Thanks to the efforts of the staff and workers of the 1st and 2nd Electromechanical Workshops, all items have been shortened by 18 days compared to the schedule, while still ensuring technical requirements and labor safety.
The project includes 2 main fans FBCDZ-10-N°32/2x400, a system of fan station control cabinets, bientors, 6kV power distribution cabinets and many accompanying items such as power distribution houses, wind ditches, fan station infrastructure...
The units have completed the dismantling of the main FBCDZ-10-N°32/2x400 fan station at MB+35 and transported and installed it into the MB+32 secondary well gate of Khe Cham II-IV mine.
The project put into operation contributes significantly to ensuring mine ventilation, effectively serving the process of digging and exploiting coal from the Khe Cham II-IV mine to 350. Thereby, improving microbiological conditions, improving a safe working environment for workers, while increasing exploitation productivity, meeting the need to expand production.
With this result, the Electromechanical Workshop 1 and 2 have successfully completed the emulation goal assigned by the Company, actively contributing to the implementation of production and business targets of Ha Long Coal Company - TKV.