Dialogue with the people, Tu Minh ward promotes the progress of Cam Doai resettlement project

Mai Hương |

Hai Phong - Tu Minh Ward dialogues and removes obstacles in compensation for site clearance for the Cam Doai commune resettlement area project, striving to pay before May 30, 2026.

On May 6, Tu Minh Ward People's Committee (Hai Phong City) organized a dialogue with households whose land was recovered to propagate and answer questions about compensation, support, and resettlement to serve the site clearance (GPMB) of the project to build technical infrastructure for the resettlement area and residential point of Cam Doai commune (phase 1).

According to the report of the Economic, Infrastructure and Urban Department, the project was approved by Cam Giang District People's Committee in Decision No. 4672/QD-UBND dated December 31, 2024, with a recovered area of 1.44 ha, involving 20 households and individuals.

To date, 6 households have received money and handed over the land; 10 households subject to coercive inventory have not received money; some cases still have problems with mechanisms and policies. The Land Clearance Council has publicly posted plans, received and explained people's opinions according to regulations.

Người dân nêu ý kiến về diện tích bồi thường, chính sách hỗ trợ tại buổi đối thoại. Ảnh: Nguyên Thương
People express opinions on compensation area and support policies at the dialogue. Photo: Nguyen Thuong

At the dialogue, households proposed to review the compensation area; consider supporting bidding ponds and agricultural land; clarify the compensation unit price and support policies for arising population; and at the same time request to provide legal information and grounds for project implementation.

Some opinions also proposed ensuring production conditions, supporting stable living conditions and guiding payment for crops and flowers. Representatives of the Economic, Infrastructure and Urban Department explained and clarified the contents according to the provisions of law; and at the same time received and summarized the opinions to report to competent authorities for consideration.

Mr. Le Van Trung - Deputy Secretary of the Party Committee, Chairman of the Ward People's Committee - emphasized that the compensation and support plan is built on the basis of current regulations, ensuring publicity, transparency and the legitimate rights of the people.

Regarding specific recommendations, the Ward People's Committee will continue to review and respond in writing according to regulations. At the same time, it is requested that households urgently complete population declarations as a basis for supporting life stabilization, coordinate to receive money and hand over land.

In the coming time, Tu Minh ward will continue to promote propaganda and mobilization, striving to complete the approval and payment of compensation and support plans before May 30, 2026; cases of non-compliance will be handled according to the provisions of law.

Mai Hương
RELATED NEWS

Converting resettlement housing to social housing, it is necessary to ensure harmonious interests

|

Hanoi is allowed to flexibly switch between types of housing according to the revised Capital Law, opening up directions to handle thousands of vacant resettlement apartments.

Accelerate resettlement areas to serve Gia Binh airport project

|

Bac Ninh - Provincial People's Committee requests to accelerate the progress of resettlement areas serving the Gia Binh airport project.

Ninh Binh invests 70 billion VND to build resettlement area to serve high-speed railway

|

Ninh Binh is building a resettlement area in Trung Son ward with a total investment of 70 billion VND to serve site clearance for the North-South high-speed railway project.

Live football Nam Dinh vs Selangor in the Southeast Asian semi-finals

|

Live match between Nam Dinh club and Selangor in the semi-finals of the Southeast Asian Club Championship 2025-2026, taking place at 8:00 PM tonight (May 6).

Health insurance drug list will be updated soon, and many cancer treatment drugs will be added

|

The list of drugs paid for by the Health Insurance Fund (HI) is expected to add 84 new drugs. In which, 30 cancer treatment drugs are added.

Despite the ban, openly trading and using e-cigarettes

|

Despite penalty regulations, e-cigarettes are still secretly traded online, publicly used in many places, with increasingly sophisticated methods.

Chuong Duong bridge is overloaded for many days, Long Bien bridge accelerates to complete repairs

|

Hanoi - Chuong Duong bridge is congested for a long time due to increased traffic pressure, Long Bien bridge is being quickly repaired to soon reduce the load on the area.

Converting resettlement housing to social housing, it is necessary to ensure harmonious interests

Như Hạ - Phúc Lộc |

Hanoi is allowed to flexibly switch between types of housing according to the revised Capital Law, opening up directions to handle thousands of vacant resettlement apartments.

Accelerate resettlement areas to serve Gia Binh airport project

Vân Trường |

Bac Ninh - Provincial People's Committee requests to accelerate the progress of resettlement areas serving the Gia Binh airport project.

Ninh Binh invests 70 billion VND to build resettlement area to serve high-speed railway

Hà Vi |

Ninh Binh is building a resettlement area in Trung Son ward with a total investment of 70 billion VND to serve site clearance for the North-South high-speed railway project.