On June 21, the Standing Committee of Phu Nghia Commune Party Committee, the Steering Committee for Site Clearance (GPMB) of the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section in the commune, organized a review of the progress of site clearance work in the form of field trips to 10 villages along National Highway 6 through the commune (starting point from Phu Yen village and ending in Pho Got village).
After actual inspection, working at the Phu Nghia Commune Economic Department, the Standing Committee of the Party Committee, the Steering Committee for Site Clearance of the project to renovate and upgrade National Highway 6 of the commune listened to the Commune Economic Department, the Hanoi Traffic Construction Investment Project Management Board report on the progress of site clearance work until June 20.
Accordingly, the whole commune has handed over 1,355/1,366 land plots within the project scope, reaching 99.8%.
Currently, there are still 11 land plots of 9 households and individuals that have not signed land handover minutes.
For the land plots that have been handed over, there are still more than 100 cases that have not completed the dismantling of works and architectural structures on the land.
At the conference, Mr. Tran Van Son - Vice Chairman of Phu Nghia Commune People's Committee reported on the development of a plan and implementation of a plan to organize coercion against cases of intentionally failing to comply with the handover of land according to regulations.
Mr. Duong Duc Hien - Deputy Director of the Hanoi Traffic Construction Investment Project Management Board also provided specific information on the compensation and support payment for households whose land is recovered; and proposed solutions to accelerate the dismantling progress of the remaining 116 households, striving to complete before June 30.

Speaking at the conclusion of the conference, Mr. Trinh Tien Tuong - Secretary of the Party Committee, Chairman of the Commune People's Council, Head of the Site Clearance Steering Committee for the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section in Phu Nghia commune emphasized that the time from now until June 30 is the final sprint to complete site clearance work to serve project construction.
Mr. Tuong requested the Vietnam Fatherland Front Committee of the commune, the Commune Police and the Party committees and authorities of the villages to continue to promote propaganda, mobilization, and persuasion for 11 households that have not handed over the land in order to create consensus and minimize the need to organize coercion.
For more than 100 households that have handed over land but have not dismantled the works, functional sectors need to focus on supporting people to move assets and organize dismantling to be completed before June 26.
For the Dong Phuong Yen market and Got market areas, the Commune Police and the Commune Investment - Infrastructure Project Management Board are assigned to coordinate in maintaining urban order, not allowing market meetings to arise within the GPMB area. The Commune People's Committee and the Commune Economic Department urgently implement the plan to allocate resettlement land to households that have been approved, ensuring the legitimate rights of the people.
With the drastic involvement of the entire political system, the close coordination between the investor, construction units and the consensus of the people, Phu Nghia commune is highly focused and determined to complete the site clearance of the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section on schedule, creating conditions for the project to be implemented synchronously soon, contributing to promoting socio-economic development of the locality and the region.