Progress of Vingroup's VND41,270 billion urban area project in Bac Ninh

Trần Tuấn |

Bac Ninh - Vingroup's urban area project in Kinh Bac ward, with a total planning of 277 hectares, reclaimed land from 1,423 households.

Currently in the site clearance phase

On September 7, in Kinh Bac ward, Mr. Vuong Quoc Tuan - Chairman of the People's Committee of Bac Ninh province - chaired a working session with relevant departments, branches, sectors and localities on the progress of projects south of the Cau River.

At the conference, Kinh Bac Ward People's Committee informed about the progress of site clearance (GPMB) for the new urban area project in the Northwest of Bac Ninh city (zone 1).

Accordingly, this project has a total planning of 277 hectares, reclaiming land from 1,423 households.

Currently, the first compensation and support plan has been approved by the meeting on August 15, 2025 with a reclaimed area of 35,879.7 m2.

However, about 118 hectares have not been handed over by the Gia Thuan Land Fund Development Center Branch for maps; 901 households have not received land reclamation notices, causing difficulties in implementing land acquisition.

Du an khu do thi moi phia Tay Bac thanh pho Bac Ninh (cu).
New urban area project in the Northwest of Bac Ninh city (old). Photo: Huu Thang

According to the reporter's investigation, the above project is invested by Vingroup Corporation, expected to be implemented in 7 years, operating from 2032. The project is adjacent to the Cau River and the existing residential area, the project planning area is mainly residential land, agricultural land, ponds and lakes.

According to the plan, the urban area will have about 60 hectares of land to build houses, providing nearly 3,500 villas, 4-storey townhouses and a maximum of 35 apartment buildings.

The project is also allocated 9.5 hectares of land to develop social housing.

Some other items include service works, offices, parks, health stations, inter-level schools, sports areas, etc.

The total investment capital of the project is about VND 41,270 billion (equivalent to USD 1.58 billion), including compensation and support costs for site clearance of more than VND 1,100 billion.

Also at the above conference, localities also reported on the progress of site clearance for a number of other projects such as: DT.277B connecting to Ha Bac 2 bridge, Ring Road 4 (in Kinh Bac ward), investment project to build H2 route, Investment project to build emergency treatment works for landslides in the riverbank area from K49+300÷K49+430 of the bridge's right dike...

Projects better serve people's living conditions, for common development

Chairman of the People's Committee of Bac Ninh province Vuong Quoc Tuan affirmed that in recent times, especially after the newly put into operation of Bac Ninh province, provincial leaders and localities have focused on directing strongly in the field of socio-economic development, especially implementing investment projects to build infrastructure, urban areas, and services, to create space and momentum for the development of the province.

However, many projects are still behind schedule and planning, the main reason being the lack of close coordination between investors and local departments and branches. A part of the people are not fully aware, so they do not agree or support.

Toan canh buoi lam viec
Mr. Vuong Quoc Tuan spoke at the meeting. Photo: Huu Thang

Mr. Vuong Quoc Tuan requested all localities and units to focus on directing more drastically, realizing the Resolution of the Party Congresses of communes and wards and the Resolution of the Provincial Party Congress for the 2025 - 2030 term, with the goal of building Bac Ninh into a centrally-run city before 2030.

The steps and implementation processes of construction investment projects are all implemented seriously and in accordance with regulations, but many projects are still most stuck in the compensation and site clearance stages. The province's viewpoint is to make the most of the provisions of the law on support policies for the people.

The Chairman of the People's Committee of Bac Ninh province requested localities to strengthen propaganda and mobilization work for people, support construction investment projects, and create consensus in society.

"Households must clearly identify that investing in the construction of infrastructure, urban and service projects is mainly to better serve the living conditions of the people, for the common development of the locality, the province and the country" - Chairman of the People's Committee of Bac Ninh province Vuong Quoc Tuan emphasized.

Trần Tuấn
RELATED NEWS

Discovering cases of buying social housing for the wrong subjects in Bac Ninh

|

Bac Ninh - Through the investor's review, a case of buying social housing for the wrong subjects was discovered.

Ensuring security and order in a ward with 110,000 people temporarily residing in Bac Ninh

|

Bac Ninh - Nenh Ward is identified as a key area for industrial development in Bac Ninh province.

Audiences brave the rain to watch the final night of the concert "Anh trai vu ngan cong gai"

|

On the afternoon of September 7, despite the sudden rain in Ho Chi Minh City, thousands of audiences still carried the rain to watch the final night of the concert "Brother overcoming thousands of obstacles".

Closely monitoring each fishing trip to the wharf, Tran De Fishing Port contributes to removing the yellow card

|

Can Tho - Tran De Fishing Port is always bustling with boats coming and going, but all activities are strictly monitored, contributing to removing the EC "yellow card".

Deputy Prime Minister Tran Hong Ha inspects the progress of the Long Thanh airport project

|

Dong Nai - Deputy Prime Minister Tran Hong Ha inspected the progress and presented gifts to encourage officers, engineers and construction workers at the Long Thanh airport project.

Russia airstrikes Kiev, Ukrainian government building catches fire

|

Drone and missile strikes caused a major fire in central Kiev, including the Ukrainian government building, killing many people.

Vinh Tuy Bridge is still flooded with cars and motorbikes after the fire at the parking lot

|

Hanoi - After the fire, many other locations under Vinh Tuy Bridge were still flooded with cars, motorbikes, and factories, accompanied by the risk of fire and explosion that could occur at any time.

Discovering cases of buying social housing for the wrong subjects in Bac Ninh

Trần Tuấn |

Bac Ninh - Through the investor's review, a case of buying social housing for the wrong subjects was discovered.

Ensuring security and order in a ward with 110,000 people temporarily residing in Bac Ninh

Vân Trường |

Bac Ninh - Nenh Ward is identified as a key area for industrial development in Bac Ninh province.

Chủ đầu tư báo cáo vụ NOXH ở Bắc Ninh bàn giao 10 năm chưa có sổ hồng

Trần Tuấn |

Bắc Ninh - Chủ đầu tư đã có báo cáo liên quan phản ánh của người dân về dự án nhà ở xã hội bàn giao 10 năm chưa có sổ hồng.