Lao Cai removes site bottlenecks for nearly 2,200 billion VND industrial park

Đinh Đại |

Lao Cai - By mid-June 2026, Au Lau ward has basically completed site clearance for the western area of the Tran Yen Industrial Park Project with a rate of 99.4%.

Au Lau Ward People's Committee has just organized a conference to summarize the site clearance work of the Tran Yen Industrial Park infrastructure construction and business investment project, assess the implementation results, remove difficulties and set out tasks for the coming time.

Immediately after implementing the two-level local government model from July 1, 2025, the People's Committee of Au Lau ward has received all project site clearance dossiers from the old Tran Yen district to organize implementation according to regulations.

Identifying this as a key project of important significance for socio-economic development of the locality and Lao Cai province, Au Lau ward has mobilized the entire political system to participate in implementation.

The Site Clearance Steering Committee was established, maintaining regular meetings to promptly remove arising difficulties and obstacles.

Khu công nghiệp Trấn Yên có quy mô gần 255ha, tổng mức đầu tư trên 2.184 tỉ đồng. Ảnh: Văn Đức
Tran Yen Industrial Park (Au Lau ward, Lao Cai province) has a scale of nearly 255ha, with a total investment of over 2,184 billion VND. Photo: Van Duc

In the process of implementation, the locality has organized more than 20 dialogue conferences with people and 168 thematic meetings to resolve existing issues related to compensation, support and resettlement.

Many officials and civil servants directly go to the grassroots level to propagate, mobilize, and create consensus among the people.

For the western area of the project, the recovered area is 109ha, affecting 165 households and organizations.

To date, the locality has completed the inventory of 100% of affected households, approved compensation funds of more than 212 billion VND. 163/165 households have handed over land, the cleared area reaches more than 108.4ha, equivalent to about 99.4%.

Along with that, the land allocation and land lease for more than 107.9ha has been completed to be handed over to the investor.

In the Eastern area, the recovered area is more than 145.6ha, affecting 260 households and organizations.

To date, the locality has inventoried 250 households, reaching over 96%, and at the same time continues to complete compensation, support and resettlement dossiers according to regulations.

The ward sets a goal to complete the compensation plan for eligible dossiers before August 1, 2026.

Khen thưởng các tập thể và cá nhân có thành tích xuất sắc trong công tác giải phóng mặt bằng Dự án Khu công nghiệp Trấn Yên giai đoạn I. Ảnh: Thanh Nghị
Rewarding collectives and individuals with outstanding achievements in site clearance for the Tran Yen Industrial Park Project phase I. Photo: Thanh Nghi

At the conference, delegates also pointed out many difficulties such as the large volume of dossiers, some dossiers not being handed over synchronously, lack of professional human resources, and problems with land origin and infrastructure in some resettlement areas that are not yet complete.

Concluding the conference, leaders of Au Lau ward requested to continue to promote mass mobilization, complete inventory dossiers, accelerate the progress of preparing compensation plans for the Eastern area, and at the same time coordinate with functional agencies and investors to remove obstacles to ensure project progress.

On this occasion, the People's Committee of Au Lau ward commended 3 collectives and 6 individuals with outstanding achievements in site clearance for the Tran Yen Industrial Park Project phase I.

Đinh Đại
RELATED NEWS

Series of industrial infrastructure expands Lao Cai's development space

|

Lao Cai - Many large-scale industrial park and cluster infrastructure projects are being implemented to create clean land funds and attract businesses to invest.

Overview of the Industrial Park worth over VND2,184 billion in Lao Cai that just broke ground

|

On August 19, Lao Cai province held a groundbreaking ceremony, starting the Tran Yen Industrial Park construction project phase I, with a total investment of more than VND 2,184 billion.

100-year-old stone bridge in Hai Phong had many ancient stone slabs stolen at night

|

Hai Phong - People reflect that the Dong Trang stone bridge in Ai Quoc ward was stolen many stone components, functional agencies have intervened to verify the incident.

101 years of Revolutionary Journalism accompanying the country, promoting innovation

|

The 101st anniversary of the Vietnamese Revolutionary Press Day contributes to affirming the journey of accompanying the nation and promoting innovation.

Long Thanh airport passenger terminal technical operation in September

|

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Apartment prices fall, cash flow shifts from residential land to apartments

|

Apartment prices have cooled down, while the trend of shifting from landed houses to apartments continues to increase thanks to affordable prices that are more suitable for real housing needs.

Hanoi residents gradually switch to green vehicles with new support policies

|

Hanoi - Hanoi residents are starting to switch to green vehicles after a new support policy, contributing to reducing emissions and protecting the urban environment.

Series of industrial infrastructure expands Lao Cai's development space

Đinh Đại |

Lao Cai - Many large-scale industrial park and cluster infrastructure projects are being implemented to create clean land funds and attract businesses to invest.

Overview of the Industrial Park worth over VND2,184 billion in Lao Cai that just broke ground

Văn Đức |

On August 19, Lao Cai province held a groundbreaking ceremony, starting the Tran Yen Industrial Park construction project phase I, with a total investment of more than VND 2,184 billion.