Duy Tuấn |

Lam Dong - The technical infrastructure project for the social housing area in Tien Loi commune (old) is still unfinished due to many problems in site clearance and land price determination.

On October 15, Lam Dong Provincial Inspectorate announced the public conclusion of the thematic inspection for the Social Housing Infrastructure Project in Tien Loi Commune, Phan Thiet City (before the arrangement).

This is one of 10 projects and works with difficulties, problems, delays, long-term backlogs, low efficiency, and risk of causing loss and waste that Lam Dong Provincial Inspectorate announced inspection decisions in early August.

Phia truoc cong vao du an ha tang ky thuat khu nha o xa hoi tai xa Tien Loi. Anh: Duy Tuan
In front of the entrance to the technical infrastructure project of the social housing area in Tien Loi commune. Photo: Duy Tuan

From August 5 to August 29, the Inspection Team conducted an inspection at the Binh Thuan Province Civil and Industrial Construction Investment Project Management Board, now the No. 2 Construction Investment Project Management Board, under the Lam Dong Provincial People's Committee.

The Social Housing Technical Infrastructure Project in Tien Loi Commune, Phan Thiet City, now in Tuyen Quang Commune, has a total investment of more than 51 billion VND.

The project has an area of about 4.5 hectares and is an urgent project, belonging to Group B project, implemented from 2016 - 2020 and extended to 2021 - 2025.

The goal is to create a clean land fund and build technical infrastructure for social housing. However, by the end of 2023, the project was forced to temporarily suspend construction due to prolonged problems in compensation and site clearance.

Tru so Thanh tra tinh Lam Dong - co so tai phuong Phan Thiet. Anh: Duy Tuan
Lam Dong Provincial Inspectorate Headquarters - facility in Phan Thiet Ward. Photo: Duy Tuan

According to the inspection conclusion, at the time of inspection, the project did not have a specific land price to calculate compensation and support. The on-site resettlement plan has not been approved; the land location of the project has not been included in the province's annual land price list. This leads to insufficient legal basis to complete compensation, support and site clearance.

Lam Dong Provincial Inspectorate also pointed out the responsibilities of many relevant agencies and units. For example, the Department of Agriculture and Environment is slow to guide the determination of specific land prices to carry out compensation, support and resettlement for projects.

Ben trong du an ha tang ky thuat khu nha o xa hoi tai xa Tien Loi. Anh: Duy Tuan
Inside the technical infrastructure project of the social housing area in Tien Loi commune. Photo: Duy Tuan

In addition, the Provincial Land Fund Development Center, Phan Thiet City People's Committee (before the arrangement), Tien Loi Commune People's Committee (before the merger) and the Compensation, Support and Resettlement Council also have related responsibilities.

These agencies are slow in guiding, determining land prices, developing resettlement plans and resolving people's complaints.

From the above shortcomings, the project has been stalled, causing waste of budget capital and affecting social security.

The Inspectorate recommended that the Provincial People's Committee direct relevant departments and localities to urgently coordinate in determining land prices to conduct compensation, site clearance for the remaining area of the project and handle responsibilities for related collectives and individuals.

Duy Tuấn
RELATED NEWS

Publicly publicizing the inspection conclusion of 6 units under the Hanoi Police

|

At the end of the inspection, Hanoi City Police issued inspection conclusions to relevant units for implementation.

Close-up of a series of coastal projects in Lam Dong subject to inspection

|

Lam Dong - A series of projects are on the list of thematic inspections in coastal areas of the province.

Promoting the potential, intelligence and creativity of female union members and workers

|

According to President of the Vietnam General Confederation of Labor Nguyen Dinh Khang, the success of the emulation movement "Good at public work, good at housework" and the typical examples of female union members are motivation for the Vietnam Trade Union to continue to innovate the content and methods of operation, promote the potential, intelligence and creativity of female union members and workers in the new period.

Updated gold price at the end of the session on October 15: Increased to 5.7 million VND/tael after one day

|

Updated gold price at the end of the session on October 15: All increased. In the country, some units adjusted the price up to 5.7 million VND/tael after just one day.

"More excellent" Ginkgo Biloba, the first vitamin to take advantage of marketing, easily causes misunderstanding

|

An advertisement by First Blood Trade Group believes that this product has outstanding effects when compared to the active ingredient Ginkgo Biloba EGB 761, which can easily deceive viewers.

Publicly publicizing the inspection conclusion of 6 units under the Hanoi Police

SÓNG HỮU |

At the end of the inspection, Hanoi City Police issued inspection conclusions to relevant units for implementation.

Close-up of a series of coastal projects in Lam Dong subject to inspection

Duy Tuấn |

Lam Dong - A series of projects are on the list of thematic inspections in coastal areas of the province.

5 dự án nhà ở xã hội, nhà ở cho công nhân đang triển khai ở Bình Thuận

Duy Tuấn |

Thời gian qua, tỉnh Bình Thuận phát triển nhà ở đa dạng các loại hình, trong đó chú trọng phát triển nhà ở xã hội, nhà ở cho công nhân các khu công nghiệp để giải quyết yêu cầu về nhà ở cho người lao động, người có thu nhập thấp khó khăn về nhà ở.