Provincial Road 414C workers work through holidays to meet schedule

CÔNG HÒA |

To open Provincial Road 414C through Ba Vi District (Hanoi) to technical traffic in October 2024, workers are working overtime and holidays to keep up with the project's progress.

Work hard day and night

According to Lao Dong Newspaper, during the National Day holiday on September 2, under the scorching sun at the construction site of the project to upgrade and expand Provincial Road 414C, workers were still working to complete the project soon.

Mr. Nguyen Cong Thanh - Driver Team of Quang Tay Joint Stock Company confided that he works at a construction site far from home so he always misses his wife and children, but still tries to put work first to ensure the project's progress.

According to Mr. Thanh, his hometown is in Quang Nam, more than 800km away, and his economic conditions are still difficult, so he has not returned home to visit his family for nearly a year. He stayed to work to earn more income and save on travel expenses.

"There is only about 1 month left until the road is completed, I can reunite with my family, so it's okay if I don't go home this holiday," Thanh shared.

Workers work in shifts to complete the project according to plan. Photo: Hoang Loc
Workers work overtime to complete the project according to the plan. Photo: Hoang Loc

Mr. Phung Tien Sinh - Rock pouring team of Quang Tay Joint Stock Company said that when it rains, the construction roads become slippery due to mud and soil, making it unsafe for road users.

"There have been a few cases of falling off motorbikes, but only minor scratches. At that time, the workers always encouraged each other and tried to speed up the construction to soon complete Provincial Road 414C," Mr. Sinh added.

Mobilize maximum human resources to speed up the project

Mr. Nguyen Duc Luong - Technical Officer of the Project to renovate and expand provincial road 414C under Quang Tay Joint Stock Company said that workers on holidays, in addition to receiving salary, also receive bonuses and allowances according to regulations.

According to Mr. Luong, all workers unanimously participated in labor even on holidays, to soon complete the project on schedule.

“Currently, the project has completed more than 90% of the work volume. All workers at the construction site continue to maintain their enthusiastic working spirit to ensure technical traffic opening in October 2024, completing the entire route by the end of 2024,” Mr. Luong added.

Workers work overtime to complete the sidewalk of Provincial Road 414C through Ba Vi District, Hanoi. Photo: Hoang Loc
Workers work overtime to complete the sidewalk of Provincial Road 414C through Ba Vi District, Hanoi. Photo: Hoang Loc

According to Mr. Nguyen Ngoc Manh - Director of Ba Vi District Project Management Board, the construction unit is currently focusing on the seamless renovation of the entire Provincial Road 414C, while repairing and upgrading degraded areas.

"Completing the project on schedule will not only help upgrade the transport infrastructure but also meet the expectations of local people after a long period from 2022 to present," Mr. Manh added.

The project to renovate and expand Provincial Road 414C is more than 8km long, with a total investment of more than 276 billion VND, and will start construction in October 2022. It is expected to open to technical traffic in October 2024.

CÔNG HÒA
TIN LIÊN QUAN

Tăng ca để kịp thông xe kỹ thuật Tỉnh lộ 414C vào tháng 10

HOÀNG LỘC - CÔNG HÒA |

Công nhân thi công Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) thực hiện 3 ca, 4 kíp bất kể ngày đêm để thông xe kỹ thuật vào tháng 10.2024.

Người dân Ba Vì vất vả khi qua Tỉnh lộ 414C

CÔNG HÒA |

Dự án nâng cấp Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) vướng giải phóng mặt bằng nên thi công không liền mạch, khiến việc đi lại của người dân gặp nhiều khó khăn.

Dự án nâng cấp Tỉnh lộ 414C hoàn thành vào cuối năm 2024

HOÀNG LỘC - CÔNG HÒA |

Dự án nâng cấp, mở rộng Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) hoàn thành đưa vào sử dụng vào cuối năm 2024 sau nhiều năm vướng giải phóng mặt bằng.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

Tăng ca để kịp thông xe kỹ thuật Tỉnh lộ 414C vào tháng 10

HOÀNG LỘC - CÔNG HÒA |

Công nhân thi công Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) thực hiện 3 ca, 4 kíp bất kể ngày đêm để thông xe kỹ thuật vào tháng 10.2024.

Người dân Ba Vì vất vả khi qua Tỉnh lộ 414C

CÔNG HÒA |

Dự án nâng cấp Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) vướng giải phóng mặt bằng nên thi công không liền mạch, khiến việc đi lại của người dân gặp nhiều khó khăn.

Dự án nâng cấp Tỉnh lộ 414C hoàn thành vào cuối năm 2024

HOÀNG LỘC - CÔNG HÒA |

Dự án nâng cấp, mở rộng Tỉnh lộ 414C qua huyện Ba Vì (Hà Nội) hoàn thành đưa vào sử dụng vào cuối năm 2024 sau nhiều năm vướng giải phóng mặt bằng.