According to information on the socio-economic situation of Hai Phong City, by the end of February 2026, 24 industrial park infrastructure construction investment projects will basically closely follow the set progress. In which, the city focuses on urging 5 more projects to ensure the Q1 scenario, including Tien Thanh Industrial Park, Xuan Cau IP and non-tariff area; Thuy Nguyen IP (phase 1); Tien Lang airport IP (zone B) and Tran Duong - Hoa Binh IP (zone B).
In addition, the city also directed the People's Committees of communes and wards to accelerate the progress of site clearance for industrial park infrastructure construction investment projects in the area: Gia Loc Commune People's Committee, Gia Phuc Commune People's Committee (Hoang Dieu Industrial Park project); Duong An Commune People's Committee, Thuong Hong Commune People's Committee (Binh Giang Industrial Park project); Nguyen Binh Khiem Commune People's Committee (Tran Duong - Hoa Binh Industrial Park project, phase A phase 1 and Tran Duong - Hoa Binh Industrial Park project, zone B).
24 industrial cluster infrastructure construction investment projects are also basically closely following the progress. The city directs the People's Committees of communes and wards to focus on removing difficulties and accelerating site clearance for industrial cluster infrastructure construction investment projects in the area such as the People's Committees of Thien Huong and Le Ich Moc wards with the Thuy Nguyen mechanical and casting craft village industrial cluster project, the People's Committee of An Phong ward with the Le Thien Dai Ban industrial cluster project, the Trang Due supporting industrial cluster project; the People's Committee of An Quang commune to accelerate the progress of the Cua Hoat - Quan Thang industrial cluster project, the People's Committee of Lai Khe commune with the Cong Hoa industrial cluster project; the People's Committee of Cam Giang commune (Luong Dien commercial service industrial cluster project), the People's Committee of Nguyen Luong Bang commune with the Doan Tung 2 industrial cluster project; the People's Committee of Nam An Phu commune with the Thang Long industrial cluster project and the People's Committee of Quyet Thang commune with the Tien Cuong III industrial cluster project.
Regarding the goals and tasks for March and the following months, the city focuses on urging the commencement of construction according to the plan of 9 industrial parks.Among them, 5 industrial parks expected to start construction in the first quarter of 2026 are Ngu Phuc Industrial Park, Thuy Nguyen Industrial Park (phase 1), Nam Trang Cat Industrial Park, Binh Giang Industrial Park and Kim Thanh 2 Industrial Park.In addition, 4 industrial park projects including Nomura Hai Phong Industrial Park (phase 2); Tran Duong - Hoa Binh (Zone A) - Phase 1; Hoang Dieu; Tran Duong - Hoa Binh (Zone B) - Phase 1 are also being accelerated, preparing to start construction.
The city also urged the progress of 11 industrial park projects that have been started, including Trang Due 3 Industrial Park, Tien Lang 1 Industrial Park; Vinh Quang Industrial Park (Phase 1); Tien Lang Airport Industrial Park (Zone B); Luong Dien - Ngoc Lien Industrial Park; Hai Phong International Gateway Port Industrial Park; Tien Thanh Industrial Park; Tan Truong Expanded Industrial Park; Tan Trao Industrial Park (Phase 1); Xuan Cau IP and non-tariff zone and Kim Thanh IP.
The Chairman of the City People's Committee assigned the Economic Zone Management Board to urge and accelerate the progress of newly established and started industrial parks; port projects from No. 7 to 12 in Lach Huyen, especially site clearance, infrastructure investment and attracting secondary investors.