Building embankment to prevent landslides on 500kV power pole foundation, circuit 3

TRẦN TUẤN |

Ha Tinh - Currently, at some locations of 500kV circuit 3 power poles in Ha Tinh, workers are building embankments around the pole foundations to prevent landslides.

On December 2, according to a reporter from Lao Dong Newspaper, at power pole No. 174 of the 500kV line circuit 3 in Cam My commune (Cam Xuyen district, Ha Tinh province), a group of nearly 10 workers from the North Central Power Construction Company (a subcontractor of Song Da Construction and Service Joint Stock Company) were constructing a stone embankment around the foundation area of ​​this power pole.

Mr. Nguyen Xuan That - the investor's supervisor present at the construction site - said that the construction of the reinforced stone embankment around the column foundation has been carried out since the column was erected until now.

According to Mr. That, the stone embankment work at column 174 is expected to be completed in a few days. After that, the area around the construction site will be cleaned up and restored.

Viec xay ke nham bao ve mong cot dien han che sat lo quanh mong. Anh: Tran Tuan.
The embankment construction aims to protect the foundation of the electric poles and limit landslides around the foundation. Photo: Tran Tuan

However, the restoration will take a long time because it is necessary to agree on a plan with the forest owner (acacia plantation) before it can be implemented.

According to Mr. That, at column 175, the embankment around the column foundation has been completed. At the next column 176, a group of about a dozen workers are also constructing a stone embankment around the column foundation.

Mr. Mai Vu Tran Quang - technical officer of Song Da Construction and Service Joint Stock Company - said that the construction of embankment around the foundation of 500kV power pole circuit 3 is to carry out the design item with the purpose of ensuring the stability of the pole foundation, limiting landslides affecting the pole foundation.

Cong nhan dang xay ke. Anh: Tran Tuan.
Workers are building a dike. Photo: Tran Tuan.

According to Mr. Quang, the construction of this embankment was supposed to be completed in November 2024, but due to the heavy rain, it was delayed and is expected to be completed by the end of this week.

Regarding the landslide and the erosion of a part of the soil previously used to dig the column foundation, Mr. Quang informed that the construction unit had transported and filled the area around the column foundation to balance it. In addition, some remaining soil locations will be covered with a layer of roof surface to limit landslides.

Sat lo, dat tren khu vuc cot dien troi xuong rung trong keo cua nguoi dan. Anh: Tran Tuan.
Landslide in the area where an electric pole fell into a local acacia forest. Photo: Tran Tuan

Mr. Quang added that regarding the restoration, the forest owner will have to agree on a plan, possibly compensating the forest owner for the trees affected by the construction of the electric pole, or replanting the affected or damaged part of the forest if requested by the forest owner.

Bun dat tu tren mong cot dien troi xuong theo suon doi. Anh: Tran Tuan.
Mud from the electric pole's foundation flows down the hillside. Photo: Tran Tuan
Duong vao vi tri cot dien so 174 va 175 thuoc duong day 500kV mach 3 lay loi do xe tai cho vat lieu len cong truong de thi cong ke mong cot. Anh: Tran Tuan.
The road to the location of electric poles 174 and 175 of the 500kV line 3 is muddy due to trucks carrying materials to the construction site to construct the pole foundation. Photo: Tran Tuan

Mr. Bui Xuan Thai - Deputy Head of Technical Department, Central Power Project Management Board - said that the construction of stone embankments around the foundation of the 500kV power pole circuit 3 is to limit landslides and rock slides, and will then be restored according to the Government's direction.

According to Mr. Thai, the construction of the foundation embankment and restoration work is scheduled to be completed in December 2024.

TRẦN TUẤN
RELATED NEWS

500kV line circuit 3 and the miracle of speed, economy and efficiency

|

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

dong, people count down to welcome the moment Notre Dame Cathedral lights up

|

HCMC - From the afternoon, the center of HCMC was packed with people and tourists counting down, welcoming the moment Notre Dame Cathedral lit up, bringing a warm and bustling Christmas atmosphere.

Him Lam, Vinaconex are on the list of inspectors in 2026

|

Some investors and projects are included in the 2026 inspection plan of the Government Inspectorate.

Hanoi reclaims land, clears land to build Tran Hung Dao bridge

|

Hanoi - It is expected that there will be about 640 households subject to land acquisition and site clearance to build Tran Hung Dao bridge, with a total capital of VND 16,226 billion.

The Central Executive Committee of the Vietnam Young Physicians Association, course V, has 89 members

|

Ms. Bui Thi Minh Hoai - Politburo member, Secretary of the Party Central Committee, Chairwoman of the Central Committee of the Vietnam Fatherland Front attended the 5th National Congress of the Vietnam Young Physicians Association, term 2025 - 2030.

Ending the 886 billion VND flood control project after 16 years of unfinished

|

Ha Tinh - The Provincial People's Committee has just decided to terminate the project of the canal system for water separation, flood division, and flood prevention for communes in the south of Ky Anh after 16 years of unfinished work.

Securities waiting for cash flow's spread signal

|

The stock market returns to check the psychological resistance zone of 1,700 points according to the scenario of cash flow circulation between industry groups.

Appointment of Chairman of the Executive Agency of the International Financial Center in Ho Chi Minh City, Da Nang

|

The People's Committees of Ho Chi Minh City and Da Nang have announced decisions on the transfer and appointment of leaders of the management agencies of the International Financial Centers in the two cities.

500kV line circuit 3 and the miracle of speed, economy and efficiency

Cường Ngô |

In the article "Fighting waste", General Secretary and President To Lam emphasized the need to summarize and replicate the experience of implementing the 500kV line 3 project for key and important national public investment projects and works.

Đường dây 500kV mạch 3 có bị ảnh hưởng bởi bão số 3?

Anh Tuấn |

Theo EVNNPT, đường dây 500kV mạch 3 từ Quảng Trạch (Quảng Bình) đến Phố Nối (Hưng Yên) không bị ảnh hưởng, hư hỏng bởi bão số 3.

66 tập thể và cá nhân xây dựng đường dây 500kV mạch 3 được nhận Bằng khen

Hà Anh |

Ngày 29.8, dự án đường dây 500kV mạch 3 chính thức khánh thành. Dự án có ý nghĩa đặc biệt quan trọng bảo đảm an ninh năng lượng quốc gia.