting landslides affecting the pole foundation.

Cong nhan dang xay ke. Anh: Tran Tuan.
Workers are building a dike. Photo: Tran Tuan.

According to Mr. Quang, the construction of this embankment was supposed to be completed in November 2024, but due to the heavy rain, it was delayed and is expected to be completed by the end of this week.

Regarding the landslide and the erosion of a part of the soil previously used to dig the column foundation, Mr. Quang informed that the construction unit had transported and filled the area around the column foundation to balance it. In addition, some remaining soil locations will be covered with a layer of roof surface to limit landslides.

Sat lo, dat tren khu vuc cot dien troi xuong rung trong keo cua nguoi dan. Anh: Tran Tuan.
Landslide in the area where an electric pole fell into a local acacia forest. Photo: Tran Tuan

Mr. Quang added that regarding the restoration, the forest owner will have to agree on a plan, possibly compensating the forest owner for the trees affected by the construction of the electric pole, or replanting the affected or damaged part of the forest if requested by the forest owner.

Bun dat tu tren mong cot dien troi xuong theo suon doi. Anh: Tran Tuan.
Mud from the electric pole's foundation flows down the hillside. Photo: Tran Tuan
Duong vao vi tri cot dien so 174 va 175 thuoc duong day 500kV mach 3 lay loi do xe tai cho vat lieu len cong truong de thi cong ke mong cot. Anh: Tran Tuan.
The road to the location of electric poles 174 and 175 of the 500kV line 3 is muddy due to trucks carrying materials to the construction site to construct the pole foundation. Photo: Tran Tuan

Mr. Bui Xuan Thai - Deputy Head of Technical Department, Central Power Project Management Board - said that the construction of stone embankments around the foundation of the 500kV power pole circuit 3 is to limit landslides and rock slides, and will then be restored according to the Government's direction.

According to Mr. Thai, the construction of the foundation embankment and restoration work is scheduled to be completed in December 2024.

TRẦN TUẤN
RELATED NEWS

500kV line circuit 3 and the miracle of speed, economy and efficiency

|

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Live football U23 Vietnam vs U23 UAE in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Vietnam and U23 UAE in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 16).

Prosecuting the accident on the highway that killed 4 people in Thanh Hoa

|

Thanh Hoa - The Police Agency has initiated a criminal case related to a particularly serious traffic accident on the highway that killed 4 people.

Live football U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship

|

Live football match between U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship at 6:30 PM tonight (January 16).

Ms. Lam Thi Phuong Thanh is introduced to run for National Assembly Deputy of the 16th term

|

Voters at the Ministry of Culture, Sports and Tourism voted to agree to introduce Ms. Lam Thi Phuong Thanh, Standing Deputy Minister, to run for National Assembly Deputy of the 16th term.

Thu Thiem - Long Thanh railway line 42km long connects Long Thanh airport

|

Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.

More provinces and cities announce the 3rd exam subject for 10th grade in 2026

|

Up to now, many provinces and cities have announced the 3rd exam subject in the 10th grade entrance exam for the 2026 - 2027 school year.

After Metro Line 2, Ho Chi Minh City is about to start construction of 5 more metro lines in 2026

|

Ho Chi Minh City - After starting Metro Line 2 (Ben Thanh - Tham Luong), Ho Chi Minh City plans to start construction of 5 more metro lines in 2026, completed in 2030.

500kV line circuit 3 and the miracle of speed, economy and efficiency

Cường Ngô |

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Đường dây 500kV mạch 3 có bị ảnh hưởng bởi bão số 3?

Anh Tuấn |

Theo EVNNPT, đường dây 500kV mạch 3 từ Quảng Trạch (Quảng Bình) đến Phố Nối (Hưng Yên) không bị ảnh hưởng, hư hỏng bởi bão số 3.

66 tập thể và cá nhân xây dựng đường dây 500kV mạch 3 được nhận Bằng khen

Hà Anh |

Ngày 29.8, dự án đường dây 500kV mạch 3 chính thức khánh thành. Dự án có ý nghĩa đặc biệt quan trọng bảo đảm an ninh năng lượng quốc gia.