Reasons why Khanh Hoa disburses low public investment capital

Hữu Long |

Khanh Hoa - It is proposed that investors must commit to disbursement of capital in 2024 reaching 95% or more and take responsibility for not completing disbursement of the year plan.

Identify the causes of low capital disbursement

According to a report from the Department of Planning and Investment of Khanh Hoa province, the total capital plan for 2024 assigned by the Prime Minister to the locality is VND 8,269 billion.

By the end of June 2024, this locality has allocated a capital plan of 7,133 billion VND; Unallocated capital is 1,135 billion VND, of which 279 billion VND is unallocated from land use fees due to projects that have not completed investment procedures according to regulations and local government bonds that have not been issued. in 2024 is 855 billion VND.

By the end of June 30, the disbursement rate of the 2024 capital plan compared to the capital plan assigned by the Prime Minister reached 20.0%, lower than the average disbursement rate of the whole country (the general disbursement rate of the Prime Minister). The whole country in the first 6 months of 2024 reaches 29.39%). Compared to the actual capital plan assigned by Khanh Hoa province, the disbursement rate of the capital plan in 2024 reached 22.3%.

The disbursement results of the public investment plan in the first 6 months of the year are still slow due to the objective reason that the unissued local government bond capital is 855 billion VND. To date, Khanh Hoa province has decided not to issue bonds anymore.

Second, according to the provisions of the Law on Public Investment, new projects starting in 2024 are assigned annual capital plans after the competent authority decides to approve the investment project. Next, the project must carry out procedures for land acquisition and site clearance, which usually lasts 7-9 months... Therefore, disbursement of capital plans for projects usually starts at the beginning of the quarter. III onwards.

In addition, there is also a reason that the district-level human resources allocated to carry out compensation work in districts, towns and cities are still small compared to the increasing need for site clearance to serve projects.

Recommend that investors commit to disbursement of 95% or more

The subjective reason is that investment procedures and contractor selection are slow, affecting the project's disbursement progress.

Among them, there is a project assigned a large capital plan, which is the construction component project of the Road Project from National Highway 27C to Provincial Road DT 656 in Khanh Hoa province - connecting with Lam Dong province and Ninh Thuan province; Capital plan allocated is 500 billion VND, estimated disbursement by the end of June 2024 is only 2%; Up to now, the work of selecting construction contractors has not been completed.

Second, the current implementation of compensation and site clearance is facing difficulties due to the work of determining specific land prices for compensation and resettlement support at the district level being implemented very slowly..., affecting progress. disbursement of the project.

From the above facts, the Department of Planning and Investment recommends that Khanh Hoa Provincial People's Committee direct investors to commit to disbursement in 2024 reaching 95% or more and take responsibility for not completing disbursement of the year plan. .

Hữu Long
TIN LIÊN QUAN

Vì sao Quảng Ngãi giải ngân vốn đầu tư công thấp?

VIÊN NGUYỄN |

Tại kỳ họp thứ 25, Hội đồng nhân dân tỉnh khoá XIII, lãnh đạo tỉnh Quảng Ngãi cho hay, kết quả giải ngân vốn đầu tư công trong 6 tháng đầu năm 2024 vẫn còn thấp.

Bộ NN&PTNT đốc thúc Quảng Ngãi giải ngân vốn được bố trí

VIÊN NGUYỄN |

Bộ NN&PTNT bố trí vốn cho Quảng Ngãi để nâng cấp và mở rộng cảng cá Tịnh Hòa, TP Quảng Ngãi. Tuy nhiên, đến nay việc giải ngân vốn đang rất trì trệ do vướng mặt bằng.

Đắk Nông có trên 70 dự án vướng mắc, chậm giải ngân vốn đầu tư công

PHAN TUẤN |

Toàn tỉnh Đắk Nông hiện có trên 70 dự án đang vướng mắc, chậm giải ngân vốn đầu tư công. Trong đó, hiện có 7 dự án có tiến độ giải ngân dưới mức 5%.

Bác tin "lái đò Chùa Hương bị cắt suất sau khi đi hỗ trợ bão lũ"

KHÁNH AN |

Mạng xã hội hiện đang lan truyền thông tin nhiều lái đò Chùa Hương (Mỹ Đức, Hà Nội) sau khi chuyển đò đi cứu trợ vùng lũ bị cắt suất, không cho chèo đò phục vụ khách.

Lý do tiếp tục đề nghị truy tố cựu Bí thư TX Bến Cát

ĐÌNH TRỌNG |

Sau khi phục hồi điều tra, Cơ quan Cảnh sát điều tra Công an tỉnh Bình Dương đã hoàn tất điều tra, ra kết luận chuyển hồ sơ đề nghị truy tố cựu Bí thư TX Bến Cát.

Thủ tướng Israel tuyên bố mở rộng mục tiêu chiến sự ở Gaza

Thanh Hà |

Israel tuyên bố mở rộng mục tiêu trong cuộc chiến ở Gaza, bao gồm việc để những người Israel chạy trốn khỏi các khu vực gần biên giới Lebanon trở về nhà.

Thu nhập thấp, công nhân xoay xở lo chi phí đầu năm học

NGỌC DIỆP |

Để lo các khoản chi tiêu đầu năm học mới cho con, nhiều công nhân, người lao động phải tiết kiệm, xoay xở đủ mọi cách.

Gia hạn xác minh vụ luận án tiến sĩ bị tố đạo văn

PHÚC ĐẠT |

HUẾ - Đại học Huế vừa có thông báo liên quan đến vụ việc luận án tiến sĩ của trưởng phòng nghiên cứu khoa học bị tố đạo văn.