Au Lau Ward People's Committee has just organized a conference to summarize the site clearance work of the Tran Yen Industrial Park infrastructure construction and business investment project, assess the implementation results, remove difficulties and set out tasks for the coming time.
Immediately after implementing the two-level local government model from July 1, 2025, the People's Committee of Au Lau ward has received all project site clearance dossiers from the old Tran Yen district to organize implementation according to regulations.
Identifying this as a key project of important significance for socio-economic development of the locality and Lao Cai province, Au Lau ward has mobilized the entire political system to participate in implementation.
The Site Clearance Steering Committee was established, maintaining regular meetings to promptly remove arising difficulties and obstacles.

In the process of implementation, the locality has organized more than 20 dialogue conferences with people and 168 thematic meetings to resolve existing issues related to compensation, support and resettlement.
Many officials and civil servants directly go to the grassroots level to propagate, mobilize, and create consensus among the people.
For the western area of the project, the recovered area is 109ha, affecting 165 households and organizations.
To date, the locality has completed the inventory of 100% of affected households, approved compensation funds of more than 212 billion VND. 163/165 households have handed over land, the cleared area reaches more than 108.4ha, equivalent to about 99.4%.
Along with that, the land allocation and land lease for more than 107.9ha has been completed to be handed over to the investor.
In the Eastern area, the recovered area is more than 145.6ha, affecting 260 households and organizations.
To date, the locality has inventoried 250 households, reaching over 96%, and at the same time continues to complete compensation, support and resettlement dossiers according to regulations.
The ward sets a goal to complete the compensation plan for eligible dossiers before August 1, 2026.

At the conference, delegates also pointed out many difficulties such as the large volume of dossiers, some dossiers not being handed over synchronously, lack of professional human resources, and problems with land origin and infrastructure in some resettlement areas that are not yet complete.
Concluding the conference, leaders of Au Lau ward requested to continue to promote mass mobilization, complete inventory dossiers, accelerate the progress of preparing compensation plans for the Eastern area, and at the same time coordinate with functional agencies and investors to remove obstacles to ensure project progress.
On this occasion, the People's Committee of Au Lau ward commended 3 collectives and 6 individuals with outstanding achievements in site clearance for the Tran Yen Industrial Park Project phase I.