The fate of a dormitory worth over VND860 billion abandoned for 15 years

NGUYỄN TRƯỜNG |

Ninh Binh - The concentrated student dormitory project started construction in 2009, and up to now, after 15 years, this project is still unfinished and abandoned.

According to the investigation of Lao Dong Newspaper, the Ninh Binh Province Concentrated Student hostel Project was approved by the Provincial People's Committee in Decision No. 1015/QD-UBND dated September 4, 2009. The project has started construction to accommodate more than 7,600 students of colleges and universities in Ninh Binh province. Up to now, after 15 years of construction, this project is still unfinished and abandoned, causing waste.

The project is invested in construction on an area of 11.29 hectares (in Hoa Lu city) invested by the Department of Construction of Ninh Binh province with 4 5-storey buildings and other auxiliary works. The total investment of the project is over 860 billion VND, of which 835 billion VND is used for government bonds, the rest is the local budget, the project completion time is in 2013.

Immediately after the Ninh Binh Provincial People's Committee issued the approval decision, the investor quickly started implementing the project. However, by the end of 2013, the Government bond capital had stopped being provided for the project, and at the same time, implementing the Prime Minister's directive and the direction of the Ninh Binh Provincial People's Committee on controlling outstanding debts in basic construction, this project had to stop implementation to wait for capital allocation.

Present at the Ninh Binh Province Concentrated Student hostel Project area on March 12, according to Lao Dong reporters, the contractor has basically completed the rough construction of 4 5-storey buildings (A, B, C, D); basically finished the placement of 2 buildings A, D and 2/3 of building B.

In the project area, weeds grow wildly, moss covers the walls of all 4 rows of houses, many completed construction items are seriously degraded...

On March 7, the People's Committee of Ninh Binh province held a conference to listen to reports on the plan and results of the implementation to remove and resolve difficulties and problems in the Ninh Binh Province Concentrated Student dormitory construction project (phase I).

After listening to the reports and opinions of relevant units, on behalf of the People's Committee of Ninh Binh province, Mr. Pham Quang Ngoc - Chairman of the Provincial People's Committee concluded, basically agreeing with the proposed plan of the Department of Construction, in which it is expected to continue to use 2 blocks of houses A and D as dormitories to serve the needs of students and supplement public duties for lecturers, teachers, leasing to civil servants, public employees, employees, and workers of agencies, units and enterprises subject to investment attraction in the province.

Use blocks B and C to serve medical purposes (hospital examination, treatment and treatment facilities). The remaining land plot (6.79ha) is assigned to the People's Committee of Hoa Lu city to manage and organize implementation according to the plan.

The conclusion of the Chairman of Ninh Binh Provincial People's Committee stated: Ninh Binh Provincial People's Committee identified this as an important task, which needs to be highly focused on and completed soon. To have a full basis to report to the Provincial Party Committee Standing Committee and the Provincial Party Committee Standing Committee on the handling plan, ensuring suitability and feasibility. The People's Committee of Ninh Binh province requested the Department of Construction and related units to continue to focus on reviewing, researching, clarifying related issues and reporting to the People's Committee of Ninh Binh province in March 2025.

NGUYỄN TRƯỜNG
TIN LIÊN QUAN

Vingroup wants to build a 250km/h metro line from District 7 to Can Gio

|

HCMC - Vingroup Corporation proposed to invest in a 48.7km long elevated metro line, a speed of 250km/h connecting District 7 to the Can Gio coastal urban tourism project.

Nam Nghiep ancient paint flower forest attracts visitors in the most beautiful season

|

Son La - Nam Nghiep village (or Nam Nghiep), Ngoc Chien commune is in the most beautiful mountainside flower season in recent years when flowers bloom evenly.

Effectively organize patriotic emulation movements

|

On March 20 in Ninh Binh, the Central Emulation and Reward Council summarized the Emulation Bloc of Socio-political Organizations and the Lien minh 2024.

The billion-dollar hospital in Can Tho is stuck, who is responsible?

|

Can Tho - The Can Tho City Oncology Hospital project with a total capital of more than 1,700 billion VND has been stuck for many years and is still not completed, while the current Oncology Hospital is always crowded with patients.

Special training class of the Russian army

|

Russian forces are organizing UAV control training in the rear area of the special war zone.

Quang Nam refuses to give away free tickets for visitors to cultural exchanges

|

Quang Nam - The proposal to offer free admission to visitors to Hoi An's cultural exchange events has been rejected by Quang Nam province.

It is not surprising that the Vietnamese team will have difficulty against Cambodia

|

Cambodia is a weak opponent but it is not surprising that the Vietnamese team encountered many difficulties in the friendly match on the evening of March 19.

Công viên 1,7ha bỏ hoang ở Hà Nội thành bãi đỗ xe

KHÁNH AN |

Hà Nội - Sau nhiều năm bỏ hoang, Công viên Mặt Trời Mới (quận Tây Hồ) được chuyển công năng thành bãi đỗ xe.

Số phận của Bệnh viện Sản - Nhi Ninh Bình sau nhiều năm bỏ hoang

NGUYỄN TRƯỜNG |

Ninh Bình - Sau nhiều năm bỏ hoang, gây lãng phí, tỉnh Ninh Bình đã quyết định chuyển giao Bệnh viện Sản - Nhi (cũ) cho 3 đơn vị khác sử dụng.

Loạt ki ốt bỏ hoang lãng phí tại khu đô thị ở Long Biên

KHÁNH AN |

Hàng loạt ki ốt tầng 1 của Khu đô thị Việt Hưng (phường Giang Biên, quận Long Biên, Hà Nội) hiện đang bỏ hoang lãng phí.