HCMC reclaims 27.8 hectares of land to build 12.5 km of Thu Bien - Dat Cuoc road

ĐÌNH TRỌNG |

HCMC - Branches of the Land Fund Development Center are coordinating with localities to clear land and reclaim land to build the Thu Bien - Dat Cuoc road.

According to the Ho Chi Minh City People's Committee, the Thu Bien - Dat Cuoc road site clearance project (additional) is 12.5 km long. The recovered land area is about 27.8 hectares, affecting 165 cases. The project passes through Thuong Tan commune and Tan Uyen ward. Of which, the project passing through Tan Uyen ward is about 5.2 km long, with a total of about 63 households and organizations affected.

In 2025, Ho Chi Minh City has allocated 549 billion VND to implement the site clearance compensation project. Currently, the units have completed the issuance of land reclamation notices, investigation, survey, measurement, and inventory.

Regarding land prices, the People's Committees of localities have issued them. Currently, there are over 50 cases where compensation plans have been approved with a disbursed amount of about 80 billion VND.

Branches of the Land Fund Development Center are coordinating with the People's Committees of Tan Uyen Ward and Thuong Tan Commune to mobilize people to agree to hand over the site to get clean land for the Thu Bien - Dat Cuoc road construction project.

Tuyen duong xuong cap. Anh: Dinh Trong
The Thu Bien - Dat Cuoc route is degraded. Photo: Dinh Trong

According to records, the Thu Bien - Dat Cuoc road is currently damaged in many sections. The road surface is deformed, many deep holes appear... The Ho Chi Minh City Department of Construction has issued an official dispatch requesting relevant units to handle the points with deep holes, restore the road surface to be flat, ensuring safety for people traveling.

ĐÌNH TRỌNG
RELATED NEWS

Hot Saigon: Land reclaimed from nearly 600 households to implement a project to expand roads and build parks

|

Hot Saigon News on December 9: Land recovered from nearly 600 households to implement a project to widen roads and build parks; Forecast of increased thunderstorms in the South from tomorrow;...

Progress of site clearance and construction of 46km of highway in Ho Chi Minh City

|

HCMC - After nearly 1 year of construction, the HCMC - Thu Dau Mot - Chon Thanh expressway project, the section through Binh Duong, has not yet had enough construction site.

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

|

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.

Vietnam vs Myanmar women's football match schedule at SEA Games 33

|

The Vietnam women's team will face Myanmar in the final match of the 33rd SEA Games group stage, taking place at 4:00 p.m. on December 11.

Chairman of Son Hai Group raised problems with land obligations in Quang Tri

|

At the 5th session of the Quang Tri Provincial People's Council, Chairman of the Board of Members of Son Hai Group raised many problems arising from land obligations in the province.

Salary statement for the entire company when applying for CT3 Kim Chung social housing - unreasonable requirement

|

Hanoi - People submitting documents at the CT3 Kim Chung social housing project said that they were required to present the salary table of the entire agency.

Live SEA Games 33 today (December 10): Vietnamese sports delegation takes part

|

Live updated competition events of Vietnamese sports at today's 33rd SEA Games (December 10).

Hot Saigon: Land reclaimed from nearly 600 households to implement a project to expand roads and build parks

NGỌC ÁNH - CHÂN PHÚC |

Hot Saigon News on December 9: Land recovered from nearly 600 households to implement a project to widen roads and build parks; Forecast of increased thunderstorms in the South from tomorrow;...

Progress of site clearance and construction of 46km of highway in Ho Chi Minh City

ĐÌNH TRỌNG |

HCMC - After nearly 1 year of construction, the HCMC - Thu Dau Mot - Chon Thanh expressway project, the section through Binh Duong, has not yet had enough construction site.

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

ĐÌNH TRỌNG |

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.