There is still 1 month left to hand over enough land to expand Tam Trinh Street

HỮU CHÁNH |

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

The project to expand Tam Trinh Street (Hoang Mai District, Hanoi) with a length of 3.5km started in 2016, expected to be completed after 3 years. However, due to many difficulties in site clearance (GPMB), the project was stalled.

By July 2024, Hoang Mai district handed over about 800m of clean land to the contractor to implement the project. However, the allocated site was not seamless, causing many difficulties for the project implementation process.

a
A section of Tam Trinh Street is under construction and expansion. Photo: Huu Chanh

According to the People's Committee of Hoang Mai District, to implement the project, the locality must reclaim over 54,000 m2 (after adjusting the boundary), involving about 1,590 households and 20 organizations in the three wards of Mai Dong, Hoang Van Thu and Yen So.

Up to now, the site clearance work has not been completed because the locality still faces some difficulties and problems that need to be resolved.

The Standing Committee of Hoang Mai District Party Committee has decided to postpone the handover deadline for the Tam Trinh road project by 30 days, ending before April 30, 2025.

Thus, the site clearance work of this project has changed the completion time frame four times: September 30, 2024; December 31, 2024; March 31, 2025 and now April 30, 2025.

a
Many works on Tam Trinh Street have not been dismantled and the site has been handed over to the project. Photo: Huu Chanh

To speed up the progress of the site clearance for the Tam Trinh road expansion project, the Hanoi Department of Natural Resources and Environment (now the Department of Agriculture and Environment) has proposed that the City People's Committee consider and approve another support plan according to the proposal of the Hoang Mai District People's Committee for households subject to land acquisition.

Regarding resettlement support for people, the People's Committee of Hoang Mai district proposed a period of support for renting houses from the time the households handed over the site to the date of completion of the repair and handover of the houses to the households.

The People's Committee of Hoang Mai District proposed that the city approve other support levels for 30 households that have approved the plan, drawn lots for apartments and households preparing for approval, and drawn lots for resettlement houses at the same level (equivalent to the temporary housing support level prescribed in Article 17 of Decision 56/2024 of the city).

With this proposal, after consulting with departments and branches, the Department of Agriculture and Environment proposed that the City People's Committee assign the Hoang Mai District People's Committee to coordinate with the Department of Construction to review and report to the City People's Committee for consideration and permission to change the resettlement housing fund to arrange resettlement for households before making and approving the plan and reclaiming land according to regulations.

While waiting for resettlement arrangements, Hoang Mai District People's Committee will provide temporary housing support according to the provisions of Article 17 of Decision No. 56/2024/QD-UBND.

a
The allocated site is not seamless, making it difficult for the contractor to construct. Photo: Huu Chanh

Regarding the property compensation support policy, the People's Committee of Hoang Mai district said that the project has 786 households subject to land acquisition. Of which, 381 households with illegal housing and assets attached to land have had their compensation, support and resettlement plans approved under Decision No. 10.2017; and 405 households using land have not yet approved their compensation, support and resettlement plans.

The People's Committee of Hoang Mai District proposes that the city consider the level of support for cases that are not eligible for compensation for construction works and houses.

In case the provisions of the 2024 Land Law are more beneficial to people whose land is recovered, it is allowed to adjust the plan according to the 2024 Land Law.

After consulting with departments and branches, the Department of Agriculture and Environment proposed that the City People's Committee approve other support policies as proposed by the Hoang Mai District People's Committee.

At the same time, the People's Committee of Hoang Mai District was assigned to review the time of announcing land recovery for cases where compensation, support and resettlement plans have not been approved; approve other support plans for cases that do not meet the conditions for compensation for works and housing for households (not yet approved) similar to other previous support policies.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi begins construction of nearly VND2,400 billion intersection

|

Hanoi - The project of the different level of the intersection between Ring Road 3.5 and Thang Long Avenue, with an investment capital of nearly VND 2,400 billion, has begun construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

|

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.

Hanoi is about to build two new routes 30-65m wide

|

Hanoi is about to build 2 routes in Hoang Mai and Thuong Tin districts with cross-sections of 30m and 65m respectively.

Rescuing 11 students in Hoa Binh trapped in a stream after heavy rain

|

Hoa Binh - While swimming in a stream, 11 students in Hoa Binh City suddenly encountered heavy rain, rising water, causing them to get stuck in the rushing water.

What did Nick Ut say before the copyright dispute of the famous photo Napalm Baby

|

Author Nick Ut spoke out after organizing the World Press Photo to stop recording him as the author of the photo " Napalm Baby".

People suffer because the nearly 10 billion VND traffic road project has been suspended

|

Lam Dong - The Lac Long Quan road project in Bao Loc city is temporarily suspended, becoming a problem, making it difficult for people to move.

Hanoi Metro admits the mistake of passengers having to cover themselves when taking the Cat Linh - Ha Dong train

|

Hanoi - Cat Linh - Ha Dong electric train experienced a phenomenon of water flowing to regulate the air on the passenger car.

Latest information on the second session of negotiations on Vietnam - US tariffs

|

The 2nd negotiation session of the Bilateral Agreement on Comparative Trade between Vietnam and the United States will be held from May 19-22, 2025 in Washington, D.C., United States.

Hanoi begins construction of nearly VND2,400 billion intersection

SÓNG HỮU - KHÁNH LINH |

Hanoi - The project of the different level of the intersection between Ring Road 3.5 and Thang Long Avenue, with an investment capital of nearly VND 2,400 billion, has begun construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

HỮU CHÁNH |

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.

Hanoi is about to build two new routes 30-65m wide

HỮU CHÁNH |

Hanoi is about to build 2 routes in Hoang Mai and Thuong Tin districts with cross-sections of 30m and 65m respectively.