Quang Tri airport project accelerates, still stuck with more than 20 hectares of land

HƯNG THƠ |

Quang Tri - Taking advantage of the dry weather at the end of November, units have stepped up construction of many items of the Quang Tri airport project.

In late November, the weather in Quang Tri has stabilized after a long period of flooding. At the construction site of the Quang Tri Airport Project (Quang Tri Airport Construction Investment Project), workers and many types of machinery are working continuously to compensate for the progress after the construction was stopped due to floods.

For the runway item, Mr. Bui Van Toan, construction manager of Cienco4 Group, said that the unit is spreading crushed stone against the top layer, preparing to test the spraying of cement concrete. The 2.4km long, 45m wide runway is currently about 20% complete and is expected to be completed before April 30, 2026.

Khoan coc xu ly nen yeu o du an san bay Quang Tri. Anh: Hung Tho
Drilling for depots to treat weak foundations at the Quang Tri airport project. Photo: Hung Tho

"The unit has arranged many construction teams and mobilized more vehicles to compensate for the interruption caused by floods" - Mr. Toan said.

Some locations on the runway have not been cleared, the contractor is taking advantage of the construction of the handed-over part such as drilling cement stones for weak foundation treatment. In the core area of the runway, there is still a church and a house that cannot be relocated because the locality has not completed resettlement.

In parallel with the runway, the units also focus on the construction of terminals, air traffic control towers and other technical items. The atmosphere at the construction site these days is urgent when the weather is favorable again.

Thi cong du an san bay Quang Tri. Anh: Hung Tho
Construction of the Quang Tri airport project. Photo: Hung Tho

Mr. Le Van Thong - Chairman of Cua Viet Commune People's Committee said that the locality has made efforts to hand over the site to serve the project. However, there are still 32 households that have not been resettled and more than 200 graves that have not been relocated.

"The Provincial People's Committee has agreed on the policy, the locality is urgently constructing the resettlement area to soon complete site clearance" - Mr. Thong said.

It is known that Quang Tri airport is being implemented under the PPP form with a total investment of about 5,800 billion VND, built in Cua Viet and Gio Linh communes. The airport is designed according to ICAO's 4C standard, capable of operating wide-body aircraft and performing level II military functions. In the first phase, the airport is expected to serve 5 million passengers per year. Up to now, Quang Tri province has handed over 245 hectares of land, and about 20 hectares of land are still stuck and need to be resolved.

Currently, some items of the airport project have been completed, including the aircraft parking lot and some connecting roads.

Phoi canh nha ga o du an san bay Quang Tri. Anh: Hung Tho
Perspective of the terminal in the Quang Tri airport project. Photo: Hung Tho

During the inspection on July 26, 2025, Prime Minister Pham Minh Chinh requested to speed up the progress of phase 1, and definitely complete the entire project by mid-2026. The Prime Minister also assigned the task of researching and developing the space around the airport into an aviation industrial park, airport urban area, high-tech industry; at the same time, perfecting the connecting infrastructure system to create momentum for regional development and expand connections with Laos and Thailand.

HƯNG THƠ
RELATED NEWS

The Prime Minister requested the completion of Quang Tri airport and Dong Hoi T2 terminal on April 30, 2026

|

Prime Minister Pham Minh Chinh requested Quang Tri and related units to strive to complete Quang Tri airport and Dong Hoi airport's T2 terminal by April 30, 2026.

Quang Tri airport project faces difficulties due to slow site clearance

|

Quang Tri - The price has not been agreed upon, the land origin is unknown and the resettlement area is not yet available, so the site clearance for the Quang Tri airport project has not been completed.

Hanoi Party Secretary requests drastic removal of urban bottlenecks

|

Hanoi - Hanoi Party Secretary Nguyen Duy Ngoc requests the Construction sector to thoroughly handle congestion, flooding, and urban bottlenecks.

Live football U23 Korea vs U23 Australia in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Korea and U23 Australia in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 17).

Live football Man United vs Man City in the Premier League

|

Live football match Man United - Man City in round 22 of the Premier League, taking place at 7:30 PM on January 17 (Vietnam time).

15-year traffic jam at the eastern gateway of Ho Chi Minh City is about to be removed

|

Ho Chi Minh City - The bottleneck on National Highway 1, the section of the new Mien Dong Bus Station - Tan Van, is expected to be expanded from the end of 2026, helping to eliminate traffic jams at the eastern gateway.

Excavation of an ancient tomb nearly 2,000 years old in Quang Ninh

|

Quang Ninh - During the excavation of an ancient tomb nearly 2,000 years old in Vang Danh, Quang Ninh province, many important artifacts were discovered.

3-year corporate income tax exemption according to Decree 20

|

3 years of corporate income tax exemption for small and medium-sized enterprises from the date of first issuance of the Enterprise Registration Certificate.

The Prime Minister requested the completion of Quang Tri airport and Dong Hoi T2 terminal on April 30, 2026

CÔNG SÁNG |

Prime Minister Pham Minh Chinh requested Quang Tri and related units to strive to complete Quang Tri airport and Dong Hoi airport's T2 terminal by April 30, 2026.

Quang Tri airport project faces difficulties due to slow site clearance

HƯNG THƠ |

Quang Tri - The price has not been agreed upon, the land origin is unknown and the resettlement area is not yet available, so the site clearance for the Quang Tri airport project has not been completed.

Dự án sân bay Quảng Trị sẽ giúp địa phương cất cánh bay lên

HƯNG THƠ |

Dự án đầu tư xây dựng Cảng hàng không Quảng Trị (sân bay Quảng Trị) đã chính thức khởi công xây dựng. Dự kiến dự án sẽ đi vào khai thác từ tháng 7.2026, đáp ứng nhu cầu vận tải đường hàng không ngày càng tăng cao, góp phần thúc đẩy phát triển chính trị, kinh tế, xã hội.