On July 22, as noted by a reporter from Lao Dong Newspaper, at the location of electric pole No. 171 of the 500kV circuit 3 line project in My Lam village, Cam My commune (Cam Xuyen district), there were about 30 engineers and workers training. Working on high scaffolding to pull electric wires.
Bui Van Quyen (born 1981, native of Hoa Binh province) - a worker of Song Da Construction and Services Joint Stock Company - said that his team has been constructing and erecting electric pole No. 175 for a long time, but after completing After more than a week, reinforcements were deployed to column 171 to install scaffolding and pull electric wires here.
Also according to Mr. Quyen, the position of pole number 175 on the hill has not yet been pulled, but the position of pole next to pole number 174 has been pulled to pole position 172. At pole number 170 down in the plain, next to pole number 171 also pulled the rope.
“Pillar number 171 is preparing to pull the wire. This is the connection position between the two adjacent columns that have already pulled the wire. Therefore, today, our brothers are focused on mobilizing construction work at column number 171" - Mr. Quyen shared.
Also according to Mr. Quyen, this time the progress pressure is not as intense as before June 30, but progress is still accelerated. In the morning, wire pulling construction on the construction site begins at 6:00 a.m., until 11:30 a.m. for lunch. In the afternoon, work from 2:00 p.m. until the sun goes down completely before taking a break.
Here are some pictures of construction workers erecting scaffolding to pull electric wires on a 500kV circuit line project in Ha Tinh: