According to the decision, the investor implementing the project is Khanh Hai Land Co., Ltd. (Ninh Binh province).
The project is implemented in Yen Khanh commune, Ninh Binh province. The project implementation boundary is determined: the North borders Bai Dinh - Kim Son road; the South borders 481B road; the East borders 11m concrete road and cemetery; the West borders water ditch and agricultural land.
The investment objectives of the project are updated and supplemented with industry codes according to the Vietnam Economic Industry System (VSIC), including: real estate business; construction of civil engineering works; site preparation; installation of electrical systems; installation of water supply, drainage and wastewater treatment systems...
The project invests in building synchronous infrastructure, creating conditions to attract secondary investors to lease land for production, mechanical processing; processing agricultural, forestry and food products; production of building materials. Industries applying modern and advanced technology, not causing environmental pollution and capable of creating links with other industrial parks and clusters in the area are prioritized for attraction.
Regarding the implementation progress, the project must be completed within no more than 24 months from the date the State allocates land. It is expected that the project will be completed and officially put into operation by the end of the fourth quarter of 2028. The progress of capital contribution and capital mobilization of investors must ensure compliance with the project implementation progress.