Project to invest in construction and business of repair and maintenance services for vehicles, aviation equipment and commercial ground service No. 1 at Long Thanh International Airport.
Investment project for construction and business of repair and maintenance services for vehicles, aviation equipment and ground commercial technical services No. 2 at Long Thanh International Airport.
The investment objective is to build, provide and sell repair and maintenance services for aviation vehicles and equipment and ground commercial technical services, meeting the airport's operating requirements. Long Thanh international.
Regarding investment scale: Works to serve the repair and maintenance of vehicles and aviation equipment and works to serve the operation and cleaning of aircraft; auxiliary items, synchronous technical infrastructure; Invest in equipment to serve production and business.
Project implementation location: Areas E-07 and E-11 at Long Thanh International Airport. 6. Current status, area, and purpose of land use.
The Ministry of Transport said that the current land use status: The land area has been cleared; The land use right certificate has been issued to the Southern Airport Authority.
The detailed area of land for project implementation is as follows:
Construction investment project and business of repair and maintenance services for vehicles, aviation equipment and ground commercial technical services No. 1 with an area of about 7,045 m2.
Construction investment project and business of repair and maintenance services for vehicles, aviation equipment and ground commercial technical services No. 2 with an area of about 7,045 m2.
Project implementation deadlines and progress are as follows:
Project implementation progress is expected to be about 18 months (from the effective date of the project contract).
The project implementation period is about 24 years and 08 months (from the date of completion of investment.
The bidder is the Vietnam Aviation Administration.
Form of investor selection: Open domestic bidding.
Investor selection method: One stage, one envelope.
Time to start organizing investor selection: Third quarter, 2024
The tracking table for 2 projects is as follows: